Presentation is loading. Please wait.

Presentation is loading. Please wait.

Study of Adjustment Orders in Projects K-LEAD LEARNING EXPERIENCE

Similar presentations


Presentation on theme: "Study of Adjustment Orders in Projects K-LEAD LEARNING EXPERIENCE"— Presentation transcript:

1 Study of Adjustment Orders in Projects K-LEAD LEARNING EXPERIENCE
COHORT NO. – 2 TEAM MEMBERS ABDULLA AL AWADHI (KOC) SAUD RAKHEES (KNPC) SULAIMAN AL ABDUL SALAM (PIC) AMEENA RAJAB (KOC)

2 Study of Adjustment Orders in Projects
What is an Adjustment Order? Typical definition of Adjustment Order “Adjustment Order means, where required to be issued in accordance with the Contract, an order issued by the Superintendent adjusting the Contract Price and/or Scheduled Turnover Date and/or amending any of the Contractor’s obligations under the Contract”. Adjustment Orders (AO) arise from Variations to any of the contract terms and conditions including scope, technical requirements and specifications. Variations can be proposed by: Company Contractor As claims based on contract provisions Adjustment Orders could be for contract price, schedule or both

3 Study of Adjustment Orders in Projects
High number of Adjustment Orders are undesirable Cost Schedule Quality Project dependencies Success of any project depends on completing the project on time, within the budget and with required quality Large number of AOs upset project budget and schedule Affects other connected projects May impact production targets

4 Study of Adjustment Orders in Projects
What causes Adjustment Orders? Changes in Scope Of Work (SCOW) Extension of Time (EOT) Adjustment Orders Others In order to reduce number of AOs we have to get to the root causes Others include: Changes to conditions of contract, Impact due to other Projects/Entities, late Shutdowns & from Health Safety and Environmental studies (HSE). etc.

5 Study of Adjustment Orders in Projects
Typical distribution of Adjustment Order causes Main contributors to AOs Change of scope Change of scope [with cost + Extension of time] Extension of time [without scope change, example: Tie in availability, shutdowns, client inputs] Others [slit trenching findings, Hazard & Operability Studies (HAZOP) recommendations, etc.]

6 Study of Adjustment Orders in Projects
Are Adjustment Orders preventable? AOs are preventable to a great extent though not totally eliminated. Requires careful root cause analysis Typical engineering root cause analysis methodology: Analyze the visible causes --> find out latent causes --> arrive at the root causes |--Immediate causes-| |--Latent causes--| |---Root causes---|

7 Study of Adjustment Orders in Projects
Immediate cause Latent causes Root causes Additions /deletions / relocation of equipment / units Lack of adherence to FEED scope and parameters by concerned stakeholders Changes to input data Change in equipment design/ material /specifications Lack of involvement by concerned stakeholders during feasibility studies / FEED Change of Scope Route changes for pipelines and piping Potential for pipeline reroutes not foreseen during FEED Changes from the FEED at the interface points Interface issues with facilities, other projects, & outside entities Major equipment additions during detailed engineering, DCS expansions FEED quality issues Non availability / reliability of As-Built documentation Quantities increase in re-measurement Quality of HSE studies during FEED Impacts from Hazop / SIL studies Impact from Tie ins issues

8 Study of Adjustment Orders in Projects
Immediate cause Latent causes Root causes Additions /deletions / relocation of equipment / units Changes to input data Interface management issues with all stakeholders Change in equipment design/ material /specifications Extension of Time Contractor performance Route changes for pipelines and piping Changes from the FEED at the interface points Operational reasons (Shutdowns, etc.) Major equipment additions during detailed engineering, DCS expansions Quantities increase in re-measurement Impacts from Hazop / SIL studies Impact from Tie ins issues

9 Study of Adjustment Orders in Projects
Immediate cause Latent causes Root causes Others Impacts from Hazop / SIL studies Quality of Design / Safety reviews during FEED Lack /change of reservations for location, power, space. Etc. Absence of systems and procedures Unforeseen incidents (fire etc.)

10 Study of Adjustment Orders in Projects
Lessons Learned Scope creep and specification changes need to be controlled. Preferential engineering requirements must be identified and eliminated Project delays due to Interface issues are a repeated feature. Issues within stakeholders as well as third parties must be addressed. Conditional scoping & grey areas in in the FEED are to be minimized Contractor’s non agreements with estimates on various changes are to be handled effectively. 5. Availability and reliability of As-Built documentation is a serious over arching issue impacting projects and in turn operations and safety. System for maintaining of as built drawings / continuous updating in a centralized repository are needed

11 Study of Adjustment Orders in Projects
Recommendations 1. Encourage active & effective participation of all concerned stakeholders during Concept selection and FEED development phases. Ensure continuity of key personnel in project. 2 Establish a permanent Project Interface Coordination Committee (PICC) with external entities in order to have proactive and effective coordination. Ensure that each project has an ‘Interface Diagram’ that is approved by all concerned teams. A signed ‘Interface Agreement’ at the senior management level will be preferable for critical projects. Interface management: First option -- Avoid engineering and execution of projects within the Battery Limit of other entities. Second option--> FEED within another battery limit to be engineered by the concerned entities. Any changes within their battery limits will be managed the concerned entities directly with the contractor.

12 Study of Adjustment Orders in Projects
Recommendations continued 4. Improve quality of FEED deliverables by enhancing effectiveness of ‘Third party’ review during FEED by utilizing in house experts who are not involved in project. 5. Create mechanism for proper As-Built documentation and continuous updating. A comprehensive Centralized Document Management System (CDMS) is recommended with suitable accessibility options by all stakeholders. Outsourcing of the entire document updating work is the suggested model.

13 Thank you.


Download ppt "Study of Adjustment Orders in Projects K-LEAD LEARNING EXPERIENCE"

Similar presentations


Ads by Google