1 Personnel Safety Systems
Bryce Karnaghan

2 Background My history Beamline PSS 25 Years in control systems
Most experience on water, power and rail Leaning about synchrotrons Beamline PSS Via booster and storage ring PSS

3 Requirements of a PSS Protect personnel Other requirements
Safety Integrity Level 3 No single point of failure Fail-safe Other requirements Separate system from controls and instrumentation system (EPICS) Be able to transfer data to EPICS Control personnel access when radiation hazards exist Allow mtce access when radiation hazards removed

4 Meeting the requirements
Equipment Uses safety rated PLC/relay system from Pilz

5 Meeting the requirements (cont)
Equipment (cont) An intercom and video surveillance system at access points Controlled access gates Captive permit key Blue lights in vaults when no access is not allowed Illuminated signs, at appropriate locations within the facility Emergency Stop buttons throughout the vaults Ability to crash out of an access gate Safety switches on doors as interlocks

6 Meeting the requirements (cont)
Three operation modes Open Access Mode: Allows unlimited and open entry to authorised personnel. Both the radiation and electrical hazards are interlocked to be off.

7 Meeting the requirements (cont)
Three operation modes (cont) Authorised Access Mode: Allows limited and controlled entry to authorised personnel through controlled doors only. The radiation hazards are interlocked to be off. Electrical hazards may be on to allow specialised testing. This access mode allows for the search / secure procedure of each zone and for limited / controlled procedural access. In both cases access is allowed only to authorised personnel following a strict protocol.

8 Meeting the requirements (cont)
Three operation modes (cont) No Access Mode: Allows operation of the beam in the Linac Booster Area (zones 1, 2 and 3) and/or into the Storage Ring (zones 4, 5 and 6). Radiation and electrical hazards exist and no personnel are allowed in the zone. Must complete search before entering this mode

9 Implementation External contract
Installed by Sage Automation in partnership with Pilz and Nielsen. Meeting all requirements

10 Implementation (cont)
Equipment Pilz safety rated PLC/relay system

11 Implementation (cont)
Equipment (cont) Triple redundant CPUs Safety bus Inputs and outputs are dual channel Certified software

12 Implementation (cont)
Equipment (cont) Control desk located in the control room Video feed from labyrinth doors Intercoms to labyrinth doors Master Reset PMI (HMI) located in control desk

13 Implementation (cont)
Equipment (cont)

14 Implementation (cont)
PMI

15 Implementation (cont)
PMI (cont)

16 Progress Linac, Booster, Storage Ring
Type testing of major systems (FAT) Final functional requirements definition Physical installation commence May

17 Beamline PSS Storage ring PSS provides a failsafe contact indicating shutters can be opened Beamline PSS's will be standalone systems Will provide personnel safety in the Beamline hutch Will utilise the search method for securing Will be responsible for opening the shutters Use Pilz safety rated equipment Will be coded in house


Download ppt "Personnel Safety Systems"