Objective Provide enough wind generation to supply 15% of Rhode Island’s native demand from wind powered generation in Rhode Island, for Rhode Island consumers.

Similar presentations


Presentation on theme: "Objective Provide enough wind generation to supply 15% of Rhode Island’s native demand from wind powered generation in Rhode Island, for Rhode Island consumers."— Presentation transcript:

1

2 Objective Provide enough wind generation to supply 15% of Rhode Island’s native demand from wind powered generation in Rhode Island, for Rhode Island consumers

3 What does that mean? Native demand = approx. 1,000 MW 1,000 MW X 15% = 150 MW Assume 50% efficiency 150 MW / 50% = 300 MW installed capacity

4 Anywhere in Rhode Island
Blank slate Anywhere in Rhode Island Onshore Near Shore Offshore Single generators Groups of generators One or more wind farms

5 Site selection criteria
Technically feasible Financially feasible Permittable Sites force-ranked based on cost

6 Business Model To be determined Under consideration: Developer Rhode Island Power Authority Buyers’ Cooperative

7 Process Solicitation for Site Selection Study Decide on business model RFP for construction