1 On the National Scene

2 On the Local Scene

3 St. Louis MSA 96 Major Projects $13.5 billion in Construction

4 Project Listings and Manpower Requirements
68 Major Projects $14 billion in Construction 96 Major Projects $13.5 Billion Backlog

5 Labor “Sand Pile” Chart
The “wave” of work predicted last year is on track to begin in mid 2018. Currently at or near Full Employment Current Labor Conditions near 100% Full Employment

6 Manpower Loading Curves
20% More Resources

7 Tactics and Strategies to Reduce on-site Labor Hours
Prefabrication Off-Site Pre-Manufacturing Off-Site Pre-Assembly Off-Site Better Material Handling and Sequencing Strategic Use of Overtime (Critical Path Activities) Avoid Shift Work (Additional Work Force may not be Available) Use of 4 ten hour days for trades that have it in their contract. (Friday as Make-up Day not exceeding 40 hours per week)