Presentation is loading. Please wait.

Presentation is loading. Please wait.

Managing Project Risks and Opportunities

Similar presentations


Presentation on theme: "Managing Project Risks and Opportunities"— Presentation transcript:

1 Managing Project Risks and Opportunities
MGMT 412 Week 3 Chat

2 MGMT 440 Week 2 Chat

3 Scenario The design manager and the engineering manager were discussing with you the software tool they normally use for their design and engineering work. It is critical to their process, but there are some defects in the software that result in errors in the designs. MGMT 412 Week 3 Chat

4 Scenario The team knows how to find the errors and correct them, but it takes additional time during the design and engineering timeline. The managers just received an from the software vendor stating that a new version of the tool will be available right as the design tasks are expected to begin. MGMT 412 Week 3 Chat

5 Scenario Historically, the vendor is known to deliver the software about four weeks later than announced. The upgrade corrects the defects that the team knows about, as well as provides some new functionality that will make some of the engineering tasks faster. MGMT 412 Week 3 Chat

6 Scenario The vendor is strongly encouraging training for the design and engineering teams to use this new version. As the project manager, you must decide whether or not the team will use this new version of the software. The vendor is offering a 50% discount on the training if people are signed up within the next ten days. MGMT 412 Week 3 Chat

7 Scenario Answer the following questions:
What risks does this use of technology introduce to the project? What is the impact of each risk? What is the probability of each risk? Based on your understanding of the risks, will you tell the managers whether or not they should sign up their people for training? MGMT 412 Week 3 Chat

8 What risks does this use of technology introduce to the project?
MGMT 412 Week 3 Chat

9 Software Risks A list of potential software risks include:
Database complexity Development required Management ability Software complexity Software maturity System size Telecommunication aspects MGMT 412 Week 3 Chat

10 Suppliers & Sub-contractors Risks
Ability to deliver, skills, and quality of the software Accreditation Alternative suppliers and/or sub-contractors Availability Claims and variations Commercial terms Quality of goods and services provided Reliability of supplier Safety attitude Special considerations MGMT 412 Week 3 Chat

11 Suppliers & Sub-contractors Risks (cont.)
Control and supervision Cost of goods and services provided Delivery of goods and services provided Failure of a critical supplier and/or sub-contractor Flow-on conditions from prime contract Lead times for orders Limited number of suppliers or producers New or existing sub-contract Overseas versus local sub-contractors MGMT 412 Week 3 Chat

12 Suppliers & Sub-contractors Risks (cont.)
Stability of joint ventures and/or partnerships Timeliness Transferability of warrantees and/or guarantees Warranty of goods and services provided MGMT 412 Week 3 Chat

13 Technology Risks A list of technology risks include:
Availability of key components Failure rates Lack of technical knowledge Maintenance Need for further development New or non-standard performance Quality requirements MGMT 412 Week 3 Chat

14 Technology Risks (cont.)
Obsolescence Reliability, availability, maintainability Spare parts and support Specification does not reflect client needs Specification incomplete or misleading Technical standards or regulations change Technical standards or regulations unclear Technological change Technology not available MGMT 412 Week 3 Chat

15 What is the impact of each risk?
MGMT 412 Week 3 Chat

16 Cost, Schedule, and Performance Factors
Cost, schedule, and performance are what is impacted by risk. The impact probabilities include: 0.1 = Insignificant 0.3 = Low 0.5 = Medium 0.7 = Very High 0.9 = Catastrophic MGMT 412 Week 3 Chat

17 0.1 = Insignificant Cost Factor Schedule Factor Performance Factor
Budget estimates not exceeded, some transfer of money Negligible impact, slight schedule change compensated by available schedule slack Minimal or unimportant performance impacts MGMT 412 Week 3 Chat

18 0.3 = Low Cost Factor Schedule Factor Performance Factor
Project costs exceed budget by 1% to 5% Minor slip in project schedule, less than 1 month Small reduction in performance MGMT 413 Week 3 Chat

19 0.5 = Moderate Cost Factor Schedule Factor Performance Factor
Project cost estimates increased by 5% to 10% Small slip in project schedule from 1 to 3 months Some reduction in performance MGMT 412 Week 3 Chat

20 0.7 = Very High Cost Factor Schedule Factor Performance Factor
Project cost estimates increased by 10% to 20% Project schedule slip from 3 to 6 months Significant reduction in performance MGMT 412 Week 3Chat

21 0.9 = Catastrophic Cost Factor Schedule Factor Performance Factor
Project costs increased by more than 20% Large project schedule slip, key milestones not achieved Key performance criteria cannot be achieved MGMT 412 Week 3 Chat

22 Cost, Schedule, and Performance Factors
For each risk you will need to determine the following: Whether it is a cost, schedule, or performance factor Whether the impact is insignificant, low, moderate, very high, or catastrophic Read the number that ranges from 0 to 1 from the appropriate table, and then use that number in the succeeding calculations MGMT 412 Week 3 Chat

23 What is the probability of each risk?
MGMT 412 Week 3 Chat

24 Probability Factors They include: Maturity factors Complexity factors
Integration, interfacing, and dependency factors Commercial risk and management process factors MGMT 412 Week 3 Chat

25 Probability Factors Here are the actual probabilities that you will employ: 0.1 = Rare 0.3 = Unlikely 0.5 = Possible 0.7 = Likely 0.8 = Highly likely 0.9 = Almost certain MGMT 412 Week 3 Chat

26 Impact & Probability Factors
First, you will need to figure out which of the four (4) impact probabilities listed in the previous slides applies. Second, you will need to decide which one of the other six (6) probabilities to assign. Once you have made these two decisions, you have just about answered the question. In the last part of the question, will need to justify your selections. MGMT 412 Week 3 Chat

27 Based on your understanding of the risks, how will you tell the managers whether or not they should sign up their people for training. MGMT 412 Week 3 Chat

28 Risk Priority Matrix MGMT 440 Week 2 Chat

29 Recommended Formula there are two formulas that can be used to calculate the risk factor. The recommended equation is: RF = P + C – (P*C) where P = the selected probability and C = the selected consequence or impact value. MGMT 412 Week 3 Chat

30 Recommendation All you need to do is substitute the probability and impact factors selected into the equation on the previous slide, perform the calculation, and calculate the result. This will tell you whether or not the team members should or should not sign up for the training. MGMT 412 Week 3 Chat

31 Example It is obvious that the impact is an interfacing factor.
Suppose that you believe that it is unlikely that there will be only minor interfacing problems. Then, the probability value is 0.3, which is read off from the first column of the Table on slide 24 . MGMT 412 Week 3 Chat

32 Example Next, you will need to decide the impact factor.
Since going to training may impact the budget, create a minor slip in the schedule with possibly a small reduction in performance, the impact factor is 0.5. The last step is to substitute these two values into the equation. MGMT 412 Week 3 Chat

33 Example Here is the calculation: RF = P + C – (P * C)
= – (0.3 * 0.5) = 0.8 – 0.15 = 0.65 MGMT 412 Week 3 Chat

34 Example With a 0.65 probability of the training affecting the project schedule, you may come to the conclusion that the training is not worthwhile. This is not an unreasonable conclusion, and so you see how to address this discussion board question. MGMT 412 Week 3 Chat

35 Caveat Please note that your selection of probabilities may be different from my selection. I encourage you to review the example carefully, specify your own values, and then reach your own conclusions. Then you will have answered the question, and understand how to deal with this elusive issue called risk. MGMT 412 Week 3 Chat


Download ppt "Managing Project Risks and Opportunities"

Similar presentations


Ads by Google