REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA

Similar presentations


Presentation on theme: "REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA"— Presentation transcript:

1 REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA 14.07.2014
Restructured Accelerated Power Development and Reforms Programme (R-APDRP) REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA

2 Go-Live Status of ESCOM’s of Karnataka
Restructured Accelerated Power Development and Reforms Programme (R-APDRP) Go-Live Status of ESCOM’s of Karnataka Scheduled date for Go live / integration of all towns : Sep 2014 Town Integration Energy Audit Schedule Month Up to Jan’ 13 Up to Feb’ 13 Up to Mar’ 13 Up to Apr’ 13 Up to May’ 13 Up to Jun’ 13 Up to Jul’ 13 Aug’ 13 Up to Sep’ 13 Up to Oct’ 13 Nov’ 13 Dec’ 13 Jan’ 14 Feb’ 14 Mar’ 14 Apr’ 14 Up to May’ 14 Up to Jun’ 14 Jul’ 14 Aug’ 14 Sep’ 14 Target 10 18 40 50 53 55 75 91 98 Achieved 6 31 46 51 60 ESCOM MBC live (100% implementation in Karnataka) Full Stack with Energy Audit BESCOM 25 16 CESC 12 6 GESCOM 21 11 HESCOM 29 26 MESCOM 1 TOTAL 98 60

3 Module wise / ESCOM’s Wise Status as on May 2014
Restructured Accelerated Power Development and Reforms Programme (R-APDRP) Module wise / ESCOM’s Wise Status as on May 2014 % progress taken SDO wise ESCOM Total Towns Total SDOs Office Infrastructure Primary Network Secondary Network MBC Go Live GIS Network Approved GIS Consumer Approved Meter-installed Modems installed Full Stack Go-Live BESCOM 25 74 100% 43 70% 29 40% 1 1% 16 22% CESC 12 19 10 53% 6 32% GESCOM 21 23 91% 60% 11 48% HESCOM 37 26 34 92% 23** MESCOM 17 15 88% 5 30% 4 24% 65% 6% 5% Total 98 170 124 84% 169 158 86% 157 85% 110 72% 63 38% 35% CCC Operational across All ESCOMs *Only for 26 towns modems are installed and all 29 towns DTC meter DLMS meters installed. ** 23 towns FS go-live ( Hubli-dharwad, Belgaum, Bijapur, Gadag, Bagalkot & Ranebennur pending). Only 19 towns DTC SIMs are activated, balance 4 towns DTC SIMs activation is under progress by RCOM. SIMs are communicating in 12 towns only i.e. also about 30% only & SIMs in balance 7 towns are not actually communicating. Out of 4852 only 701 no.s of modems are communicating.

4 CRITICAL ISSUES OF PROJECT IMPLEMENTATION
Restructured Accelerated Power Development and Reforms Programme (R-APDRP) CRITICAL ISSUES OF PROJECT IMPLEMENTATION Issues Resolution Network issues / Performance and availability Increase of Bandwidth from 2Mbps to 4Mbps at each SDO of BESCOM, with Optical fiber as the last mile connectivity. ITIA to confirm on the application stability after up gradation of the network to 4Mbps. Reliance Links going down early during office hours and restoration after office hours At many sites tickets are not getting resolved within 24hrs as per SLA Links frequently going down due to Packet drops , Latency , fibre cuts, Link Flapping and no proper power back up for the Base Transceiver Station(BTS) towers of RCOM BSNL links being integrated by ITIA in some sites as an alternate to meet the targets. GIS Deployment of GIS based integrated Network analysis Module NEPLAN pending by ITIA. Incremental data updates on Network and Consumers incorporated by ITIA at Mulbagil town only Poor performance of GIS Online application, ITIA has informed the same is due to license issues. A committee formed y BESCOM comprising directors of IEEE to deliberate on the same, the committee has opined addition of hardware and requisite software will only provide marginal increase in performance and not in an order of magnitude, with the following recommendations Committee has suggested changes / implants to GIS architecture and ITIA to incorporate the same.

5 CRITICAL ISSUES OF PROJECT IMPLEMENTATION
Restructured Accelerated Power Development and Reforms Programme (R-APDRP) CRITICAL ISSUES OF PROJECT IMPLEMENTATION Module: GIS based Consumer Indexing and Asset mapping Benefits of Bypass GIS online for loads up to 10HP/ 7.5kW: As a measure to simplify the process in RAPDRP end-to-end application and in accordance with KERC regulation, online GIS application is bypassed for Customer loads up to 10HP/ 7.5kW where there is no extension of network. This process is deployed w.e.f Speedy disposal of New Connection cases using By-Pass GIS On-line option: For a single connection, users are able to save minutes in the end-to-end process. Currently, BYPASS GIS option is built for SINGLE NEW CONNECTIONS. This option is to be built for “LOAD ENHANCEMENT”, “LOAD REDUCTION” and “MULTIPLE CONNECTION” cases by ITIA. ESCOM ONLINE BYPASS GIS STATISTICS Total NC cases NC cases without Online GIS % Without Bypass GIS NC cases with Online GIS % With Bypass GIS BESCOM 3006 277 9.2% 2729 90.8% CESC 1657 64 3.9% 1593 96.1% GESCOM 1402 39 2.8% 1363 97.2% HESCOM 3675 212 5.8% 3463 94.2% MESCOM 282 4 1.4% 278 98.6% Total 10022 596 5.9% 9426 94.1%

6 CRITICAL ISSUES OF PROJECT IMPLEMENTATION
Restructured Accelerated Power Development and Reforms Programme (R-APDRP) CRITICAL ISSUES OF PROJECT IMPLEMENTATION Issues Resolution GIS Feature restriction to be done immediately MAP slicing to be done at division level. Explore switchover from web editing mode to client editing mode. Optimise On-line GIS by-pass for other use cases Carryout an exercise by executing a live case of Asset creating in GIS at Data Centre and observe the performance of the application and check all the logs in the system process-wise. Committee felt it is not very confident that procurement of licenses will be very helpful unless the above issues are taken care. Hence ITIA is asked to implement the suggestions as above MDAS The legacy meter replacement to DLMS meters are in progress. 44295 No’s of meters already fixed and commissioned and balance 9589 Nos yet to be fixed BESCOM. 17251 modems installed by ITIA as on date modems yet to be installed. Energy Audit SIM card not communicating. Gaps in GIS Incremental update and PART B network upgradation. Modems burnt out issue Additional Chief Secretary to conduct a meeting with ITIA and Modem Vendor. New Connection Process simplification by introducing bypass of GIS online for loads up to 10HP/ 7.5kW Asset and Maintenance Management WAMS system down since 01 June 2014, manual updation in progress till the system stabilizes

7 RAPDRP PART-A FINANCIAL PROGRESS Rs in Crores
Restructured Accelerated Power Development and Reforms Programme (R-APDRP) RAPDRP PART-A FINANCIAL PROGRESS Rs in Crores ESCOM NO.OF TOWNS TOTAL PROJECT COST LOAN SANCTIONED (Convertible to Grant ) PFC DISBURSEMENT DETAILS TOTAL EXPENDITURE INCURRED FROM PFC FUNDS FROM OWN FUNDS TOTAL BESCOM 25 282.70 261.36 146.65 101.27 24.62* 125.89 MESCOM 11 25.33 12.07 7.24 7.19 14.43 CESC 12 27.80 27.73 16.64 11.7 HESCOM 29 53.30 52.62 15.78 22.26 38.04 GESCOM 21 38.70 37.36 11.21 10.53 - 98 427.83 391.14 197.52 146.52 54.07 200.59 * Rs crores spent for metering out of BESCOM funds