1 Public Works Planning and Design Division
City of Bowling Green Public Works Project Review Board (PRB) FY07 Capital Project Execution 03 November 2006 Public Works Planning and Design Division

2 Introduction Introduce Staff Project Overview Total Projects: 34
Carry Over Projects: 11 Active Projects: 25 Pending Projects: 9 Budget Overview Project Budget Total: $23.7 M New Project Budget: $15.2 M

3 Distribution of Project Types

4 Distribution of Project Funding

5 Current Projects Maintenance Projects ($2.9 M)
FY 06 Street Resurfacing FY 07 Street Resurfacing FY 07 Alley Overlay FY 07 Sidewalk Curb and Gutter Parker Bennett Street Rehabilitation Road Construction ($8.9 M) Ken Bale Blvd. 14th Avenue Realignment Lee Square Fields/Patton Connector Downtown Signal Project Shive Lane extension Broadway Curve Realignment Old Morgantown Road (Prelim. Design) Modern Way Storm Water Projects ($400 K) FY 06 Storm Water Quality FY 07 Storm Water Quality FY 06 BY CIP FY 07 BY CIP Facilities ($11 M) Parks and Recreation Rolland Skate Park Hobson House Roof Greenwood Fire Station Fire Expansion (Headquarters) Fire Expansion (Airport) Airport Fire Station Force Main Greenways ($1.5 M) Kereiakes Greenway Riverfront Phase III Boatlanding Trail Cemetery Road (Hays to Winfield) 31-W Bypass (Natcher to State) Parker Bennett Hobson Grove Lost River Jennings Creek (Creekwood)

6 Maintenance Projects

7 FY06 Street Resurfacing Project
Project Description: Asphalt overlay of approximately 17 miles of various City-maintained streets Project Manager: Dan Chaney Schedule: Complete Start: July 05 Finish: November 06 Status: Construction (100% complete) Budget: $842,175 (Construction budget)

8 FY07 Street Resurfacing Project
Project Description: Asphalt overlay of approximately 14 miles of various City-maintained streets & approximately 3 miles of alleys Project Manager: Joe Webb/ Dan Chaney Schedule: On schedule Start: July 06 Finish: July 07 Status: Bidding (100% complete), Award (50% complete) Budget: $1,192,000 (Construction budget)

9 FY07 Alley Overlay Project Description: This project is to overlay city-maintained alleys. Approximately 3 miles of alleys have been identified for this project. Project Manager: Joe Webb/ Dan Chaney Schedule: On schedule Start: July 06 Finish: July 07 Status: Bidding (100% complete), Award (50% complete) Budget: $100,000 (Construction budget)

10 FY07 Sidewalk, Curb & Gutter Reconstruction
Project Description: Reconstruction of sidewalk, curb & gutter along City-maintained street(s). Locations are currently being compiled and reviewed for viability. Project Manager: Dan Chaney/Joe Webb Schedule: On schedule Start: August 06 Finish: July 07 Status: Sidewalk Assessment (100% complete), Design (35% complete) Budget: $100,000 (Construction budget)

11 FY07 Sidewalk Program Project Description: Program to construct new sidewalk in various locations. Project Manager: Dan Chaney/Joe Webb Schedule: On schedule Start: August 06 Finish: July 07 Status: Policy development (50% complete) Budget: $200,000 (Construction budget)

12 Parker-Bennett Area Street Reconstruction
Project Description: Rehabilitation of concrete pavement in the Parker-Bennett neighborhood. Project Manager: Kyle Hunt/Dan Chaney Schedule: On schedule Status: Application for funding approved; Design (33% complete) Start: July 06 Finish: July 07 Budget: $500,000 (Construction budget)

13 Road Projects

14 Ken Bale Boulevard Construction
Project Description: Construction of approximately 1 mile of 5-lane road connecting Scottsville Road and Shive Lane. Project Manager: Derek Gray Schedule: Punch list completion underway. Status: Construction (99.5% complete) Start: July 04 Finish: November 06 Budget: $1,547,850 (Design and construction budget) Issues: Pending completion of punch list item (final payment pending completion).

15 14th Avenue Realignment Project Description: Realignment of 14th Avenue from College Street to Kentucky Street. Project Manager: Dan Chaney Schedule: Behind schedule (three months) Start: May 06 Finish: December 06 Status: Construction (45% Complete) Budget: $193,500 (Construction budget) Issues: WKU utility work and weather delays have pushed the project behind schedule by 3 months. Additionally, property issues with Steve Downey are being addressed. Schedule Recovery: WKU enacted liquidated damages.

16 Lee Square Subdivision
Project Description: Construction of infrastructure at Lee Square (block between 2nd & 3rd Avenues and College & State Streets) Project Manager: Dan Chaney Schedule: On schedule Start: July 06 Finish: December 06 Status: Construction (50% complete) Budget: $269,750 (Construction budget) Issues: Change Order issues may impact construction deadline. Schedule Recovery: We will include any delays in a change order schedule extension on an as-needed basis. Currently, the project is 2 weeks behind schedule.

17 Fields Drive Extension
Project Description: Fields Drive Extension is a 0.34 mi. project to connect Navajo Way to Campbell Ln., providing better circulation in the area and reducing traffic through the Shawnee neighborhood. Project Manager: Kyle Hunt/Derek Gray Schedule: On Schedule Start: August Finish: January 08 Status: Phase I Construction (90% Complete) Phase II Design (50% Complete) Budget: $117,500 Phase I (Design & construction) $382,500 Phase II (Design & construction)

18 Downtown Signals Project Description: Project to replace and upgrade antiquated hardware, replace existing traffic markings and link all the new controllers via fiber optic lines connected to a master controller order to improve traffic flow through 19 downtown intersections. Project Manager: Mark Absher Schedule: Behind Schedule – Design (six weeks) Start: May 06 Finish: December 07 Status: Design (90% Complete) Budget: $1,874,000 (Construction) Issues: Schedule has been delayed for additional value engineering review by staff.

19 Shive Lane Extension Project Description: Widening and extension of Shive Lane from Ken Bale Blvd. to Lovers Lane at Searcy Way. Project Manager: Kyle Hunt/Derek Gray Schedule: On Schedule Start: June Finish: January 09 Status: Design (80% Complete) Budget: $3,500,000 (Construction)

20 Broadway Curve Realignment
Project Description: Design and construction of a portion of the Broadway Avenue curve near High Street to improve geometrics of the curve and the intersection with High Street. Project Manager: Melissa Cansler/Derek Gray Schedule: Start: October 06 Finish: September 08 Status: A/E procurement Budget: $688,000 (Design & Construction)

21 Old Morgantown Road (Preliminary Design)
Project Description: Preliminary engineering to determine necessary improvements to corridor between University Blvd. And Morgantown Road. Purpose of this project is to improve traffic flow, safety and access. Project Manager: Melissa Cansler Schedule: Start: January 07 Finish: November 07 Status: A/E procurement Budget: $90,000 (Preliminary Design) Issues: To date, discussions have taken place with Forest Park neighborhood representatives, Greenways, and other stakeholders along the corridor.

22 Modern Way Project Description: Design and construction of a portion of a connection between Modern Way and Industrial Drive to improve traffic flow. Project Manager: Jeff Lashlee; Dan Chaney Schedule: On Schedule Start: August 06 Finish: June 08 Status: Survey (100% complete), Design (90% complete) Budget: $13,300 (Design) & TBD (Construction)

23 Storm Water Projects

24 FY 06 Water Quality Projects (Hunting Creek Subdivision & Parks and Recreation)
Project Description: Rehabilitation to the existing ponds as a demonstration project to improve water quality and meet permit requirements. Project Manager: Matt Zoellner Schedule: On Schedule (Parks Facility) Start: April 06 Finish: March 07 Status: Parks Facility - Design & award (100% complete) Hunting Creek – Design (100% complete) Budget: $50,000 (Hunting Creek Pond) $50,000 (Parks and Recreation Facility) Issues: Hunting Creek project is pending neighborhood meeting

25 FY07 Stormwater Quality Program Project(s)
Project Description: Lost River Cave Wetland project includes design and construction of a wetland to treat storm water entering Lost River Cave. Project Manager: Kyle Hunt/Matt Zoellner/Tim Slattery Schedule: On Schedule Start: August 06 Finish: November 07 Status: Pending professional services RFP & contract Budget: $100,000 (Design and construction) Issues: We would like to encourage WKU, Kentucky Division of Water, and the Friends of Lost River to partner in this effort.

26 FY06 BY-CIP Project Description: Design and construction of two basins and installation of new stormwater piping to an existing basin. Project Manager: Matt Zoellner Schedule: Complete; awaiting final billing. Start: July 06 Finish: November 06 Status: Construction (90% complete) Budget: $100,000 Construction

27 FY07 BY-CIP Proposed Project
Project Description: This project includes the following project locations: 1. Hunting Creek Pond Pipe Repair, and 2. Block of 7th and 8th and Center and College. Project Manager: Matt Zoellner Schedule: On schedule Start: August 06 Finish: November 07 Status: Design (51% complete) Budget: $100,000 (Design and construction budget) Issues: Due to high cost of the Audobon/Glen Lily pump station and the downtown re-development in the Center-College Street area, we recommend Hunting Creek Pipe Repair as the FY07 BY-CIP

28 Facilities Projects

29 Parks & Recreation Community Center Expansion
Project Description: Construction of an approximately 28,000 square feet building on BG Parks and Recreation 20-acre campus; renovation of approximately 8,000 square feet of existing facility. Project Manager: Derek Gray Schedule: On schedule Start: June 05 Finish: July 08 Status: Bidding (100% complete); Construction (2% complete) Budget: $3,950,000 (Construction)

30 Roland Bland Skate Park
Project Description: Design and construction of an approximately 21,000 sq. ft. skate park. Project Manager: Matt Zoellner Schedule: Due to weather delays, the project is 1 month behind schedule. Start: August 06 Finish: December 06 Status: Construction (30% complete) Budget: $800,000 (Construction) Issues: Due to weather and the uniqueness of this type of project, project is behind schedule. Schedule Recovery: Contract has been extended by 45 days.

31 Hobson House Roof Project Description: Replacement of copper roof with weather-tight metal system Project Manager: Dan Chaney Schedule: On schedule Start: September 06 Finish: December 06 Status: Construction (75% complete) Budget: $98,730 (Construction)

32 Greenwood Fire Station
Project Description: Project to design and construct a 17,000 s.f. fire station in the south Scottsville Road area. Project Manager: Derek Gray Schedule: On schedule Start: January 07 Finish: April 09 Status: Pending A/E procurement Budget: $2,584,800 (Design and Construction)

33 Headquarters Fire Station Expansion
Project Description: Project to design and construct a 10,000 s.f. expansion to the existing Headquarters Fire Station including administration. Project Manager: Derek Gray Schedule: On schedule Start: January 07 Finish: June 08 Status: Pending A/E procurement Budget: $2,872,000 (Design and construction)

34 Airport Fire Station Expansion
Project Description: Project to design and construct a 3,500 s.f. expansion to the existing Airport Fire Station. Project Manager: Derek Gray Schedule: On schedule Start: January 07 Finish: June 08 Status: Pending A/E procurement Budget: $538,500 (Design and construction)

35 Greenway Projects

36 Kereiakes Greenway Project Description: Construction of a multi-use path from Kereiakes Park to 31W By-Pass Project Manager: Dan Chaney Schedule: Completed October 2006 Start: August 05 Finish: August 06 Status: Construction (100% complete) Budget: $264,471 (Construction budget) Issues: Winter delay, property line encroachments Schedule Recovery: Schedule adjusted to offset delays; property line issues resolved

37 Boat Landing Trail Greenway
Project Description: Construction of a multi-use path from Boat Landing Park to KY-185 Project Manager: Dan Chaney Schedule: Completed October 2006 Start: August 05 Finish: October 06 Status: Construction (100% complete) Budget: $44,720 (Construction budget)

38 Riverfront Park Phase III Greenway
Project Description: Construction of a multi-use path servicing Riverfront Park Project Manager: Dan Chaney Schedule: Completed October 2006 Start: August 05 Finish: December 06 Status: Construction (100% complete) Budget: $305,816 (Construction budget)

39 Creekwood Greenway Project Description: Construction of a multi-use path along Jennings Creek in the Creekwood Subdivision vicinity Project Manager: Dan Chaney Schedule: On schedule. Start: August 06 Finish: April 07 Status: Design (100% complete) Budget: $35,000 (Construction budget)