Team Mio.

Similar presentations


Presentation on theme: "Team Mio."— Presentation transcript:

1 Team Mio

2 Project: Solid-State Thermostat for Peltier Beverage Temperature Control
Team Members Kristian Liwanag Gregory Brady Adrienne Suñer Jackie Floyd Faculty Advisor Dr. Peter Osterberg Industry Representative Steve Westdal, Insitu, Inc. Client Sarah Anderson, Owner, Anna Bananas Cafe

3 Outline Project Refresher Design Process Accomplishments Concerns
Plans

4 Project Refresher Double-insulated Off-the shelf

5 Project Refresher (Hysteresis)
Heat Off Heat Off 55°C 52°C Heat 25°C Cool 8°C Cool Off 5°C Off Cool 2°C

6 Top Level Block Diagram
Adrienne – thermocouple, ADC Thermocouple received Initial ADC design complete Testing design Kristian – MOSIS; includes the clock Initial MOSIS EDF files complete Greg – BCD-to-7 segment decoder, peltier device Decoder received Peltier received and tested Jackie – BJT switch Initial BJT switch design complete

7 Cup with Thermocouple

8 Top Level Block Diagram
Adrienne – thermocouple, ADC Thermocouple received Initial ADC design complete Testing design Kristian – MOSIS; includes the clock Initial MOSIS EDF files complete Greg – BCD-to-7 segment decoder, peltier device Decoder received Peltier received and tested Jackie – BJT switch Initial BJT switch design complete

9 Op Amps, ADC, EEPROM

10 Top Level Block Diagram
Adrienne – thermocouple, ADC Thermocouple received Initial ADC design complete Testing design Kristian – MOSIS; includes the clock Initial MOSIS EDF files complete Greg – BCD-to-7 segment decoder, peltier device Decoder received Peltier received and tested Jackie – BJT switch Initial BJT switch design complete

11 MOSIS IC Design

12 Top Level Block Diagram
Adrienne – thermocouple, ADC Thermocouple received Initial ADC design complete Testing design Kristian – MOSIS; includes the clock Initial MOSIS EDF files complete Greg – BCD-to-7 segment decoder, peltier device Decoder received Peltier received and tested Jackie – BJT switch Initial BJT switch design complete

13 BJT Switch and Peltier Circuit

14 Top Level Block Diagram
Adrienne – thermocouple, ADC Thermocouple received Initial ADC design complete Testing design Kristian – MOSIS; includes the clock Initial MOSIS EDF files complete Greg – BCD-to-7 segment decoder, peltier device Decoder received Peltier received and tested Jackie – BJT switch Initial BJT switch design complete

15 LED Displays

16 Design Process

17 Milestones Status Description Due Date Completion Date Completed
Characterization of Thermocouple, ADC, Peltier Device, and BJT Switches 11/12/2012 01/24/2013 Remaining Project Components Ordered and received 01/13/2013 Macro-model Built 01/25/2013 In Progress January Program Review - Accomplishments since last PR According to Formal Milestones Functional Specification v1.0 approved Top Level MOSIS Block Diagram completed Component selection completed with parts ordered; thermocouple, peltier, 7-segment displays, BCD decoder received and tested Initial MOSIS design complete Milestones for November Continue working with Fatima Villatoro to complete project business assessment Finish Design Document Finalize MOSIS design Order all remaining parts

18 Accomplishments Macro-model built Mug built with thermocouple
555 timer characterized

19 Cooling Demonstration
Macro-model (Demo) Cooling Demonstration

20 Concerns Heat dissipation on the BJT circuit

21 Plans Debug macro-model Finish programming the EEPROM
Construct the user interface Construct circuitry casing and base contents

22 Questions? Gregory Brady (Spring Semester Team Lead / Peltier/Arduino)
Kristian Liwanag (Fall Semester Team Lead / MOSIS / 555 timer) Adrienne Suñer (Treasurer / Thermocouple / ADC / Cup) Jackie Floyd (Secretary / BJT Switches / Base)