Presentation is loading. Please wait.

Presentation is loading. Please wait.

PRESENTATION OVERVIEW

Similar presentations


Presentation on theme: "PRESENTATION OVERVIEW"— Presentation transcript:

1

2 PRESENTATION OVERVIEW
Background Design Construction Operation Takeaways Questions

3 PROJECT BACKGROUND Crow Irrigation Project (CIP) work commenced 1885
Source: Crow Irrigation Project (CIP) work commenced 1885 US Reclamation Services: Up until 1922 Bureau of Indian Affairs: – present 11 units Surface water sources Source: Source:

4 PROJECT BACKGROUND

5 PROJECT BACKGROUND Condition Assessment Funding Implementation
Completed in 2005 and updated in 2007 Funding Crow Tribal Water Right Settlement Act of 2010 Implementation 638 Contract between Crow Tribe and Bureau of Reclamation

6 PROJECT DESIGN – EXISTING CONDITIONS
Reno Diversion Dam and Headworks: Diversion Dam 80 foot reinforced concrete sill with stoplogs Headworks Reinforced concrete structure 85 cfs design capacity Measurement Parshall flume Deficiencies: Safety Structural Operational

7 PROJECT DESIGN – EXISTING CONDITIONS

8 PROJECT DESIGN – EXISTING CONDITIONS

9 Mean Monthly Flows (CFS)
PROJECT DESIGN – EXISTING CONDITIONS Little Bighorn River: Monthly Mean Flows USGS Station Upstream River Channel Increasing upstream water surface comes with risk Source: US Geological Survey Mean Monthly Flows (CFS) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 135 188 299 298 614 839 264 117 126 152 149 131

10 PROJECT DESIGN – REQUIREMENTS
Divert water from Little Bighorn River Provide delivery water surface during low flows Handling flood flows Handling debris in river: Floating Sediment Measure water diversions Safety and O&M

11 PROJECT DESIGN – ALTERNATIVES
Diversion Dam Obermeyer gate Inflatable rubber dam system (rubber dam) Radial gate Concrete ogee crest Stoplogs Headworks Replacement Water Measurement Calibrate slide gates

12 PROJECT DESIGN – ADVANTAGES
Diversion Dam: Retain usable portion of structure Automation Handle flood flows Delivery water surface during low flows Rubber dam for floating debris Radial gate for sluicing sediment Minimal O&M in river and addresses safety concerns Headworks and Ramp Flume: New structures

13 PROJECT DESIGN – DISADVANTAGES
Diversion Dam: Higher initial cost Life expectancy for rubber bladder Requires power source Potential for damage Requires trained operators Headworks and Ramp Flume:

14 PROJECT DESIGN – RUBBER DAM vs. OBERMEYER GATE

15 PROJECT DESIGN – RUBBER DAM vs. OBERMEYER GATE
Rubber Dam Advantages: Lower initial cost Lower operating pressure (1-5 verses 15+ psi) Can handle minor leaks Debris bounces off Simplicity Can be patched in the field Obermeyer Gate Advantages: Protection from debris

16 PROJECT DESIGN – RUBBER DAM
PROJECT DESIGN – RUBBER DAM

17 PROJECT DESIGN – OBERMEYER GATE

18 PROJECT DESIGN – DIVERSION DAM & HEADWORKS
Rubber Dam: Single bladder/anchor system Maintain 3.35 foot water surface Inflate in 30 minutes PLC – based upstream water level control system Two pre-approved manufacturers: YOOIL Engineering HTE Engineering

19 PROJECT DESIGN – DIVERSION DAM & HEADWORKS
Radial Gate: Reinforced concrete sluiceway 10’ x 10’ radial gate with motor operator Headworks Reinforced concrete headworks Double 8’ x 6’ box culvert 72” x 60” stainless steel slide gates (2)

20 PROJECT DESIGN – DIVERSION DAM & HEADWORKS

21 PROJECT CONSTRUCTION – GENERAL
General Contractor: NW Construction, Bozeman, MT Rubber Dam Supplier: YOOIL Engineering, Goyang City, South Korea Controls: Thousand Hills, Port Ludlow, WA

22 PROJECT CONSTRUCTION – EQUIPMENT
Rubber Dam Single bladder/anchor system 30 year design life for rubber bladder 10 mm rubber, 3 mm EPDM outer cover Fins to deflect nappe Air Supply System Operating pressure: 1 – 1.5 psi Inflation time: 12 minutes 4” air supply line and 1” pressure sensing line Specific Components: Ring compressor Level pressure sensor and pressure transmitter Actuated butterfly valve

23 PROJECT CONSTRUCTION – EQUIPMENT
Controls: Manual Water Level Control Level pressure sensor < 0.1 feet ± target water level, no correction > 0.1 feet ± target water level, adjust every 5 minutes > 0.3 feet ± target water level, adjust continuously Pressure Control Mechanical safety system

24 PROJECT CONSTRUCTION – EQUIPMENT

25 PROJECT CONSTRUCTION – EQUIPMENT

26 PROJECT CONSTRUCTION

27 PROJECT CONSTRUCTION

28 PROJECT CONSTRUCTION

29 PROJECT CONSTRUCTION

30 PROJECT CONSTRUCTION

31 PROJECT CONSTRUCTION

32 PROJECT CONSTRUCTION

33 PROJECT CONSTRUCTION

34 PROJECT CONSTRUCTION

35 PROJECT CONSTRUCTION

36 PROJECT CONSTRUCTION

37 PROJECT CONSTRUCTION

38 PROJECT CONSTRUCTION - COMPLETION

39 PROJECT CONSTRUCTION - COMPLETION

40 PROJECT CONSTRUCTION - COMPLETION

41 PROJECT CONSTRUCTION - COMPLETION

42 PROJECT CONSTRUCTION - COMPLETION

43 PROJECT CONSTRUCTION - COMPLETION

44 PROJECT CONSTRUCTION - COMPLETION

45 PROJECT CONSTRUCTION - COMPLETION

46 PROJECT CONSTRUCTION - CHALLENGES
Dewatering Subgrade Downstream sill Air line routing Second pressure sensing line

47 PROJECT OPERATION Operation Power Outages Winter Future
Simple operation Radial gate operated regularly Power Outages Control panel reverts to manual mode Winter Managing ice Future Install UPS and incorporate telemetry

48 PROJECT TAKEAWAYS Importance of As-Built Drawings
Defining tolerances for maintaining water elevation Air line routing Power source Contractor experience

49 PROJECT DESIGN – REFERENCES
Design Standards No. 3 – Canals and Related Structures, Bureau of Reclamation Design of Small Dams, Bureau of Reclamation FlowMaster, V8i, Bentley HEC-RAS, US Army Corps of Engineers Water Measurement with Flumes and Weirs, ILRI Publication 58 Ramp flumes: .html

50


Download ppt "PRESENTATION OVERVIEW"

Similar presentations


Ads by Google