1 LUSI MANAGEMENT OVERVIEW
Thomas Fornek Project Manager April 20-22, 2009

2 Provided Material Location Items
Items Project Management Documents PEP, Risk Registry, Schedules, Detailed Cost Estimate, February Monthly Report Procurement Documents APP Status Log, Statements of Work, Specifications Interface Control Documents Instrument Team Documents October meeting reports Update of CD-2 Responses to Recommendations Design Status Design Review Reports

3 PART 1 LUSI STATUS REVIEW

4 LUSI WBS Organization WBS TITLE 1.1 Project Management 1.2.
X-ray Pump Probe Instrument (XPP) 1.3 Coherent X-ray Imaging Instrument (CXI) 1.4 X-ray Correlation Spectroscopy Instrument (XCS) 1.5 Diagnostics and Common Optics (DCO) 1.6 Controls and Data Acquisition (CDA)

5 Project description (1)
Near Experimental Hall X-ray Transport Far Experimental Hall 1 3 2 4 5 6 XCSMono AMO SXR XPP XCS CXI H6 Part of LCLS Installation Part of LCLS FES ARRA Funds Beam Transport LCLS Offset Monochromator Exp. Chamber Detector LUSI H6

6 Project description (2)
CXI WBS 1.3 X-ray transport tunnel (200 m) XCS WBS 1.4 XPP WBS 1.2 LCLS SXR XCS Offset Monochromator WBS 1.5 H6 LCLS AMO

7 LUSI Integrated Project Team
DOE-HQ H. Kung, Acquisition Executive T. Brown, Program Manager DOE-SSO H. Joma DOE Federal Project Director DOE-SSO Support Instrument Team Leaders LCLS Directorate Support ES&H, QA, Finance, EVMS, Procurement… SLAC T. Fornek LUSI Project Manager Deputy – R.M. Boyce Technical Configuration Control Committee (Scope Decisions) Installation Manager B. Poling WBS 1.2 XPP IIT D. Fritz (Instr. Scientist) J. Langton ( Lead Eng) N. van Bakel (Detectors) WBS 1.3 CXI IIT S. Boutet (Instr. Scientist) P. Montanez ( Lead Eng) N. van Bakel (Detectors) WBS 1.4 XCS IIT A. Robert (Instr. Scientist) E. Bong (Lead Eng) N. van Bakel (Detectors) WBS 1.5 Diagnostics & Common Optics Y. Feng (Lead Scientist) E. Ortiz (Lead Eng ) WBS 1.6 Data Acquisition & Controls G. Haller (Lead) P. Anthony (Alternate)

8 LUSI Cost Baseline Baseline Oct 2008 February 2009 Base Cost (BCWS)
$42.10 M $42.37 M Contingency $13.00 M $12.73 M TEC $55.10 M OPC $4.90 M TPC $60.00 M

9 Interface/Stakeholder Management
Weekly LUSI Project Meetings Weekly Meetings with DOE-SSO Teleconferences every two weeks with DOE-HQ LCLS-SSRL Joint User’s Meeting in Oct. 08 Coherence Workshop in October 2008 Team Leader Meetings (XPP, CXI and XCS) in October 2008 Team Leader Representatives at FIDRs XPP Completed in February CXI, XCS planned for June Weekly Meetings Started between XPP and Controls Detectors Weekly Telecon with BNL Weekly Telecon with Cornell Interface Meetings with LCLS XFD every two weeks LCLS/LUSI management meetings in the off weeks CD-3 Dates are important. I am pretty sure you will be asked how much you can advance them if there is more funding. are the CD-3 dates set by manpower limitation? BA limits? both? do you need early BA to achieve CD-3 deliverables? or did you set CD-3 to coincide with arrival of BA needed to procure instruments? note change in wording of 2nd yellow box

10 Critical Decision Milestones
CD-0 - Mission Need - Approved Aug 2005 CD-1 - Alternative Selection and Cost Range – App’d Sep 2007 CD-2 - Approve Performance Baseline – Approved October, 2008 CD-3 - Approve Start of Construction Baseline, April, 2010 CD-4 - Approve Start of Operations Baseline, August, 2012 Baseline utilizes tailored approach with long lead procurement approvals and XPP Early Science Instrument Procurement Approval: XPP goniometer/detector positioner and CXI 1 micron mirror system (Approval received December 19, 2008) XPP Early Science Procurement Approval Received March 12, 2009 XCS goniometer/detector positioner and Large offset monochromator (Review scheduled for April 23, 2009)

11 Other Major Accomplishments
Purchase Order for the XPP Goniometer Placed (3/31) Purchase Order for the XPP Robot Placed (4/3) Procurement Review of the CXI 1 micron Mirror System Completed (Added 0.1 micron mirror as an option) Major CCB Actions BCR to move XCS Monochromator closer to sample approved by the Technical Configuration Control Committee (TCCC) and the LUSI Change Control Board Pending CCB Actions Add Large Offset Monochromator into XPP Scope Approved by TCCC

12 Project Completion TEC Overall Completion – 16% (based on costs to date) TPC Overall Completion – 24% (based on $47.22M EAC) Design Completion XPP Instrument Design through FIDR CD-3 Ready CXI Instrument FIDR in June 75% CD-3 Ready Now Instrument configuration is solid XCS Instrument FIDR in June 90% CD-3 Ready Now Diagnostics and Common Optics Design Harmonic Rejection Mirror PDR in June Controls and Data Acquisition 85% CD-3 Ready Now Inherited Designs from LCLS comprise many items Procurement is just starting Installation not started

13 Cost and Schedule Performance
In general, the experiments performed as this endstation will use an ultrafast laser pulse to initiate a transient response in a system. The system will be probed using various x-ray scattering techniques. The time evolution of the response will be mapped by variably delaying the arrival time of the x-ray pulse with respect to the pump laser pulse. The success of this end station will depend upon the ability to accommodate a wide variety of laser excitation techniques, samples, sample environments and x-ray scattering methods.

14 CPR

15 LUSI Project Summary Schedule
Early Dates Reflect ARRA Facilitated Schedule Advancement

16 Risk Management LUSI Follows the LCLS Risk Management Plan and uses the LCLS Risk Registry LCLS Project Management Document Risk Registry Updated April, 2009 Major Risks Annual funding - Continuing Resolutions (Retired) Foreign procurements – Dollar fluctuation, sole source Loss and/or availability of critical personnel (Exercised) Ability to place procurements CXI mirror delivery, performance XPP, XCS Monochromator delivery, performance XPP, XCS Detector delivery, performance

17 Cost and Schedule Contingency
Available Contingency is $12.73M Bottoms-up” contingency estimate is $9.65M on $39.22M ETC Contingency is managed at the project level Annual comprehensive ETC and contingency update Float 100 working days to CD-4 (Final Instrument Readiness Review Held March 6, 2012) Critical Path XPP Diffractometer (Contract issued) Monochromator (Pending BCR) CXI 1 micron K-B mirror system XCS Diffractometer Monochromator XCS Detector (Dec 2011 RFI)

18 Long Lead & Major Procurements
Advance Procurements XPP Goniometer/Detector Mover System $ K Goniometer Order Placed for $427.5K Robot Detector Positioner Placed for $74.8K About $230K remaining misc procurements CXI 1.0 Micron KB Mirror System $ K Bids Received – Under Evaluation Other Major Procurements CXI 0.1 Micron KB Mirror System $ K XCS Diffractometer System $ K XCS Detector Mover $ K XCS Large Offset Monochromator $1,160K XPP Large Offset Monochromator (Not yet in scope) $1,160K XPP Ti-Sapphire Power Amplifier $ 245K

19 LUSI MOUs Brookhaven National Laboratory – Detector Systems for XPP and XCS Instruments XPP Detector System: Estimated Delivery – January, 2010 XCS Detector System: Estimated RFI – December, 2011 Lawrence Livermore National Laboratory – Injector System for CXI Coating for Mirrors (future) DESY Split and Delay System Long-Term Loan arrangement

20 Staffing (FTE)

21 Control Account Managers
WBS Control Account Mgr Cntrl Accts Work Pkgs Budget 1.1 PM T. Fornek 6 12 $5.5M 1.2 XPP J. Langton (WO Detect) 10 44 $4.5M 1.3 CXI P. Montanez 11 45 $9.5M 1.4 XCS E. Bong (WO Detect) 41 $5.7M 1.5 D&CO E. Ortiz 39 $4.8M Monos E. Bong $1.7M 1.6 Cntrls & DAQ G. Haller 20 289 $7.2M Detectors N. Van Bakel 8 9 $3.5M

22 Procurements

23 ES&H ES&H performance to date Safety integrated with design reviews
6090 Hours worked with no DART or recordable incidents Safety integrated with design reviews Instrument readiness process will follow precedent set by AMO instrument SLAC & LCLS safety management resources employed by LUSI

24 Responses to Previous Reviews
Detailed Responses are provided in the back-up material Initial responses were made prior to CD-2 approval Responses have been updated twice since CD-2 approval Update 1 of the responses covered XPP, Diagnostics/Common Optics and Controls/Data Acquisition and were reviewed at the XPP “Early Science” Procurement Readiness Review

25 Responses to Previous Reviews (2)
CD-4 Deliverables These are detailed in PEP and Instrument Presentations Science Team Engagement Team Leader Meetings were held in October for XPP, CXI and XCS Meeting notes in back-up info XPP (TR ) CXI (TR ) XCS (TR ) Coherence Workshop Held in October, 2008 Two Team leaders participated in XPP FIDR held in February, 2009 Team Leaders to attend CXI and XCS FIDRs Plans for Team Leader Transition to Ops (Draft LOUs)

26 BA Plan & Obligation Profile
Baseline BA Profile 08 Q1 Q2 Q3 Q4 09 10 11 12 .5M 6.5M 8.0M 9.5M 21.5M 40.5M 50.5M 55.1M

27 In Conclusion (Current Baseline)
Technical Scope Accomplishments and plans adequate to meet baseline objectives Project scope is reasonable and managed by change control Project Management LUSI Project is being managed effectively Project Team, Stakeholders and Instrument Team interactions effective Issues identified and resolved in a timely manner Resources and Risks Resources are adequate Risks are identified and mitigated in a reasonable manner Contingency is managed to reduce risks Responses to prior reviews are documented and updated as needed

28 PART 2 PLANS FOR ARRA FUNDS

29 ARRA FUNDING TOPICS Funding Profile Schedule Advancement
Moves FY10, FY11 and FY12 into this FY ($33.6M) ARRA funds have special reporting and Buy American requirements Need to segregate these charges from standard appropriations LUSI still to receive $7.8M remaining from $15M FY09 appropriation (Not ARRA funds) Standard reporting and Buy American requirements Schedule Advancement CD-3 is critical (Project needs to be able to spend funds) LUSI is near the CD-3 level of design completion – Remaining FIDRs in June Technical Scope Current project scope is solid LUSI has prioritized scope adds – Contingency needs to be managed aggressively How much risk is reasonable Procurements Resources and Risks Staffing – Project needs to plan for higher staffing level than indicated Contingency usage Reduce risk Schedule risks Attention to vendors Alternatives – second detectors

30 Prelude LUSI is in a good position to utilize ARRA funds
We still remember CD-2 baseline development and what we had to do to meet CD-2 funding limitations We also started thinking about earlier funding in January $2M in this FY, $3M next FY as a proposal to DOE We have a current baseline with well-defined scope, scope adds and cost LUSI would like to keep current CD-4 in place We will add Level 2 milestones for XCS Early Science and Project Ready for CD-4 Project efficiency is measured by how much earlier CD-3 and CD-4 are accomplished Think about using this review as “partial credit” for CD-3 review Approve CD-3 design readiness process Identify areas needing follow-on effort for CD-3

31 LUSI ARRA Modified Funding Profile
ARRA Modified Profile Moves FY10-FY12 Funds into FY09 LUSI Funding Profile (AYM$) With ARRA Funds Prior Yrs FY07 FY08 FY09 FY10 FY11 FY12 Total Pre ARRA 0.50 6.00 15.00 13.50 5.10 55.10 MIE 21.50 MIE (ARRA) 33.60 OPC 3.40 1.50 4.90 2.00 48.60 60.00 Until Recently, We thought This might only be $10M

32 BA Plan & Obligation Profile
ARRA BA Profile 08 Q1 Q2 Q3 Q4 09 10 11 12 .5M 6.5M 8.0M 9.5M 55.1M

33 Schedule Advancement Milestone Current Baseline Advanced CD-3
April 2010 October 2009 XPP Early Science October 2010 CXI Early Science August 2011 June 2011 XCS Early Science (New) NA Project Ready for CD-4 (New) March 2012 CD-4 August 2012 XCS “Early Science” allows for a functioning XCS instrument one year earlier than original schedule These dates are based on a draft of a revised schedule. Once we finalize the ARRA plans and incorporate any review comments, we will process a BCR to change the schedule.

34 Technical Scope LUSI current scope is solid
Prioritized scope contingency list Priority Scope Addition Est Cost Decision Date Comments 1 XPP Large Offset Mono $1,400K Now Pending BCR Through TCCC 2 XCS Early Science Detector $400K 3 CXI Second Full Detector $379K 4 CXI Cryogoniometer Priorities may change based on TCCC input Complete List Available in Management Break-out Talk

35 Technical Scope Adds Based on ARRA
In-Process BCR to include a Large Offset Monochromator into XPP Scope (Not in February Data) Planning a BCR to add an “Early Science” XCS Detector (XPP copy) and another CXI detector Copy of XPP detector enables XCS early science Second CXI detector is for the 0.1 micron sample chamber Both of these detectors mitigate risk since the detectors can be used for any instrument Contingency will be $11,000,000 after XPP Mono Work Remaining will be $37,493,617 Contingency will be 29% on work remaining This is reasonable for a project at CD-3

36 Procurements LUSI utilizes LCLS procurement team
LUSI/Photon Systems has a separate meeting Hiring of buyers is in process Procurement discussion in Management Breakout XPP and related DCO procurements are already progressing without funding restraints (Partial Procurement Authorization) CXI Mirror Systems 1 micron mirror system authorized 0.1 micron identical, Review in process Need CD-3 ASAP for early use of funds for procurements Risk is low due to solid scope

37 Procurements and Dollars – Current
The x-ray pump-probe instrument will take advantage of the ultrashort pulse duration of the LCLS to take snapshots of a photo-induced phenomena. In general, the experiments performed as this endstation will use an ultrafast laser pulse to initiate a transient response in a system. The system will be probed using various x-ray scattering techniques. The time evolution of the response will be mapped by variably delaying the arrival time of the x-ray pulse with respect to the pump laser pulse. The success of this end station will depend upon the ability to accommodate a wide variety of laser excitation techniques, samples, sample environments and x-ray scattering methods.

38 Procurements and Dollars – Accelerated
The x-ray pump-probe instrument will take advantage of the ultrashort pulse duration of the LCLS to take snapshots of a photo-induced phenomena. In general, the experiments performed as this endstation will use an ultrafast laser pulse to initiate a transient response in a system. The system will be probed using various x-ray scattering techniques. The time evolution of the response will be mapped by variably delaying the arrival time of the x-ray pulse with respect to the pump laser pulse. The success of this end station will depend upon the ability to accommodate a wide variety of laser excitation techniques, samples, sample environments and x-ray scattering methods.

39 ARRA vs BASELINE Staffing (FTE)
Creating 6 jobs earlier in project

40 Staffing Human Resources is starting trial process of allowing more than one hire per requisition LUSI has been very aggressive in pushing hiring – even prior to ARRA CXI has a contract in place for outside design services LUSI is working with LCLS/EPD to place standing contract for photon systems related design services on a Task Order basis

41 Six Month Look Ahead XCS Advance Procurement Review for Diffractometer, Large Angle Detector Positioner System and Large Offset Monochromator – April 23 XCS Advance Procurement Approval for these items - May CXI Final Instrument Design Review – June XCS Final Instrument Design Review – June Ready for CD-3 – July CD-3 Review – July/August CD-3 Approval – October

42 In Conclusion Funding Schedule Advancement Scope Management
No more funding constraints – Yeah! Schedule Advancement CD-3 is critical to allow funding remaining procurements Three instruments to LCLS ops by end of FY11 Scope Management Plans to aggressively add scope from priority list are reasonable Project scope is reasonable and managed by change control Procurements Procurement durations need to be improved/controlled Resources and Risks Resource planning is reasonable ARRA funds reduce funding related risks Schedule risks drive project – Need CD-3