1 SHANE ELKIN - Noise & Vibration
West Gate Tunnel Project 4/9/2017

2 Key Documents Page 2 Expert Report (dated 2 August 2017):
EES Technical Report H – Surface Noise and Vibration Impact Assessment EES Technical Report I – Vibration and Regenerated Noise from Tunnel Construction Assessment Vicroads Traffic Noise Reduction Policy Vicroads RDN Interpretation and application of Vicroads Traffic Noise Reduction Policy 2005 (superseded version) Vicroads Traffic Noise Measurement Requirements for Acoustic Consultants Vic EPA’s Submission on the West Gate Tunnel Project (dated 10 July 2017) Vic EPA’s Noise Control Guidelines (dated October 2008) Joint Expert Report (dated 14 August 2017): Matt Stead’s Expert Report (dated 2 August 2017) Darren Tardio’s Expert Report (dated 2 August 2017) Vicroads RDN Interpretation and application of Vicroads Traffic Noise Reduction Policy 2005 (current version) Project Note No. 1

3 Key Documents Page 3 In Preparation for Giving Evidence at the Hearing: Dr John Heilig’s Expert Report (dated 1 August 2017) Evidence-in-Chief presentations – Matt Stead, Darren Tardio, Dr John Heilig Vicroads Traffic Noise Reduction Policy Review (dated August 2015) Vicroads Submission to the West Gate Tunnel Project Inquiry and Advisory Committee (dated 25 August 2017) Douglas Munro’s Expert Advice (dated 11 August 2017) Project Note Nos. 4, 13, 19, 24, 26, 32, 44, 53, 54, 55 and 61

4 Expert Report – Overview Page 4
Gain an understanding of the Project Review the criteria, monitoring, modelling, assessment and mitigation contained in the EES to be comfortable there were no “show stoppers” Review/revise the EPRs to ensure they provide adequate noise and vibration protection for the constituents of Hobsons Bay Council during both construction and operation

5 Expert Report – Key Aspects Page 5
CONSTRUCTION PHASE Surface construction activities Tunnelling construction activities Construction traffic on surrounding road network OPERATIONAL PHASE Road traffic noise (project infrastructure) Road traffic noise on surrounding road network Mechanical noise (e.g. ventilation system)

6 Expert Report – Review Findings Page 6
Need for a robust Construction Noise and Vibration Management Plan (CNVMP) Universal agreement amongst experts Suggested (by Mr Elkin, Mr Stead, Mr Zerbst) revision to EPR NVP3 (based on MMRP EPR NV21) to include many aspects of a robust CNVMP Disagreement with the definition given for “inaudibility” Revised definition of “background + 0 dB” (external) agreed amongst experts for the purposes of CNVMP predictions

7 Expert Report – Review Findings Page 7
Noise Monitoring Results Request the IAC consider a definition of background noise to clarify criteria in EPR NVP4 (as agreed with Mr Stead) Incomplete data (not material) Missing Construction Compounds Lynch St and Melbourne Rd compounds will be captured by CNVMP Both very close to residences therefore likely to require substantial mitigation/management (subject to actual construction activities)

8 Expert Report – Review Findings Page 8
10 dB Noise Reduction Applied to Construction Noise Predictions for Perimeter Noise Barrier Acceptable noise reduction however still exceedences hence need for robust CNVMP and independent auditor Acoustic Sheds Need to be determined in CNVMP Preference for it to be stipulated in EPR Standard practice for tunnel portal construction worksites in Australia

9 Expert Report – Review Findings Page 9
Construction Traffic Routes Strong recommendation to avoid “local” streets I still have some concerns over northern section of New St servicing the Southern Portal worksite given Project Note 19 states that there will still be heavy vehicle movements along this street Incorrect Distances between Worksites and Residences Will ultimately be addressed via the development and implementation of the CNVMP

10 Expert Report – Review Findings Page 10
Modelled Construction Equipment SWLs Will ultimately be addressed via the development and implementation of the CNVMP Tunnelling Regenerated Noise and Vibration I am in agreement with the findings and mitigation options stated by Dr Heilig

11 Expert Report – Review Findings Page 11
Active and Passive Open Spaces My opinion (as with Mr Munroe) is that it is reasonable to treat open spaces as noise sensitive during both construction and operation Comparison of LA10(18hr) and LA10(12hr) parameters Will be addressed during detailed design and ultimately tested during post-construction compliance monitoring

12 Expert Report – Review Findings Page 12
Minor Exceedences of 63 dBA LA10(18hr) Item No 13 of the Joint Expert Report recommends EPR NVP 1 include reference to Vicroads RDN for reasonable and practicable requirements SEPP N1 Background Errors Will be addressed during detailed design and ultimately tested during post-construction compliance monitoring

13 Expert Report – Review Findings Page 13
Existing Model Verification Will be addressed during detailed design and ultimately tested during post-construction compliance monitoring Millers Road Recommend implementation of Project Note 1 (single truck toll point) – agreement with Mr Stead (Joint Expert Report Item 3(a)) If Project Note 1 is not implemented, my suggestion is to implement mitigation measures (agreement in general from Vicroads)

14 Conclave Report Page 14 MATTERS OF AGREEMENT
ITEM RECOMMENDATION EPR STATUS 3 (A) IAC to consider implementation of PN 1 With the IAC 4 (and 13) Reference to Vicroads RDN in NVP1 for off-reservation mitigation Unresolved in V3 6 Building condition surveys be undertaken where there is risk Resolved in V3 (NVP3)

15 Conclave Report Page 15 MATTERS OF AGREEMENT
ITEM RECOMMENDATION EPR STATUS 7 Requirement for real-time monitoring in high risk areas Resolved in V3 (NVP3) 8 Adoption of greater CNVMP detail contained in MMRP EPR NV21 Unresolved in V3 9 Definition of “background” noise required for CNVMP predictive purposes

16 Conclave Report Page 16 MATTERS OF DISAGREEMENT
ITEM RECOMMENDATION COMMENT 1 Deletion of “facing the traffic noise, being those adjacent to or with direct line of sight to the freeway” I am unclear on what this means and why it is required. I recommend a more simple definition Agreement from Mr Munro 2 Operational noise mitigation for public open spaces by considering them as noise sensitive Precedence in other states as well as Victoria for construction noise. Practice Note 61 Partial agreement from Mr Munro 3 (B) Consideration of noise mitigation for residences on Millers Rd Likely adverse noise impacts Agreement in-general from Vicroads

17 Conclave Report Page 17 MATTERS OF DISAGREEMENT
ITEM RECOMMENDATION COMMENT 5 Definition of when and at how many locations operational compliance noise monitoring should be undertaken Agreement from Mr Monro 10 Recommendation of annual testing of ventilation system Agreement from Mr Zerbst 11 New EPR for Independent Auditors Reports to be made public Transparency for community whilst allowing review/interpretation of raw data by professionals Mr Stead believes this is beyond the scope of this conclave