1 WORLD BANK Evaluation Process (Goods/Works)

2 BID EVALUATION Objective Other factors
Secure goods/services at most economical cost Price only one factor Other factors Commercial Time of delivery/completion Terms of payment Terms of guarantee

3 BID EVALUATION Other factors (cont’d) Criteria Technical
Technical merits Operating cost Maintenance cost Efficiency Resale value Criteria Shall be stated in bid documents Ideally all factors quantified in monetary terms

4 BID EVALUATION Bid opening Examination Cost comparison
Price Price and commercial Price, commercial and technical Lowest evaluated bid Post qualification Award recommendation Evaluation report No objection

5 BID OPENING Public opening Minutes to be recorded
Rationale Minutes to be recorded Single stage - single envelope Bid form Technical data Bid price schedule Bid security

6 PRELIMINARY EXAMINATION
Clarification Permissible and warranted Cannot change substance of bid or price Confidentiality Important Examination of bids Is bid complete? Signed? Is bid security attached? Major deviations from bid conditions Computational Errors Figures/Words Unit rate/Total Misplacement of decimal point

7 PRELIMINARY EXAMINATION
Technical Assessment - substantial responsiveness Detailed evaluation only for substantially responsive bids

8 DEVIATIONS Unacceptable Late bid Unsigned bid Inadequate bid security
Different prequalified firms and bidders Different price conditions Unacceptable alternative, timing and phasing Unacceptable sub-contracting Qualification of arbitration rules Unacceptable applicable law

9 DEVIATIONS For Consideration Different payment terms
Alternative methods/bids Minor omissions Limitation of liabilities Liquidated damages

10 COMPARISON OF BIDS CONVERSION TO COMMON CURRENCY
Object To determine lowest evaluated bid on date specified Bid price Convert into amounts payable in each currency Common currency Borrower’s or any other currency Exchange rates Official source such as central bank As on Any specified date not earlier than 4 weeks prior to bid closing nor later than original date for expiry of bid validity Date to be clearly specified in bid documents

11 EXAMPLE: CURRENCY CONVERSION (EQUIPMENT)
A B C 1. Evaluated Price US$6,300 DM15, Ll3, FF15,000 Converted to local currency pesos: At exchange rate on date of bid opening , , ,000 Ranking 3. At exchange rate on date of decision , , ,800 Ranking At exchange rate on date of , , ,000 expiry of bid validity Ranking At exchange rate on actual date of delivery , , , which is 6 months after expiry of original validity period Ranking

12 COMMERCIAL FEATURES Price Price adjustment over contract period
Adjust basic price for features, options, etc. To make bid prices comparable Price adjustment over contract period Ignore Delivery point Add local transportation

13 COMMERCIAL FEATURES Time of delivery Warranty Payment terms
Evaluate loss or gain by late or early delivery Warranty Evaluate variation Payment terms Evaluate variations at specified interest/discount rate

14 BID EVALUATION FOR URBAN BUSES
A B DOMESTIC BID FOREIGN BID PRICE EX-WORKS/FOB PES900, DM100,000 OCEAN FREIGHT AND INSURANCE DM5,625 PRICE EXWORKS/CIF PORT OF ENTRY PES900, DM105,625 PRICE EXWORKS/CIF CONVERTED TO , , COMMON CURRENCY (USD) INLAND TRANSPORTATION ,500 EVALUATED COST DELIVERED AT , , SITE

15 BID EVALUATION FOR URBAN BUSES (CONTD.)
A B DOMESTIC BID FOREIGN BID PENALTY FOR DEVIATION IN PAYMENT TERMS DELIVER/COMPLETION EVALUATION , WARRANTY TOTAL EVALUATED COST , ,350 RANKING

16 EVALUATION CRITERIA TECHNICAL FEATURES
Operating cost Fuel Training Maintenance cost Standardization Resale value/depreciated cost Life cycle cost

17 BID EVALUATION USING LIFE CYCLE COSTING FOR PROCUREMENT OF 100 HIGHWAY TRUCKS
Relevant part of the bid evaluation clauses in the bidding documents The evaluation and comparison of bids shall be based on the life cycle cost for the vehicles during the first 6 years, worked out in the following manner 1. Initial price CIF price quoted for trucks offered from abroad Ex-works/ex-showroom price for vehicles offered from within the country 2. Operating and maintenance costs Fuel costs shall be computed on the basis of 100,000 km of operation per year at a fuel price of 0.80 US$ per liter, discounted to net present value at a discount rate of 10 percent

18 BID EVALUATION USING LIFE CYCLE COSTING FOR PROCUREMENT OF 100 HIGHWAY TRUCKS
Spare parts cost shall be based on 100,000 km per year of operation, based on the guaranteed figures provided by the bidder for each year, discounted to net present values at a discount rate of 10 percent. If guaranteed figures are not provided purchaser may use estimated figures. 3. Depreciated cost Purchaser shall estimate the depreciated cost of the vehicle offered based on the guaranteed life prior to the first major overhaul, or based on past experience, but in no case more than 8 years 4. Bidders shall furnish all the data required for the above computations.

19 BID EVALUATION USING LIFE CYCLE COSTING 100 HIGHWAY TRUCKS
A B USD USD 1. INITIAL COSTS BID PRICE EX-WORKS/CIF EVALUATION , ,000 ADJUSTMENT FOR DELIVERY SCHEDULE , EVALUATION ADJUSTMENT FOR VARIATION , IN PAYMENT TERMS TOTAL , ,000 2. OPERATING AND MAINTENANCE COSTS: FUEL - GUARANTEED COST FOR EACH YEAR (8,000) (6,000) NPV FOR 6 YEARS , ,130 SPARES - GUARANTEED COST (AVERAGE) (5,000) (4,000) NPV FOR 6 YEARS , ,420 TOTAL , ,550

20 BID EVALUATION USING LIFE CYCLE COSTING 100 HIGHWAY TRUCKS (CONTD.)
A B USD USD 3. DEPRECIATED VALUE LIFE (6 YEARS) (6 YEARS) DEPRECIATED VALUE ,500 4. TOTAL LIFE CYCLE COST , ,050 RANKING

21 BID EVALUATION WORKS Comparison of bids
Conversion to single currency, after excluding provisional sums, contingency Adjust value of benefits gained or lost for completion period Adjust for “acceptable” quantifiable variations

22 EXAMPLE: CURRENCY CONVERSION (CIVIL WORKS)
BID A BID B 1. BID AS SUBMITTED BID PRICE IN LOCAL CURRENCY, PESOS P9,000, P10,000,000 FOREIGN CURRENCY COMPONENT AT EXCHANGE RATE 28 DAYS PRIOR TO CLOSING 33.3% IN US$ % IN DM 2. EXCHANGE RATES AS OF 28 DAYS PRIOR TO BID CLOSING US$1=P DM1=P50 ON DATE OF BID CLOSING US$1=P DM1=P55 ON DATE OF DECISION US$1=P DM1=P55 3. LOCAL CURRENCY COMPONENT P6,000, P6,000,000

23 EXAMPLE: CURRENCY CONVERSION (CIVIL WORKS)
BID A BID B 4. FOREIGN CURRENCY COMPONET US$30, DM80,000 FOREIGN CURRENCY COMPONENT CONVERTED TO LOCAL CURRENCY EQUIVALENT A. 28 DAYS PRIOR TO BID CLOSING P3,000, P4,000, B. B. ON DATE OF BID CLOSING P3,600, P4,400, C. C. ON DATE OF DECISION P4,500, P4,400,000 TOTAL BID PRICE A. AS OF 28 DAYS PRIOR TO BID CLOSING P9,000, P10,000,000 B. ON DATE OF BID CLOSING P9,600, P10,400,000 C. ON DATE OF DECISION P10,500, P10,400,000

24 EXAMPLE: BID EVALUATION FOR CONSTRUCTION OF HOSPITAL
A B 1. PRICE ,000, ,650, (IN LOCAL CURRENCY EQUIVALENT) 2. ADJUSTMENT FOR COMPLETION TIME , (AT 20% ANNUAL RATE OF RETURN) 3. ADJUSTMENT FOR 5% CEILING FOR , LIQUIDATED DAMAGE 4. ADJUSTMENT FOR PARKING LOT , OMITTED (FROM ORIGINAL ESTIMATE) 5. ADJUSTMENT FOR 20% OF , MOBILIZATION ADVANCES REQUESTED AS AGAINST 10% STIPULATED (AT 12% INTEREST RATE) TOTAL ,702, ,215,000 RANKING

25 DOMESTIC PREFERENCE Goods Civil works
Only to locally manufactured goods which contain labor, raw materials and components accounting for at least more than 30% of the EXW price Production facility to be used must be engaged in production of such goods at time of bid submission Applicable import tariff or 15% of CIF whichever is less Available for all borrowers Civil works Only to domestic contractors majority owned by nationals Domestic contractor must not subcontract more than 10% of the contract price excluding provisional sum to foreign contractors Must be register in the borrower country Margin 7-1/2% No domestic preference to joint venture of domestic and foreign contractor Only for borrowers below US$755 per capita GNP (Year 2000)

26 DOMESTIC PREFERENCE (ILLUSTRATIONS) CASE 1 - PROCUREMENT OF VEHICLES
A1 B1 C1 C2 C3 PRICE EX-WORKS/CIF , , , , ,000 STEP 1 LOWEST BID IN EACH , , ,500 GROUP RANKING AWARD B1

27 DOMESTIC PREFERENCE (ILLUSTRATIONS) CASE 2 - PROCUREMENT OF VEHICLES
A1 B1 C1 C2 C3 PRICE EX-WORKS/CIF , , , , ,000 STEP 1 Lowest bid in each Group , , ,500 RANKING Since LEB in group C STEP 2 Lowest in group A and , , , , ,000 All in group C bids Domestic Preference Customs Duty or 15% of CIF For group C

28 DOMESTIC PREFERENCE (ILLUSTRATIONS) CASE 2 - PROCUREMENT OF VEHICLES
A1 B1 C1 C2 C3 Customs Duty 30% of CIF , , ,800 so 15% of CIF Total for Comparison , , , ,800 RANKING 1 Award A1

29 DOMESTIC PREFERENCE (ILLUSTRATIONS) CASE 3 - 1 PROCUREMENT OF VEHICLES
A1 B1 C1 C2 C3 PRICE EX-WORKS/CIF , , , , ,000 NVP of operating costs , ,000 5,000 8, ,500 Total Evaluated Cost , , , , ,500 STEP 1 Lowest bid in each Group , , ,000 RANKING STEP 2 Group A and , , , ,500 All in group C

30 DOMESTIC PREFERENCE (ILLUSTRATIONS) CASE 3 – 1 PROCUREMENT OF VEHICLES
A1 B1 C1 C2 C3 Domestic Preference – Customs Duty 30%, so 15% of CIF , , ,350 Total for Comparison , , , ,850 RANKING Since the lowest is from Group C, go back to Step 1 (To ascertain the lowest among C without domestic preference Margin Award C1

31 DOMESTIC PREFERENCE (ILLUSTRATIONS) CASE 3 – 2 PROCUREMENT OF VEHICLES

32 DOMESTIC PREFERENCE (ILLUSTRATIONS) CASE 3 – 2 PROCUREMENT OF VEHICLES

33 POSTQUALIFICATION Only for selected bidder Criteria (goods) Capacity
Technical capability Product reputation Financial resources Parts and service Past performance

34 POSTQUALIFICATION Criteria (works)
Past experience (size/complexity) Personnel resources Equipment resources Financial capacity Litigation/arbitration history If there was prequalification, confirm that bidder’s status is substantially the same as at prequalification

35 BID EVALUATION REPORT Content Reason for rejecting each bid
Received after bid opening Incomplete Non-Responsive Commercial responsiveness Delivery Completion date Payment terms Warranty

36 BID EVALUATION REPORT Qualifications/alternatives Currency conversion
Errors (arithmetic) Currency conversion Include publication official exchange rates Technical comparison Each criteria listed and compared (attach table) Responsive bid comparison Selection of lowest evaluated bid Postqualification of selected firm Recommendation for contract award

37 AWARD CONTRACT Selected bidder should not be required To reduce price
To undertake work not specified in bidding document, or To modify the bid