5th Review Committee October 4th, 2004 Facilities and Schedule C
5th Review Committee October 4th, Facilities and Schedule C. Sanelli
2
Buildings Entrance Tunnel
3
Entrance Tunnel
4
Works for Chimney (VVFF request)
5
Works for Chimney (VVFF request)
6
SPARC HALL, Laser Nave
7
SPARC HALL Clean Room
8
Electric power distribution system:
Public Tender: Published on the Italian Official Bulletin on September 21, Documentation to be sent before October 11, 2004.
9
Electric Distribution Lay-out
10
Laser Clean Room: Installed
Note: Anti-chamber (power supply room) ready to be ordered.
11
Water Cooling and Air Conditioning System:
Detailed Design: Completed Public Tender: Directors’ Board Authorization Requested on September 17, 2004
12
Cooling System Lay-out
13
Fire protection system: Tender Completed, Order ready, Works near to start.
Radiation protection system: Tender authorized and under way
14
next argument: Schedule Just a moment…..