El Cerrito High School Stadium Project Status

Similar presentations


Presentation on theme: "El Cerrito High School Stadium Project Status"— Presentation transcript:

1 El Cerrito High School Stadium Project Status
Facilities Subcommittee Meeting April 14, 2015 El Cerrito HS Stadium Project Status

2 Project from Colusa Avenue
El Cerrito HS Stadium Project Status

3 Building B (Weight Room)
El Cerrito HS Stadium Project Status

4 Building D (Restrooms)
El Cerrito HS Stadium Project Status

5 El Cerrito HS Stadium Project Status
Bleacher Foundations El Cerrito HS Stadium Project Status

6 Installation of KECG Antenna
El Cerrito HS Stadium Project Status

7 Project Schedule Summary
Bid Date: November 5, 2013 BOE Award Date: December 2, 2013 Notice to Proceed January 27, 2014 Duration 608 Days Approved time extensions 0 Days Revised contract completion date September 27, 2015 El Cerrito HS Stadium Project Status

8 El Cerrito HS Stadium Project Status
Project Cost Summary Bid (11/05/13) $13,438,000* Change Order Summary (through 04/08/15) Approved C.O.’s $250,617 (1.87%) C.O.’s Under Review $420,156 (3.13%) Rejected C.O.’s* $153,702 ______ $747,624 (5.00%) Note: Rejected C.O.’s (1.14%) are potential claims. Additional undetermined issues are possible through completion of project. (* 15.8% over estimate) El Cerrito HS Stadium Project Status