Hall C Dump Status Beam Resuscitation Review

Similar presentations


Presentation on theme: "Hall C Dump Status Beam Resuscitation Review"— Presentation transcript:

1 Hall C Dump Status Beam Resuscitation Review
Anthony DiPette 3/4/2016

2 Hall C Dump Status - BRR Required for March Run Status Next Steps

3 Required for March 14-17 Run
Hall C Dump Status - BRR Required for March Run New Helium Tube Isolation Wall with Door & Radcon Lock Vacuum Tube with Temp Window Tune Mode Viewer

4 Hall C Dump Status - BRR Status Installed Install 3/4/16 Installed

5 Hall C Dump Status - BRR Status I & C to Complete Camera System
Inst – Fill Helium and Vacuum Tube w/ Helium Radcon – Install Lock

6 Hall C Dump Status - BRR Status End Section of He Pipe

7 Hall C Dump Status - BRR Status Isolation Wall

8 Hall C Dump Status - BRR Status Downstream Vacuum Pipe Section
Upstream Vacuum Pipe – with Actuators Installed

9 Camera Box with Periscope Tubes
Hall C Dump Status - BRR Status Camera Box with Periscope Tubes

10 Hall C Dump Status - BRR Status
High Power Viewer Periscope Tube, Diffuser Drive shaft, Iso Wall Door Hardware

11 Hall C Dump Status - BRR Next Steps
Complete Mech: Diffuser Drive & Blower, Tunnel Shielding, Iso Wall Grouting/Sealing, Aperture Plate & Window Water Cooling System, Camera Box Shielding, N2 System Final Connect and Commission Complete Diag: Diffuser Drive & Blower, Tune Mode Viewer, Calibration Puck, Water Cooling System, N2 System, Helium Monitoring, Ion Chamber Install and Commission