Presentation is loading. Please wait.

Presentation is loading. Please wait.

OVERVIEW ON THE MYPD3 PUBLIC CONSULTATION PROCESS

Similar presentations


Presentation on theme: "OVERVIEW ON THE MYPD3 PUBLIC CONSULTATION PROCESS"— Presentation transcript:

1 OVERVIEW ON THE MYPD3 PUBLIC CONSULTATION PROCESS
PRESENTATION TO THE JOINT COMMITTEE ON ENERGY 30 OCTOBER 2012

2 Contents MYPD Process/Procedure Public Consultation Processes
Timelines for processing the application Conclusion

3 MYPD Process/Procedure
There are 6 pillars used in the MYPD determination process: Pillar 1 : Planning Review of previous decisions and current regulatory rules Analysis of current/prevailing economic, political, social and legal environment Draft Process plan that includes timelines etc Pillar 2: Organising The MYPD application is broken down into key elements/teams for the ease of management of the work.

4 MYPD Process/Procedure (Contd)
Pillar 3: Analysing Actual analysis of the data received from Eskom Pillar 4: Consultation In MYPD , a broad spectrum of stakeholders are consulted for their views and comments. Written comments are solicited and Public Hearings are held in all provinces of South Africa

5 MYPD Process/Procedure (Contd)
Pillar 5: Determination This is mainly the consolidation of all evidence that has been gathered (spreadsheets, comments etc). After consolidation of the evidence, the Regulator will consider the regulatory objectives to be achieved including the public interest Pillar 6: Communication After the decision by the Energy Regulator, it is communicated to Eskom and the Minister of Energy. NERSA then holds a media conference

6 MYPD Process/Procedure (Contd)
Public Consultation Processes Requests for written comments Discussions (Information Sharing) with stakeholders and the public on Eskom’s application Radio Talk Shows (SABC & Community Radio Stations) SABC TV Public Hearings in all provinces

7 MYPD Process/Procedure (Contd)
Public Consultation Processes Public Hearings (15 – 31 January 2013) PROVINCE CITY/TOWN DATE Western Cape Cape Town Eastern Cape Port Elizabeth Kwa-Zulu Natal Durban Free State Bloemfontein Northern Cape Kimberly North West Potchefstroom Mpumalanga Nelspruit Limpopo Polokwane Gauteng Roodepoort 30 &

8 TIMELINES FOR PROCESSING ESKOM’S MYPD3 APPLICATION
ACTIVITY DATE Receipt of Eskom’s Application 18 October 2012 Publication of Application on NERSA Website (Request for written comments) 22 October 2012 Closing date for stakeholder comments on Eskom’s MYPD3 application 20 November 2012 Public Hearings in all provinces 15 – 31 January 2013 Energy Regulator’s Decision on Eskom’s MYPD3 application 28 February 2013

9 Conclusion NERSA is committed to a transparent consultative process in its decision making process Discussions with the general public and stakeholders will provide a platform to interrogate the application NERSA will also ensure engagement with the following high level stakeholders and decision makers PPC on Energy, Economic Development, Local Government and Public Enterprises; Department of Energy; Mayors of identified towns/cities; and Traditional Leaders in relevant towns/cities

10 Thank You. Tel: 012 401 4600. Fax: 012 401 4700. Website: www. nersa
Thank You Tel: Fax: Website: Physical Address: Kulawula House 526 Madiba Street Arcadia,0083 Pretoria


Download ppt "OVERVIEW ON THE MYPD3 PUBLIC CONSULTATION PROCESS"

Similar presentations


Ads by Google