1 Cutover & Implementation Aggregated Programme RAG
UK Link Programme Dashboard Report Change Overview Board – 6th October 2014 Executive summary RAG status for the Programme remains at ‘amber’ File format formal consultation for phase 1 delivered on 30th September. Subsequent phases on track for 7th & 14th October. Detailed Design for 2 of the 3 design tranches complete on schedule at the end of September, remaining tranche planned for 24th October Functional fit currently remains positive at approx % File Format Plan has been shared with the Industry, outlining the formal consultation timelines. Formal consultation for Phase 1 file formats commenced 30th September with additional files published prior to phase 2 & 3 review periods. A UK Link Programme Industry Engagement Day has been scheduled for 02/10; the event is an opportunity for Xoserve to present the background to UK Link file format changes in the context of business processes System build continues to progress System Testing commenced on schedule Recent Achievements Formal representation period for file formats in 3 phases Continuation of the To Be Process Walkthroughs in line with the agreed schedule. Complete detailed design for remaining tranche Continue build and system test activities Review delivery plan Further transition modifications to be developed at Nexus Workgroup as per the Transition Topic Schedule. Increased engagement on data resulting from source to target mapping phase Future Priorities 2014 Q1 2014 Q2 2014 Q3 2014 Q4 2015 Q1 2015 Q2 2015 Q3 2015 Q4 Industry Engagement Comms Reporting Date GO LIVE To-Be Processes IE Comms. 12/5 Test Strategy 18/6 Transition Strategy Q1 2015 Mkt Test Approach & Registration Process 31/3 Transition Mods Approved 01/6 Start of Market Trials, L/L Cutover Plan 28/8 End of Market Trials IDR1 Update IDR2 Update 22/7 Data Mapping Presentation 30/9 File Formats 30/11 Draft Industry Go/No Go Criteria 31/3 Imp. Dates Outage Window IDR3 Update 31/12 Cutover Principles & Assumptions Programme Milestones Key Milestone High Level Design Complete Detailed Design Xoserve UAT Industry Testing Start Cutover & Implementation Baseline Date 18/04/14 29/08/14 28/05/15 01/06/15 01/10/15 Current Planned Date 30/04/14 24/10/14 01/10/2015 Aggregated Programme RAG Risks Key Dependencies Risk Summary Impact Date Mitigation Industry readiness: Risk that there is a varied understanding within stakeholder organisations of Nexus requirements due to lack of or inconsistent attendance at industry forums. June 2015 Xoserve’s programme of industry engagement at all levels aims to level-set understanding. Terms of Reference in UKLIEF will avoid re-working topics agreed through PNUNC. File Formats: There is a risk that any changes to file formats as a result of the UKLC approval process (formal consultation and reps) may impact on the ability of the industry to deliver by Oct due to design re-work Oct 2014 Draft file formats released in August to give early sight and UKLP Engagement Day set up to focus on file formats in the context of business processes. Market Testing: Risk that Market Trials is insufficient in length, too late within the programme, and participants may not be ready in time to take part. Review of delivery plan following the end of detailed design will investigate options for delivering elements of Market Trials earlier than June 2015. Dependency Date Required Impact if missed Status Industry participants to cleanse data by December 2014 to feed into UAT Dec 2014 Testing timelines may increase due to increased number of data issues, leading to an overall delay to the implementation. Industry agreement of process change to adopt SAP ‘Out of the Box’ May to Oct Delays in confirmed changes to industry stakeholder systems with follow on impacts on market test and implementation readiness Industry agreement on file formats through UKLC Oct 14 The programme will continue build and testing activities at risk.

2 UK Link Programme Dashboard Report (II)
CMS Consequential Change Recent Achievements: Delivery work commenced for this workstream Priorities For Next Month: Requirements gathering to understand consequential change to CMS resulting from new world UK Link Risks: Pending design decisions within UKL application stream could impact CMS delivery timescales Dependencies: Specific requirement decisions for iGTs to determine end state to-be processes in order to take forward into design Key Milestone HLD Complete Detailed Design Xoserve UAT Industry Test Start Cutover & Implementation Baseline Date 21/10/14 20/11/14 29/05/15 01/06/15 01/10/15 Current Planned Date 17/11/14 12/12/14 03/07/15 13/07/15 Aggregated RAG SAP BW (IP/DE) Recent Achievements: Analysis on existing DE Service progressing Development of Functional and Technical Specifications NB: Detailed Design Complete date now reflects DE Service, previous reports did not. Priorities For Next Month: Progress development of Functional and Technical Specifications for Reports Continue Analysis of current DE Service and clarification of delivery on SAP technology. Risks: There is a risk that UK Link detailed design is not completed on time and leads to delays in finalising the design of SAP BW. Dependencies: Completion of UK Link detailed design to baseline the final requirements for the SAP BW solution Key Milestone Req’s Validation Detailed Design Complete Xoserve UAT Industry Test Start Cutover & Implementation Baseline Date 30/05/14 16/10/14 29/05/15 01/06/15 01/10/15 Current Planned Date 29/12/2014 30/06/15 Aggregated RAG Gemini Consequential Change Recent Achievements: Detailed Design complete Build progressing to plan Priorities For Next Month: Complete build Commence System Testing Detailed test planning in conjunction with EU Reform Risks: Risk that the UKL DD phase will define further interface requirements impacting Gemini Dependencies: Additional full scale environment required to meet test requirements Key Milestone HLD Complete Detailed Design Xoserve UAT Industry Test Start Cutover & Implementation Baseline Date 11/07/2014 12/09/14 29/05/15 01/06/15 01/10/15 Current Planned Date 30/09/14 Aggregated RAG

3 Change Portfolio: Programme Dashboards
Recent Achievements: Build phase and upgrade of test environments is progressing to plan. Detailed test planning in progress. Greater understanding is developing of the dependencies between UKLP and EU Reform and development of options to mitigate the delivery risks. Priorities For Next Month: Continue with Application Build. Continue with the upgrade of test environments to accommodate EU Changes. Risks: A solution is required to enable data exchange between Adjacent Transmission System Operators and Gemini, given that TSOs are not using the assumed mechanism. A B2B solution is under analysis. High risk of change due to unapproved EU Codes and UNC mods. Dependencies: Baselining and approval of modifications is required. EU Reform – EU Phase 2 and Gas Day Changes Key Milestone Analysis Complete Detailed Design Xoserve UAT Cutover & Imp. Baseline Date 30/06/14 15/08/14 31/07/15 06/09/15 Current Planned Date 06/09/15* Aggregated Programme RAG *Cutover to be planned alongside UKLP Smart Portfolio – DCC Day 1 & DCC Gateway Recent Achievements: The Build phase for delivery of the DCC Gateway mechanism continues despite uncertainty over potential DCC delays Priorities For Next Month: Order the DUG connection to the DCC Continue with build activities Continue to liaise with the DCC to determine the impact of potential SIT delays Risks: Uncertainty over revised DCC go-live Late delays to UKLP or DCC implementation would impact DCC Gateway cutover The timeline for ordering the UG (connection to the DCC) along with delays on the Electricity side are putting the DCC SIT timelines at risk Dependencies: DCC Gateway deployment approach remains dependent upon the sequencing of DCC and UKLP go live dates. Key Milestone DCC Day 1 Impl. HLD Complete Detailed Design Xoserve OAT Cutover & Imp. Baseline Date 29/06/14 n/a 05/09/14 24/10/14 13/12/14 Current Planned Date 23/10/14 31/12/14 18/01/15 Aggregated Programme RAG Faster Switching (Mod 477) Recent Achievements: System Testing and Performance Testing has completed and we have moved into the UAT phase Priorities For Next Month: Complete UAT execution Implementation preparation activities Risks: Increased efforts in testing as Faster Switching functionality is to be delivered in Legacy and new world UKL. Dependencies: None Key Milestone Analysis Complete Detailed Design Xoserve UAT Cutover & Imp. Baseline Date 07/04/2014 30/05/14 17/10/14 07/11/14 Current Planned Date Aggregated Programme RAG