1 City Council March 18, 2014

2 19th Street Sidewalk

3 Project Update Presentation given to Council on September 17, 2013
Agreed to proceed with design for sidewalk on south side of 19th Street Crosswalks across 19th St. Brown Street Bryant Blvd. School Zone

4 19th Street Sidewalks - Challenges
Rights-of-Way South side has approximately 2’ of ROW 10 feet of ROW appropriate for a 5-foot-wide sidewalk

5 19th Street Sidewalks - Challenges
Power Poles Signs Trees

6 19th Street Sidewalks - Challenges
Fences Mailboxes

7 19th Street Sidewalks - Challenges
Also: planters, broken sidewalk, posts, guy wires, landscaping, driveways, etc.

8 19th Street Sidewalks - Cost
Basic Cost R-O-W Constructability Contingency General Cost Estimate South $94,500 $5,300 $23,600 10% $136,000 Notes: Estimated lengths: north side = 2,259 linear feet; south side = 2,332 linear feet Basic Cost = basic cost of a 5’ sidewalk on unobstructed land with 8 curb ramps R-O-W cost based on $23,100/acre (north) and $19,600/acre (south) average land values from TGC Appraisal District Constructability costs as percentages of basic cost, estimated based on type and number of obstructions; (100% - north, 25% - south)