Download presentation
Presentation is loading. Please wait.
1
ENERGY STAR Qualified Homes
WATER MANAGEMENT SYSTEM BUILDER CHECKLIST 1, 2, 3 Footnotes: 1. The specifications in this checklist are designed to help improve moisture control in new homes compared with homes built to minimum code. However, these features alone cannot prevent all moisture problems. For example, leaky pipes or overflowing sinks or baths can lead to moisture issues and negatively impact the performance of this checklist’s specified features. 2. This checklist shall be provided by the Rater to the Builder who shall complete the checklist. Upon completion, the Builder shall return the checklist to the Rater for review. If desired by the Builder, the Rater may verify any item on this checklist. When this occurs, the Rater shall check the box of the verified items in the Rater Verified column. The Rater is only responsible for ensuring that the Builder has completed the Builder checklist in its entirety and for the items that are checked in the Rater Verified column (if any). The Rater is not responsible for assessing the accuracy of the field verifications for items in this checklist that are not checked in the Rater Verified column. Instead, it is the builder’s exclusive responsibility to ensure the design and installation comply with the Builder checklist. 3. A completed and signed Indoor airPLUS Verification Checklist may be submitted in lieu of the Water Management System Builder checklist. For more information, see
2
TABLE OF CONTENTS Section 1. Water-Managed Site and Foundation Section 2. Water-Managed Wall Assembly Section 3. Water-Managed Roof Assembly Section 4. Water-managed Building Materials
3
SECTION 1. WATER-MANAGED SITE AND FOUNDATION
1.1. Patio slabs, porch slabs, walks, and driveways sloped ≥ 0.25 in. per ft. away from home to edge of surface or 10 ft., whichever is less Back-fill has been tamped and final grade sloped ≥ 0.5 in. per ft. away from home for ≥ 10 ft. See footnote for alternatives 4 Critical Point: To prevent bulk water from entering the home. Summary:
4
SECTION 1. WATER-MANAGED SITE AND FOUNDATION
1.3. Capillary break beneath all slabs (e.g., slab on grade, basement slab) except crawlspace slabs using either: ≥ 6 mil polyethylene sheeting, lapped 6-12 in., or ≥ 1” extruded polystyrene insulation with taped joints. 5 Critical Point: To prevent bulk water from entering the home. Summary:
5
SECTION 1. WATER-MANAGED SITE AND FOUNDATION
1.4 Capillary break at all crawlspace floors using > 6 mil polyethylene sheeting, lapped 6-12 in., and installed using one of the following three options: 5 Placed beneath a concrete slab; OR, Lapped up each wall or pier and fastened with furring strips or equivalent; OR, Secured in the ground at the perimeter using stakes.
6
SECTION 1. WATER-MANAGED SITE AND FOUNDATION
1.5 Exterior surface of below-grade walls finished as follows: For poured concrete, concrete masonry, and insulated concrete forms, finish with damp-proofing coating For wood framed walls, finish with polyethylene and adhesive or other equivalent waterproofing 1.6 Class 1 vapor retarders not installed on the interior side of air permeable insulation in exterior below-grade walls 6
7
SECTION 1. WATER-MANAGED SITE AND FOUNDATION
1.7 Sump pump covers mechanically attached with full gasket seal or equivalent 1.8 Drain tile surrounded with clean gravel and fabric filter 7
8
SECTION 1. WATER-MANAGED SITE AND FOUNDATION
1.1. Patio slabs, porch slabs, walks, and driveways sloped ≥ 0.25 in. per ft. away from home to edge of surface or 10 ft., whichever is less Back-fill has been tamped and final grade sloped ≥ 0.5 in. per ft. away from home for ≥ 10 ft. See footnote for alternatives 4 Critical Point: To prevent water on the slab from draining toward the home and causing potential moisture issues. Summary:
9
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 4. Where setbacks limit space to less than 10 ft., swales or drains designed to carry water from foundation shall be provided. Backfill tamping is not required if proper drainage can be achieved using non-settling compact soils, as determined by a certified hydrologist, soil scientist, or engineer.
10
1.1- 2 Patio slabs, porch slabs, walks, and driveways sloped ≥ 0.25 in. per ft. away from home to edge of surface or 10 ft., whichever is less 4 A / B Critical Point: Moisture Flow — Bulk water is carried away from the house by properly sloping the patio slabs, walks, and driveways Picture Description: Bad- The driveway is slopped toward the home and will potentially cause bulk moisture issues. Good- The driveway is slopped away from the home reducing the chance of bulk moisture issues. Construction Phase: Varies Inspection: Final Inspection Driveway is not sloped away from the house. Driveway is installed to slope water away from the house. Water Management System Builder Checklist
11
1.1- 2 Back-fill has been tamped and final grade sloped ≥ 0.5 in. per ft. away from home for ≥ 10 ft. See footnote for alternatives 4 E Critical Point: Moisture Flow — Picture Description: Construction Phase: Inspection: The final grade does not slope away from the house. The final grade slopes away from the house.
12
1.1- 2 Back-fill has been tamped and final grade sloped ≥ 0.5 in. per ft. away from home for ≥ 10 ft. See footnote for alternatives 4 C/G Critical Point: Moisture Flow — Picture Description: Construction Phase: Inspection: BAD PIC OF IMPROPERLY INSTALLED OR NO SWALE GOOD PIC OF PROPERLY INSTALLED SWALE
13
1.1- 2 Patio slabs, porch slabs, walks, and driveways sloped ≥ 0.25 in. per ft. away from home to edge of surface or 10 ft., whichever is less 4 D/H Critical Point: Moisture Flow — Bulk water is carried away from the house by drains Picture Description: Bad- The drain is located above the substrate and thus water will have to pool before the drain can function. Water pooling around the foundation can cause moisture issues. Good- The drain is properly pitched to carry bulk water away from the home. Construction Phase: Varies Inspection: Final Inspection Drain pipe has been cut and foundation penetration has not been properly sealed. The drain slopes away from the foundation and terminates at the proper distance.
14
SECTION 1. WATER-MANAGED SITE AND FOUNDATION
1.3. Capillary break beneath all slabs (e.g., slab on grade, basement slab) except crawlspace slabs using either: ≥ 6 mil polyethylene sheeting, lapped 6-12 in., or ≥ 1” extruded polystyrene insulation with taped joints. 5 Critical Point: A capillary break (stops the movement of water up through the slab) should be used to prevent moisture from entering the concrete slab. Summary: Water can move up through concrete via capillary action. By providing a capillary break it prevents moisture from entering the home.
15
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 5. Polyethylene sheeting is not required in Dry (B) climates as shown in 2009 IECC Figure and Table 301.1, except in U.S. EPA Zone 1 Radon areas. Polyethylene sheeting is also not required for raised pier foundations with no walls. In areas with free-draining soils, identified as Group 1 in the IRC by a certified hydrologist, soil scientist, or engineer through a site visit, a gravel layer or geotextile matting is not required. EPA recommends, but does not require, radon-resistant features for homes built in EPA Radon Zones 1, 2 and 3. For more information, see
16
1.3 Capillary break beneath all slabs (e.g., slab on grade, basement slab) except crawlspace slabs using either: ≥ 6 mil polyethylene sheeting, lapped 6-12 in., or ≥ 1” extruded polystyrene insulation with taped joints. 5 B Critical Point: Moisture Flow — Polyethylene sheeting effectively stops water from wicking into the slab from underneath and ½ inch clean aggregate acts as a drainage plane. Picture Description: BAD- No polyethylene sheeting is present under the slab and thus water can penetrate the slab. GOOD- Polyethylene sheeting is present under the slab and will act as a capillary break. In addition, there is a drainage plane formed by the ½ inch gravel to help prevent moisture under the slab. Construction Phase: Foundation Inspection: Pre-Framing There is no polyethylene sheeting installed between the ground and the slab. There is polyethylene sheeting installed to provide a capillary break between the ground and slab.
17
1.3 Capillary break beneath all slabs (e.g., slab on grade, basement slab) except crawlspace slabs using either: ≥ 6 mil polyethylene sheeting, lapped 6-12 in., or ≥ 1” extruded polystyrene insulation with taped joints. 5 C Critical Point: Moisture Flow — Extruded polystyrene insulation with taped joints effectively stops water from wicking into the slab from underneath and ½ inch clean aggregate acts as a drainage plane. Picture Description: BAD- Extruded polystyrene insulation is used around the perimeter as slab insulation. However, this extruded polystyrene insulation will not act as a capillary break because it is not under the entire slab and the joints are not properly taped. GOOD- Construction Phase: Foundation Inspection: Pre-Framing The seams of the rigid insulation are not taped and it will not provide a complete capillary break. GOOD PIC OF PROPERLY INSTALLED RIGID INSULATION
18
SECTION 1. WATER-MANAGED SITE AND FOUNDATION
1.4 Capillary break at all crawlspace floors using > 6 mil polyethylene sheeting, lapped 6-12 in., and installed using one of the following three options: 5 Placed beneath a concrete slab; OR, Lapped up each wall or pier and fastened with furring strips or equivalent; OR, Secured in the ground at the perimeter using stakes. Critical Point: A capillary break (stops the movement of water up into the crawlspace) should be used to prevent moisture from entering the crawlspace. Summary: Water can move up through the ground via capillary action and enter the crawlspace. By providing a capillary break it helps manage moisture related issues in the crawl space.
19
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 5. Polyethylene sheeting is not required in Dry (B) climates as shown in 2009 IECC Figure and Table 301.1, except in U.S. EPA Zone 1 Radon areas. Polyethylene sheeting is also not required for raised pier foundations with no walls. In areas with free-draining soils, identified as Group 1 in the IRC by a certified hydrologist, soil scientist, or engineer through a site visit, a gravel layer or geotextile matting is not required. EPA recommends, but does not require, radon-resistant features for homes built in EPA Radon Zones 1, 2 and 3. For more information, see
20
1.4.1 Placed beneath a concrete slab. A
Critical Point: Moisture Flow — The concrete slab over 6 mil polyethylene will help control moisture levels in the crawl space Picture Description: BAD- There is no capillary break between the ground and the crawlspace. This can lead to elevated moisture levels in the crawl space. GOOD- The polyethylene will act as a capillary break and help control the moisture in the crawl space. Construction Phase: Foundation Inspection: Final Inspection There is no polyethylene sheeting installed in the crawlspace. There is 6 mil polyethylene sheeting installed and sealed in the crawlspace.
21
1.4.1 Placed beneath a concrete slab. B
Critical Point: Moisture Flow — The polyethylene will help control moisture levels in the crawl space Picture Description: BAD- The polyethylene is not covering 100% of the crawlspace and thus there is not a complete capillary break between the ground and the slab. This can lead to elevated moisture levels in the crawl space. GOOD- Construction Phase: Foundation Inspection: Final Inspection There is no polyethylene sheeting installed in the crawlspace. GOOD PIC OF POLY INSTALLED IN THE CRAWLSPACE OVERLAPPED 6-12”
22
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 5. Polyethylene sheeting is not required in Dry (B) climates as shown in 2009 IECC Figure and Table 301.1, except in U.S. EPA Zone 1 Radon areas. Polyethylene sheeting is also not required for raised pier foundations with no walls. In areas with free-draining soils, identified as Group 1 in the IRC by a certified hydrologist, soil scientist, or engineer through a site visit, a gravel layer or geotextile matting is not required. EPA recommends, but does not require, radon-resistant features for homes built in EPA Radon Zones 1, 2 and 3. For more information, see
23
1.4.2 Lapped up each wall or pier and fastened with furring strips or equivalent. B Critical Point: Moisture Flow — The polyethylene will help control moisture levels in the crawl space Picture Description: BAD- There is no capillary break between the ground and the crawlspace. This can lead to elevated moisture levels in the crawl space. GOOD- The polyethylene is properly overlapped and sealed to act as a capillary break and help control the moisture in the crawl space. Construction Phase: Toward the end of construction Inspection: Final Inspection There is no polyethylene sheeting installed in the crawlspace. There is polyethylene sheeting installed and sealed in the crawlspace.
24
1.4.2 Lapped up each wall or pier and fastened with furring strips or equivalent. C Critical Point: Moisture Flow — The polyethylene will help control moisture levels in the crawl space Picture Description: BAD- The polyethylene is not attached appropriately to the piers. Over time this means of fastening the poly can fail and lead to an incomplete capillary break between the ground and the crawl. This can lead to elevated moisture levels in the crawl space. GOOD- Construction Phase: Toward the end of construction Inspection: Final Inspection The polyethylene sheeting is not staked or attached to furring strips for mechanical support. GOOD PIC OF PROPERLY INSTALLED FURRING STRIPS
25
SECTION 1. WATER-MANAGED SITE AND FOUNDATION
1.5 Exterior surface of below-grade walls finished as follows: For poured concrete, concrete masonry, and insulated concrete forms, finish with damp-proofing coating Critical Point: Below grade walls have appropriate damp-proofing (concrete) or waterproofing (wood framed) to appropriately manage moisture. Summary: Damp-proofing or waterproofing below grade walls helps control moisture in basements/crawlspaces.
26
Critical Point: Summary: Construction Phase: Inspection:
27
1.5 Exterior surface of below-grade walls finished as follows: For poured concrete, concrete masonry, and insulated concrete forms, finish with damp-proof coating A Critical Point: Moisture Flow — Damp-proofing is appropriately installed to minimize moisture entry Picture Description: BAD- Water is not managed appropriately on this below grade wall. This is the result of improper damp-proofing of the exterior of the below grade wall. GOOD- Damp-proofing is being installed on the below-grade section of the concrete wall. Construction Phase: Foundation Inspection: Pre- Framing Inspection The below-grade concrete does not have the correct mixture to be impermeable to moisture. Below-grade concrete has been properly sealed against moisture and is now having insulation installed.
28
1.5 B BAD PIC OF CMU WALL WITHOUT PARGING
Exterior surface of below-grade walls finished as follows: For poured concrete, concrete masonry, and insulated concrete forms, finish with damp-proof coating B Critical Point: Moisture Flow — Picture Description: Construction Phase: Inspection: BAD PIC OF CMU WALL WITHOUT PARGING GOOD PIC OF CMU WALL WITH PARGING
29
1.5 Exterior surface of below-grade walls finished as follows: For poured concrete, concrete masonry, and insulated concrete forms, finish with damp-proof coating C Critical Point: Moisture Flow — Damp-proofing is appropriately installed to minimize moisture entry Picture Description: BAD- There is no damp-proofing installed on this below grade wall. This can lead to moisture issues in the crawl space. GOOD- Damp-proofing is properly installed on the below-grade section of the CMU wall. Construction Phase: Foundation Inspection: Pre- Framing Inspection The below-grade concrete walls do not have any damp-proof coating. The below-grade concrete walls have damp-proof coating.
30
1.5 Exterior surface of below-grade walls finished as follows: For poured concrete, concrete masonry, and insulated concrete forms, finish with damp-proof coating D Critical Point: Moisture Flow — Damp-proofing is appropriately installed to minimize moisture entry Picture Description: BAD- There is no damp-proofing on the below grade section of the ICF wall. GOOD- Construction Phase: Foundation Inspection: Pre- Framing Inspection The insulated concrete forms at the foundation do not have a damp-proof coating. The insulated concrete forms that are below grade have a damp-proof coating to prevent moisture seeping into the foundation.
31
SECTION 1. WATER-MANAGED SITE AND FOUNDATION
1.5 Exterior surface of below-grade walls finished as follows: For wood framed walls, finish with polyethylene and adhesive or other equivalent waterproofing Critical Point: Below grade walls have appropriate damp-proofing (concrete) or waterproofing (wood framed) to appropriately manage moisture. Summary: Damp-proofing or waterproofing below grade walls helps control moisture in basements/crawlspaces.
32
Critical Point: Summary: Construction Phase: Inspection:
33
1.5 Exterior surface of below-grade finished as follows: For wood framed walls, finish with polyethylene and adhesive or other equivalent waterproofing a Critical Point: Moisture Flow — Below grade walls have appropriate damp-proofing (concrete) or waterproofing (wood framed) to appropriately manage moisture. Picture Description: BAD- Construction Phase: Inspection: Untreated lumber has been used on a below-grade wall against masonry. GOOD PIC OF TREATED WOOD / MATERIALS ON BELOW GRADE WALL
34
1.5 b BAD PIC OF FOUNDATION WITHOUT POLY
Exterior surface of below-grade finished as follows: For wood framed walls, finish with polyethylene and adhesive or other equivalent waterproofing b Critical Point: Moisture Flow — Picture Description: Construction Phase: Inspection: BAD PIC OF FOUNDATION WITHOUT POLY GOOD PIC OF FOUNDATION WITH POLY
35
SECTION 1. WATER-MANAGED SITE AND FOUNDATION
1.6 Class 1 vapor retarders not installed on the interior side of air permeable insulation in exterior below-grade walls 6 Critical Point: Materials that are applied to the inside of exterior walls below grade must have a permeability greater than 0.1 Summary: High perm materials must be used to allow the materials to dry to the inside. On the outside they will have damp-proofing or water-proofing.
36
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 6. The 2009 IRC defines Class I vapor retarders as a material or assembly with a rating of ≤ 0.1 perm, as defined using the desiccant method with Procedure A of ASTM E 96. The following materials are typically rated at ≤ 0.1 perm and therefore shall not be used on the interior side of air permeable insulation in above-grade exterior walls in warm-humid climates or below-grade exterior walls in any climate: rubber membranes, polyethylene film, glass, aluminum foil, sheet metal, foil-faced insulating sheathings, and foil-faced non-insulating sheathings. These materials can be used on the interior side of walls if air permeable insulation is not present (e.g., foil-faced extruded polystyrene rigid insulation board adjacent to a below-grade concrete foundation wall is permitted). Note that this list is not comprehensive and other materials with a perm rating ≤ 0.1 also shall not be used. Also, if manufacturer specifications for a specific product indicate a perm rating above 0.1, then the material may be used, even if it is in this list. Also note that open-cell and closed-cell foam generally have perm ratings above this limit and may be used unless manufacturer specifications indicate a perm rating ≤ 0.1. Several exemptions to these requirements apply: a. Class I vapor retarders, such as ceramic tile, may be used at shower and tub walls; b. Class I vapor retarders, such as mirrors, may be used if they are mounted with clips or other spacers that allow air to circulate behind them.
37
SECTION 1. WATER-MANAGED SITE AND FOUNDATION
1.7 Sump pump covers mechanically attached with full gasket seal or equivalent Critical Point: Sump pump covers are often loose and do not form a tight seal. This can lead to the introduction of additional moisture into the home. Summary: A mechanically attached sump pump cover reduces the possibility of moisture introduction from the sump pump.
38
Critical Point: Summary: Construction Phase: Inspection:
39
1.7 Sump pump covers mechanically attached with full gasket seal or equivalent A Critical Point: Moisture Flow — A mechanically fastened sump pump cover can reduce the amount of moisture introduced into the crawlspace or basement. Picture Description: BAD- There is no cover on the sump-pump this allows moisture to freely enter the crawlspace or basement. GOOD- A mechanically sealed sump pump cover helps keep moisture from the sump pump from entering the crawlspace or basement. Construction Phase: After the electric meter is set Inspection: Final Inspection The sump pump does not have a cover. The sump pump has a sealed cover that is mechanically attached.
40
1.7 Sump pump covers mechanically attached with full gasket seal or equivalent A Critical Point: Moisture Flow — A mechanically fastened sump pump cover can reduce the amount of moisture introduced into the crawlspace or basement. Picture Description: BAD- There is no cover on the sump-pump this allows moisture to freely enter the crawlspace or basement. GOOD- A mechanically sealed sump pump cover helps keep moisture from the sump pump from entering the crawlspace or basement. Construction Phase: After the electric meter is set Inspection: Final Inspection The sump pump does not have a cover. The sump pump has a sealed cover that is mechanically attached.
41
SECTION 1. WATER-MANAGED SITE AND FOUNDATION
1.8 Drain tile surrounded with clean gravel and fabric filter 7 Critical Point: Drain tile placed around the perimeter of the foundation should effectively drain water away from the foundation. The use of clean gravel and a fabric filter help prevent the drain tile from failing due to clogs. Summary: By properly removing bulk water, via drain tile, from the perimeter of the foundation it lessens the chances of moisture intrusion into the foundation.
42
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 7. Protected drain tile shall be installed at the footings of basement and crawlspace walls, level or sloped to discharge to outside grade (daylight) or to a sump pump. The top of each drain tile pipe shall always be below the bottom of the concrete slab or crawlspace floor. Each pipe shall be surrounded with at least 6 inches of ½ to ¾ inch washed or clean gravel. The gravel layer shall be fully wrapped with fabric cloth or drain tile pre-wrapped with a fabric filter to prevent clogging of the drain tile with sediment.
43
1.8 Drain tile surrounded with clean gravel and fabric filter 7 A
Critical Point: Moisture Flow — Clean gravel and a fabric filter minimize the chances that the drain tile with clog with debris Picture Description: BAD- The drain tile does not have a fabric filter to remove particulates from the water that enters the pipe. This increase the possibility that the drain tile will fail from clogging. GOOD- An appropriate fabric filter is installed to remove particulates before entering the pipe. Construction Phase: Foundation Inspection: Pre-Framing The drain tile is not wrapped in fabric and could become clogged with debris. The drain tile is wrapped in fabric which will prevent it clogging with debris.
44
1.8 Drain tile surrounded with clean gravel and fabric filter 7 B
Critical Point: Moisture Flow — The drain tile is terminated in a location that deposits the water away from the home Picture Description: BAD- GOOD- The drain tile is pitched appropriately to remove water from the base of the foundation and drain it to an area that will not negatively affect the building. Construction Phase: Foundation Inspection: Pre-Framing The drain tile is cut and now does not extend around the entire foundation footing. The drain tile is installed along the bottom of the entire foundation footing.
45
1.8 Drain tile surrounded with clean gravel and fabric filter 7 C
Critical Point: Moisture Flow — The drain tile should be located below the crawl space/basement floor to remove water before reaching the height of the floor of the crawlspace/basement. Picture Description: BAD- The drain tile should be located below the floor of the crawl space. By having the drain tile above the floor the water level must rise above the crawl space floor level to remove water. This can cause major bulk water issues in the crawl space. GOOD- The drain tile is placed below the floor of the crawl space and drains into the sump pump. This water removal system appropriately removes bulk water from the foundation. Construction Phase: Foundation Inspection: Pre-Framing The drain tile is not installed to terminate properly and will not transport water to the exterior. The drain tile connects to a sump pump which will pump water away from the foundation.
46
1.8 Drain tile surrounded with clean gravel and fabric filter 7 D
Critical Point: Moisture Flow — Clean gravel and a fabric filter minimize the chances that the drain tile with clog with debris Picture Description: BAD- The drain tile is not surrounded by clean gravel. This increases the chance that drain tile will fail and not appropriately remove water from the foundation. GOOD- Construction Phase: Foundation Inspection: Pre-Framing The gravel surrounding the drain tile is too large and will let too much debris through. GOOD PIC OF DRAIN TILE SURROUNDED WITH GRAVEL
47
SECTION 2. WATER-MANAGED WALL ASSEMBLY
2.1 Flashing at bottom of exterior walls with weep holes included for masonry veneer and weep screed for stucco cladding systems, or equivalent drainage system 2.2 Fully sealed continuous drainage plane behind exterior cladding that laps over flashing in Section 2.1. Additional bond-break drainage plane layer provided behind all stucco and non-structural masonry cladding wall assemblies Window and door openings fully flashed 9 Critical Point: The wall assembly should have a fully sealed drainage plane at its exterior. Summary: The wall assembly should have a drainage plane to prevent any water that gets past the initial cladding to not enter the wall system.
48
SECTION 2. WATER-MANAGED WALL ASSEMBLY
2.1 Flashing at bottom of exterior walls with weep holes included for masonry veneer and weep screed for stucco cladding systems, or equivalent drainage system Critical Point: Wall constructions must be fully flashed at the base of the wall. Summary: Flashing at the base of all walls to appropriately deal with water that has passed the initial cladding.
49
Critical Point: Summary: Construction Phase: Inspection:
50
2.1 Flashing at bottom of exterior walls with weep holes included for masonry veneer and weep screed for stucco cladding systems, or equivalent drainage system A Critical Point: Moisture Flow — Wall constructions must be fully flashed at the base of the wall. Picture Description: BAD- No flashing installed at base of the wall. GOOD- Flashing installed at the base of the wall to appropriately deal with water. Construction Phase: Siding Inspection: Framing Inspection There is no flashing installed at the bottom of the exterior walls to create a drainage system. There is flashing installed at the bottom of the wall to create a satisfactory drainage system.
51
2.1 Flashing at bottom of exterior walls with weep holes included for masonry veneer and weep screed for stucco cladding systems, or equivalent drainage system A Critical Point: Moisture Flow — Wall constructions must be fully flashed at the base of the wall. Picture Description: BAD- No flashing installed at base of the wall. GOOD- Construction Phase: Siding Inspection: Framing Inspection There is no flashing installed at the bottom of the exterior walls to create a drainage system. GOOD PIC OF FLASHING INSTALLED FINISHED
52
Critical Point: Summary: Construction Phase: Inspection:
53
2.1 Flashing at bottom of exterior walls with weep holes included for masonry veneer and weep screed for stucco cladding systems, or equivalent drainage system A Critical Point: Moisture Flow — Weep holes are included on all wall systems that utilize a masonry veneer as a rain screen. This is to allow moisture that passes through the rain screen a place to exit the wall system. Picture Description: BAD- There are no weep holes on the masonry veneer. Water that passes through the rain screen will have no where to exit and can cause moisture issues in the wall system. GOOD- Weep holes are installed in the masonry veneer to deal with water that has passed through the rain screen. Construction Phase: Exterior Cladding Inspection: Final Inspection The weep holes were not properly cleaned before the weeps were installed. The weep holes are properly cleaned out and the weeps properly installed.
54
2.1 Flashing at bottom of exterior walls with weep holes included for masonry veneer and weep screed for stucco cladding systems, or equivalent drainage system B Critical Point: Moisture Flow — Weep holes are included on all wall systems that utilize a masonry veneer as a rain screen. This is to allow moisture that passes through the rain screen a place to exit the wall system. Picture Description: BAD- There are no weep holes on the masonry veneer. Water that passes through the rain screen will have no where to exit and can cause moisture issues in the wall system. GOOD- Weep holes are installed in the masonry veneer to deal with water that has passed through the rain screen and drained down to the flashing. Construction Phase: Exterior Cladding Inspection: Final Inspection There are no weep holes installed at the bottom of the exterior wall. . There is both flashing and weep holes installed at the bottom of the exterior wall.
55
2.1 B The weep holes are spaced too far apart.
Flashing at bottom of exterior walls with weep holes included for masonry veneer and weep screed for stucco cladding systems, or equivalent drainage system B Critical Point: Moisture Flow — Weep holes are included on all wall systems that utilize a masonry veneer as a rain screen. This is to allow moisture that passes through the rain screen a place to exit the wall system. Picture Description: BAD- The weep holes are not spaced every 16”. Water that passes through the rain screen may not have enough weep holes to exit through and can cause moisture issues in the wall system. GOOD- Weep holes are installed in the masonry veneer every 16” to deal with water that has passed through the rain screen. Construction Phase: Exterior Cladding Inspection: Final Inspection The weep holes are spaced too far apart. The weep holes are spaced at the correct distance to provide a complete drainage system.
56
Critical Point: Summary: Construction Phase: Inspection:
57
2.1 Flashing at bottom of exterior walls with weep holes included for masonry veneer and weep screed for stucco cladding systems, or equivalent drainage system A Critical Point: Moisture Flow — A weep screed is installed to provide a path for water to exit the wall system that has passed through the stucco. Picture Description: BAD- No weep screed is installed to deal with water that passes through the stucco. This can cause the moisture issues at the bottom of the walls. GOOD- A weep screed is installed at the base of the exterior wall to provide a path for water to exit the wall system. Construction Phase: Exterior Cladding Inspection: The weep screed can be inspected when the stucco is being installed, probably at framing, or can be checked at final. There is not a weep screed installed at the bottom of the stucco wall. There is a weep screed installed at the bottom of the wall.
58
2.1 B BAD PIC OF FLASHING OVER WATER BARRIER
Flashing at bottom of exterior walls with weep holes included for masonry veneer and weep screed for stucco cladding systems, or equivalent drainage system B Critical Point: Moisture Flow — A weep screed is installed to provide a path for water to exit the wall system that has passed through the stucco. Picture Description: BAD- The weep screed is installed over the water-resistive barrier and can allow water to pass behind the weep screed. This can cause moisture issues in the wall system. GOOD- The water-resistive barrier is installed over the weep screed providing a proper drainage plane for the water. Construction Phase: Exterior Cladding Inspection: The weep screed can be inspected when the stucco is being installed, probably at framing or insulation. BAD PIC OF FLASHING OVER WATER BARRIER There is a water-resistant barrier installed underneath the stucco and lathe.
59
2.1 Flashing at bottom of exterior walls with weep holes included for masonry veneer and weep screed for stucco cladding systems, or equivalent drainage system C Critical Point: Moisture Flow — A weep screed is installed to provide a path for water to exit the wall system that has passed through the stucco. If the stucco or lathe is installed past the first bend in the weep screed the weep screed will not provide a proper path for water to exit the wall system. Picture Description: BAD- GOOD- The lathe and stucco is installed to the first bend of the weep screed providing a proper drainage plane for the water. Construction Phase: Exterior Cladding Inspection: The weep screed can be inspected when the stucco is being installed, probably at framing or insulation. The water-resistant barrier, weep screed, and stucco lathe are not properly layered. The water-resistant barrier, weep screed, and stucco lathe are properly layered and will create a complete drainage system.
60
SECTION 2. WATER-MANAGED WALL ASSEMBLY
2.2 Fully sealed continuous drainage plane behind exterior cladding that laps over flashing in Section 2.1. Additional bond-break drainage plane layer provided behind all stucco and non-structural masonry cladding wall assemblies 8 Critical Point: The wall assembly should have a fully sealed drainage plane at its exterior. Summary: The wall assembly should have a drainage plane to prevent any water that gets past the initial cladding to not enter the wall system.
61
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 8. Any of the following systems may be used: a monolithic weather-resistant barrier (i.e., house wrap) sealed or taped at all joints; weather resistant sheathings (e.g., faced rigid insulation) fully taped at all “butt” joints; lapped shingle-style building paper or felts; or other water-resistive barrier recognized by ICC-ES or other accredited agency.
62
2.2 Fully sealed continuous drainage plane behind exterior cladding that laps over flashing in Section 2.1. Additional bond-break drainage plane layer provided behind all stucco and non-structural masonry cladding wall assemblies 8 A Critical Point: Moisture Flow —The wall assembly should have a fully sealed drainage plane at its exterior. Picture Description: BAD- There is a gap in the weather-resistant barrier and thus it is possible for moisture to enter the wall system in this area. In addition, water can move behind the lower section of the barrier which renders it useless. GOOD- A fully sealed continuous drainage plane is installed with all the joints sealed/taped. Construction Phase: Framing Inspection: Framing Inspection The water-resistant barrier is not complete and the holes and gaps could cause moisture problems. The water-resistant barrier covers the entire house and the seams are taped to provide a complete drainage system.
63
2.2 Fully sealed continuous drainage plane behind exterior cladding that laps over flashing in Section 2.1. Additional bond-break drainage plane layer provided behind all stucco and non-structural masonry cladding wall assemblies 8 B Critical Point: Moisture Flow —The wall assembly should have a fully sealed drainage plane at its exterior. Picture Description: BAD- The seams on the weather resistant sheathing are not fully taped. This allows a point of entry for moisture into the wall system. GOOD- A fully sealed continuous drainage plane is installed using weather resistant sheathing. All joints are taped to ensure water does not enter the wall system. Construction Phase: Framing Inspection: Framing Inspection The rigid sheathing seams are not taped and the gaps could cause moisture problems. The rigid insulation covers all of the exterior walls and all of the seams are taped to provide a complete drainage system.
64
2.2 C The building felt is not installed on the entire house.
Fully sealed continuous drainage plane behind exterior cladding that laps over flashing in Section 2.1. Additional bond-break drainage plane layer provided behind all stucco and non-structural masonry cladding wall assemblies 8 C Critical Point: Moisture Flow —The wall assembly should have a fully sealed drainage plane at its exterior. Picture Description: BAD- GOOD- The felt paper is properly lapped according to manufacturers' specifications and provides a fully sealed continuous drainage plane at the exterior of the wall system. Construction Phase: Framing Inspection: Framing Inspection The building felt is not installed on the entire house. The building felt is installed on all exterior walls and provides a complete drainage system.
65
2.2 Fully sealed continuous drainage plane behind exterior cladding that laps over flashing in Section 2.1. Additional bond-break drainage plane layer provided behind all stucco and non-structural masonry cladding wall assemblies 8 D Critical Point: Moisture Flow —The wall assembly should have a fully sealed drainage plane at its exterior. Picture Description: BAD- There is no fully sealed continuous drainage plane behind the exterior cladding. This can potentially cause moisture issues in the wall system. GOOD- Construction Phase: Framing Inspection: Framing Inspection There is not a water-resistant barrier installed underneath the exterior finish of the walls. GOOD PIC OF A DIFFERENT TYPE OF WATER RESISTANT BARRIER
66
SECTION 2. WATER-MANAGED WALL ASSEMBLY
2.3 Window and door openings fully flashed 9 Critical Point: The wall assembly should have a fully sealed drainage plane at its exterior. Summary: The wall assembly should have a drainage plane to prevent any water that gets past the initial cladding to not enter the wall system.
67
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 9. Include pan flashing at sills, side flashing that extends over pan flashing, and top flashing that extends over side flashing.
68
2.3 Window and door openings fully flashed 9 A
Critical Point: Moisture Flow — The fully sealed drainage plane should not be compromised at windows. This can be accomplished through properly flashing windows and doors. Picture Description: BAD- Appropriate pan flashing is not installed on the window. This can potentially allow water to enter the wall system. GOOD- Pan flashing is installed at the sill to maintain the integrity of the fully sealed drainage plane. Construction Phase: Framing Inspection: Framing Inspection The corners are not properly flashed, leaving a vulnerable area in the drainage system. The flashing is properly installed to create a complete drainage system.
69
2.3 Window and door openings fully flashed 9 B
Critical Point: Moisture Flow — The fully sealed drainage plane should not be compromised at windows. This can be accomplished through properly flashing windows and doors. Picture Description: BAD- There is no pan flashing or side flashing on around the window. There is potential for moisture issues around the window. GOOD- The side flashing extends over the pan flashing, by doing this the water can not get behind the pan flashing. Construction Phase: Framing Inspection: Framing Inspection There is no flashing installed along the sides of the window. Side flashing extends over the pan flashing.
70
2.3 Window and door openings fully flashed 9 C
Critical Point: Moisture Flow — The fully sealed drainage plane should not be compromised at windows. This can be accomplished through properly flashing windows and doors. Picture Description: BAD- No proper flashing is installed on this window. It is likely that moisture will enter the wall system around this window. GOOD- The top flashing extends over the side flashing which maintains a properly lapped drainage plane around the window. The building wrap can also be placed over the top flashing if taped appropriately. Construction Phase: Framing Inspection: Framing Inspection There is no flashing installed at the top of the window. There is flashing installed along the top of the window and the water-resistant barrier is layered over to create a complete drainage system.
71
SECTION 3. WATER-MANAGED ROOF ASSEMBLY
3.1 Step and kick-out flashing at all roof-wall intersections, extending ≥ 4” on wall surface above roof deck and integrated with drainage plane above For homes that don’t have a slab-on-grade foundation and do have expansive or collapsible soils, gutters & downspouts provided that empty to lateral piping that deposits water on sloping final grade ≥ 5 ft. from foundation or to underground catchment system ≥ 10 ft. from foundation.11 Critical Point: The roof plane is sealed and flashed correctly to prevent leaks. The water collected by gutters is deposited in a place that will not cause moisture issues to the home. Summary: By properly flashing at wall intersections and using a membrane in the valleys and at penetrations the potential for leaks is minimized. Gutters appropriately deposit water away from the home as to not introduce water to the foundation/slab/wall system.
72
SECTION 3. WATER-MANAGED ROOF ASSEMBLY
3.3 Self-sealing bituminous membrane or equivalent at all valleys & roof deck penetrations In 2009 IECC Climate Zones 5 and higher, self-sealing bituminous membrane or equivalent over sheathing at eaves from the edge of the roof line to > 2 ft. up roof deck from the interior plane of the exterior wall.12 Critical Point: The roof plane is sealed and flashed correctly to prevent leaks. The water collected by gutters is deposited in a place that will not cause moisture issues to the home. Summary: By properly flashing at wall intersections and using a membrane in the valleys and at penetrations the potential for leaks is minimized. Gutters appropriately deposit water away from the home as to not introduce water to the foundation/slab/wall system.
73
SECTION 3. WATER-MANAGED ROOF ASSEMBLY
3.1 Step and kick-out flashing at all roof-wall intersections, extending ≥ 4” on wall surface above roof deck and integrated with drainage plane above 10 Critical Point: Moisture Flow- Intersections between roof and walls are flashed appropriately to prevent leaks in the roof. Summary: Wall to roof intersections must be integrated with the drainage plane to manage water and prevent leaks.
74
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 10. Intersecting wall siding shall terminate 1 in. above the roof or higher, per manufacturer’s recommendations. Continuous flashing shall be installed in place of step flashing for metal and rubber membrane roofs.
75
3.1 A BAD PIC OF ROOF FELT INSTALLATION
Step and kick-out flashing at all roof-wall intersections, extending ≥ 4” on wall surface above roof deck and integrated with drainage plane above 10 A Critical Point: Moisture Flow- Intersections between roof and walls are flashed appropriately to prevent leaks in the roof. Picture Description: BAD- Step flashing is not present (one solid piece L-flashing) and there is no kick-out flashing. This way of flashing allows water to go under the edge of shingles and can potentially lead to moisture entering the wall system. GOOD- Construction Phase: Roofing Inspection: Final Inspection BAD PIC OF ROOF FELT INSTALLATION GOOD PIC OF PROPERLY LAYERED ROOFING
76
3.1 Step and kick-out flashing at all roof-wall intersections, extending ≥ 4” on wall surface above roof deck and integrated with drainage plane above 10 B Critical Point: Moisture Flow- Intersections between roof and walls are flashed appropriately to prevent leaks in the roof. By installing the building wrap and the shingles over the flashing the chance of water getting behind the flashing is minimized. Picture Description: BAD- The flashing is not properly integrated with the drainage plane. Water running down the building wrap can go behind the step flashing and water can enter the wall system. GOOD- Step flashing is correctly installed under the roofing material and the house wrap. Construction Phase: Roofing Inspection: Final Inspection The step flashing is not the required height above the roof deck. The step flashing is the correct height above the roof deck.
77
3.1 Step and kick-out flashing at all roof-wall intersections, extending ≥ 4” on wall surface above roof deck and integrated with drainage plane above 10 C Critical Point: Moisture Flow- Intersections between roof and walls are flashed appropriately to prevent leaks in the roof. Picture Description: BAD- There is no kick-out flashing installed and thus water drains against the wall system. This can cause potentially allow water to enter the wall system. GOOD- Step flashing is correctly installed and extends at least 4” above the roof deck along the wall. Construction Phase: Roofing Inspection: Final Inspection The water-resistant barrier is layered underneath the step flashing and could create a water damage. The water-resistant barrier is layered over the step flashing to provide a complete drainage system.
78
SECTION 3. WATER-MANAGED ROOF ASSEMBLY
3.2 For homes that don’t have a slab-on-grade foundation and do have expansive or collapsible soils, gutters & downspouts provided that empty to lateral piping that deposits water on sloping final grade ≥ 5 ft. from foundation or to underground catchment system > 10 ft. from foundation.11 Critical Point: Water collected by gutters is deposited away from the home. Summary: Water is deposited away from the home to minimize the chance that there will be a bulk water issue caused by the gutters/downspouts.
79
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 11. The assessment of whether the soil is expansive or collapsible shall be completed by a certified hydrologist, soil scientist, or engineer. Gutters shall be not required in dry climates as shown in 2009 IECC Figure and Table A roof design without gutters is also acceptable if it deposits rainwater to a grade-level rock bed with a waterproof liner and a drain pipe that deposits water on a sloping finish grade ≥ 5 ft. from foundation. Rainwater harvesting systems may also be used to meet this requirement when designed to properly drain overflow, meeting the discharge-distance requirements above.
80
3.2 For homes that don’t have a slab-on-grade foundation and do have expansive or collapsible soils, gutters & downspouts provided that empty to lateral piping that deposits water on sloping final grade ≥ 5 ft. from foundation or to underground catchment system ≥ 10 ft. from foundation.11 A Critical Point: Moisture Flow — Water collected by gutters is deposited at least 5 ft. away from the home. Picture Description: BAD- Downspout terminates under front porch right next to foundation. This increases the potential that there will be moisture entering the crawlspace/basement. GOOD- Downspout terminates at least 5’ from the foundation. Construction Phase: Inspection: Final Inspection The downspout terminates too close to the foundation of the house. The downspout pipes far enough away from the foundation to prevent moisture problems.
81
3.2 For homes that don’t have a slab-on-grade foundation and do have expansive or collapsible soils, gutters & downspouts provided that empty to lateral piping that deposits water on sloping final grade ≥ 5 ft. from foundation or to underground catchment system ≥ 10 ft. from foundation.11 B Critical Point: Moisture Flow — Water collected by gutters is deposited at least 5 ft. away from the home. Picture Description: BAD- Downspout terminates next to foundation (<5’ from foundation). This increases the potential that there will be moisture entering the crawlspace/basement. GOOD- Downspout terminates into underground catchment system that is at least 10’ from the foundation. Construction Phase: Inspection: Final Inspection The downspout terminates too close to the foundation of the house. The downspout terminates into a catchment system that moves water away from the foundation of the house.
82
3.2 For homes that don’t have a slab-on-grade foundation and do have expansive or collapsible soils, gutters & downspouts provided that empty to lateral piping that deposits water on sloping final grade ≥ 5 ft. from foundation or to underground catchment system ≥ 10 ft. from foundation.11 C Critical Point: Moisture Flow — When no gutters are present, bulk water from the roof is taken away from the foundation by means of a grade-level rock bed with a waterproof liner and a drain pipe. Picture Description: BAD- No gutters are present and there is no means of taking the bulk water from the roof away from the foundation. GOOD- No gutters are present. However, there is a grade-level rock bed with a waterproof liner and a drain pipe which carries water away from the foundation and deposits it on a sloping grade at least 5’ from the foundation. Construction Phase: Inspection: Final Inspection There are no gutters installed and there is not a proper gravel bed located at the foundation. House without gutters has waterproof liner, drain tile and gravel bed extending more than 5 feet from foundation.
83
3.2 For homes that don’t have a slab-on-grade foundation and do have expansive or collapsible soils, gutters & downspouts provided that empty to lateral piping that deposits water on sloping final grade ≥ 5 ft. from foundation or to underground catchment system ≥ 10 ft. from foundation.11 D Critical Point: Moisture Flow — Water collected by gutters is deposited at least 5 ft. away from the home. Picture Description: BAD- The rain barrel does not have an overflow drain to take care of the excess water if the barrel is full. This can cause water to be discharged next to the foundation. GOOD- Construction Phase: Inspection: Final Inspection Rain barrel installed without an overflow spout that terminates away from foundation. Rain barrel installed with an overflow spout terminating at least 5 feet from foundation.
84
SECTION 3. WATER-MANAGED ROOF ASSEMBLY
3.3 Self-sealing bituminous membrane or equivalent at all valleys & roof deck penetrations 12 Critical Point: All valleys and roof penetrations must have a self-sealing bituminous membrane to prevent leaks. Summary: Roof valleys and roof penetrations are areas that often have shingle failure and are more prone to having water pool. By using a self-sealing bituminous membrane the probability for leaks is lessened.
85
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 12. Not required in dry climates as shown in 2009 IECC Figure and Table
86
3.3 Self-sealing bituminous membrane or equivalent at all valleys & roof deck penetrations 12 A Critical Point: Moisture Flow — All valleys must have a self-sealing bituminous membrane to prevent leaks. Picture Description: BAD- There is no self-sealing membrane installed in the valley. Water has frozen in the valley and can potentially cause leaking without a self-sealing membrane. (As water freezes it can work its way under the shingles) GOOD- A self-sealing membrane is being installed in a roof valley. Construction Phase: Roofing Inspection: Framing There is not a self-sealing bituminous membrane installed at the valley of the roof. There is a self-sealing bituminous membrane installed at the valley of the roof prior to the roof felt.
87
3.3 Self-sealing bituminous membrane or equivalent at all valleys & roof deck penetrations 12 A Critical Point: Moisture Flow — All roof penetrations must have a self-sealing bituminous membrane to prevent leaks. Picture Description: BAD- GOOD- Construction Phase: Roofing Inspection: Framing Inspection BAD PIC OF ROOF WITHOUT MEMBRANE INSTALLED There is a properly installed and layered self-sealing bituminous membrane installed at the roof penetration.
88
SECTION 3. WATER-MANAGED ROOF ASSEMBLY
3.4 In 2009 IECC Climate Zones 5 and higher, self-sealing bituminous membrane or equivalent over sheathing at eaves from the edge of the roof line to > 2 ft. up roof deck from the interior plane of the exterior wall.12 Critical Point: In cold climates, self-sealing bituminous membrane must be installed at the eaves. This membrane must extend at least 2’ up the roof deck from the wall plane. Summary: In cold climates, there is a potential for ice dams that can cause water to pool at the eaves. If a self-sealing bituminous membrane is not installed at the eaves it is very probable that there will be leaks.
89
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 12. Not required in dry climates as shown in 2009 IECC Figure and Table
90
3.4 A BAD PIC OF NO MEMBRANE AT EAVES
In 2009 IECC Climate Zones 5 and higher, self-sealing bituminous membrane or equivalent over sheathing at eaves from the edge of the roof line to > 2 ft. up roof deck from the interior plane of the exterior wall.12 A Critical Point: Moisture Flow — A self-sealing bituminous membrane must be installed at eaves to prevent leaks. Picture Description: Construction Phase: Roofing Inspection: Framing Inspection BAD PIC OF NO MEMBRANE AT EAVES GOOD PIC OF PROPERLY INSTALLED MEMBRANE AT EAVES
91
3.4 A BAD PIC OF NO MEMBRANE AT EAVES
In 2009 IECC Climate Zones 5 and higher, self-sealing bituminous membrane or equivalent over sheathing at eaves from the edge of the roof line to > 2 ft. up roof deck from the interior plane of the exterior wall.12 A Critical Point: Moisture Flow — A self-sealing bituminous membrane must be installed at eaves to prevent leaks. Picture Description: Construction Phase: Roofing Inspection: Framing Inspection BAD PIC OF NO MEMBRANE AT EAVES GOOD PIC OF PROPERLY INSTALLED MEMBRANE AT EAVES
92
SECTION 4. WATER-MANAGED BUILDING MATERIALS
4.1 Wall-to-wall carpet not installed within 2.5 feet of toilets, tubs, and showers 4.2 Cement board or equivalent moisture-resistant backing material installed on all walls behind tub and shower enclosures composed of tile or panel assemblies with caulked joints. Paper-faced backerboard shall not be used 13 Critical Point: Materials that are installed do not have high moisture content and will not cause moisture issues during the life of the home. Summary: Moisture issues can cause durability issues and indoor air quality issues.
93
SECTION 4. WATER-MANAGED BUILDING MATERIALS
4.3 In Warm-Humid climates, Class 1 vapor retarders not installed on the interior side of air permeable insulation in above-grade walls, except at shower and tub walls Building materials with visible signs of water damage or mold not installed Interior walls not enclosed (e.g., with drywall) if either the framing members or insulation products have high moisture content 15 Critical Point: Materials that are installed do not have high moisture content and will not cause moisture issues during the life of the home. Summary: Moisture issues can cause durability issues and indoor air quality issues.
94
SECTION 4. WATER-MANAGED BUILDING MATERIALS
4.1 Wall-to-wall carpet not installed within 2.5 feet of toilets, tubs, and showers Critical Point: No carpet should be installed within 2.5’ of toilets, tubs, and showers. A flooring material that does not hold water should be used here. Summary: Around toilets, tubs and showers there is a high potential for water to contact the flooring material. Carpet can hold moisture and cause indoor air quality issues.
95
Critical Point: Summary: Construction Phase: Inspection:
96
4.1 Wall-to-wall carpet not installed within 2.5 feet of toilets, tubs, and showers A Critical Point: Moisture Flow — No carpet should be installed within 2.5’ of toilets, tubs, and showers. A flooring material that does not hold water should be used here. Picture Description: BAD- Carpet is installed next to the bath tub. GOOD- There is no carpet within 2.5’ of the tub or the toilet. Construction Phase: Flooring- Towards the end of construction. Inspection: Final inspection There is carpet installed too close to the plumbing fixtures in the bathroom. There is no carpet installed in the bathroom.
97
4.1 Wall-to-wall carpet not installed within 2.5 feet of toilets, tubs, and showers A Critical Point: Moisture Flow — No carpet should be installed within 2.5’ of toilets, tubs, and showers. A flooring material that does not hold water should be used here. Picture Description: BAD- Carpet is installed next to the bath tub. GOOD- There is no carpet within 2.5’ of the tub or the toilet. Construction Phase: Flooring- Towards the end of construction. Inspection: Final inspection There is carpet installed too close to the plumbing fixtures in the bathroom. There is no carpet installed in the bathroom.
98
SECTION 4. WATER-MANAGED BUILDING MATERIALS
4.2 Cement board or equivalent moisture-resistant backing material installed on all walls behind tub and shower enclosures composed of tile or panel assemblies with caulked joints. Paper-faced backerboard shall not be used 13 Critical Point: A moisture-resistant backing material is installed on walls behind tubs and shower enclosures that have the potential for failure and moisture to pass behind the shower or tub. Summary: Tile and panel tub surrounds and showers have joints that can fail and allow water to pass behind the tub or shower. This moisture can cause durability issues and/or indoor air qualities.
99
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 13. Monolithic tub and shower enclosures (e.g., fiberglass with no seams) are exempt from this backing material requirement unless required by the manufacturer. Paper-faced backerboard may only be used behind monolithic enclosures and only if it meets ASTM mold-resistant standards ASTM D3273 or ASTM D6329.
100
4.2 A No backing installed behind shower enclosure.
Cement board or equivalent moisture-resistant backing material installed on all walls behind tub and shower enclosures composed of tile or panel assemblies with caulked joints. Paper-faced backerboard shall not be used 13 A Critical Point: Moisture Flow — A moisture-resistant backing material is installed on walls behind tubs and shower enclosures that have the potential for failure and moisture to pass behind the shower or tub. Picture Description: BAD- GOOD- Construction Phase: Rough-in plumbing Inspection: Framing Inspection No backing installed behind shower enclosure. Foam board taped at seams installed behind shower enclosure.
101
4.2 B BAD PIC OF NON MOISTURE RESISTANT MATERIAL BEHIND TUB/SHOWER
Cement board or equivalent moisture-resistant backing material installed on all walls behind tub and shower enclosures composed of tile or panel assemblies with caulked joints. Paper-faced backerboard shall not be used 13 B Critical Point: Moisture Flow — A mold-resistant backerboard is used behind monolithic tub/shower enclosures to prevent mold growth. Picture Description: BAD- There is no mold-resistant backerboard installed behind the shower. GOOD- There is a mold-resistant backerboard installed behind the shower. Construction Phase: Rough-in plumbing Inspection: Framing Inspection BAD PIC OF NON MOISTURE RESISTANT MATERIAL BEHIND TUB/SHOWER Moisture resistant backing material has been used above the tub enclosure.
102
SECTION 4. WATER-MANAGED BUILDING MATERIALS
4.3 In Warm-Humid climates, Class 1 vapor retarders not installed on the interior side of air permeable insulation in above-grade walls, except at shower and tub walls 6 Critical Point: All materials used on the interior side of exterior walls has a permeability rating of 0.1 or more. This allows moistures to pass through the wall systems freely. Summary: In warm-humid climates moisture flows both directions through the wall depending on the season. Moisture flows from hot to cold and wet to dry. By having a high perm rating the moisture is not trapped in the wall.
103
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 6. The 2009 IRC defines Class I vapor retarders as a material or assembly with a rating of ≤ 0.1 perm, as defined using the desiccant method with Procedure A of ASTM E 96. The following materials are typically rated at ≤ 0.1 perm and therefore shall not be used on the interior side of air permeable insulation in above-grade exterior walls in warm-humid climates or below-grade exterior walls in any climate: rubber membranes, polyethylene film, glass, aluminum foil, sheet metal, foil-faced insulating sheathings, and foil-faced non-insulating sheathings. These materials can be used on the interior side of walls if air permeable insulation is not present (e.g., foil-faced extruded polystyrene rigid insulation board adjacent to a below-grade concrete foundation wall is permitted). Note that this list is not comprehensive and other materials with a perm rating ≤ 0.1 also shall not be used. Also, if manufacturer specifications for a specific product indicate a perm rating above 0.1, then the material may be used, even if it is in this list. Also note that open-cell and closed-cell foam generally have perm ratings above this limit and may be used unless manufacturer specifications indicate a perm rating ≤ 0.1. Several exemptions to these requirements apply: a. Class I vapor retarders, such as ceramic tile, may be used at shower and tub walls; b. Class I vapor retarders, such as mirrors, may be used if they are mounted with clips or other spacers that allow air to circulate behind them.
104
SECTION 4. WATER-MANAGED BUILDING MATERIALS
4.4 Building materials with visible signs of water damage or mold not installed Interior walls not enclosed (e.g., with drywall) if either the framing members or insulation products have high moisture content 15 Critical Point: Water damage and mold is not present on any material that is installed on the home. Summary: By not installing any water damaged/moldy materials in the home the potential for mold and durability issues in minimized.
105
Critical Point: Summary: Construction Phase: Inspection: Footnotes: 14. If mold is present, effort should be made to remove all visible signs of mold using detergent or other method. If removal methods are not effective, then the material shall be replaced. 15. For wet-applied insulation products, follow manufacturer’s drying recommendations. As guidance, EPA recommends that lumber not exceed 18% moisture content.
106
4.4-5 Building materials with visible signs of water damage or mold not installed 14 A Critical Point: Moisture Flow — Storing building materials in a dry location minimizes the potential for mold and water damage to the building materials. Picture Description: BAD- Materials are stored in a location that has lots of moisture present. GOOD- Materials kept on pallets despite the ground being very wet they are wrapped and dry still. Construction Phase: Pre-Construction & During Construction Inspection: Throughout Construction Building materials are being stored outdoors with no protection from weather. Shingles kept wrapped and on pallets to prevent from getting wet.
107
4.4-5 Building materials with visible signs of water damage or mold not installed 14 B Critical Point: Moisture Flow — Materials installed do not have any mold or water damage present. Picture Description: BAD- Materials installed have mold present. GOOD- Materials installed are free of water damage and mold. Construction Phase: Pre-Construction & During Construction Inspection: Throughout Construction Building materials with visible signs of mold have been used. Building materials were kept dry and free of mold.
108
4.4-5 Interior walls not enclosed (e.g., with drywall) if either the framing members or insulation products have high moisture content 15 C Critical Point: Moisture Flow — No high moisture content materials are enclosed in the wall system Picture Description: BAD- Materials that have high moisture content have been installed ***NOT A WALL SYSTEM, JOIST HANGER PRESENT*** GOOD- Moisture meter shows that the wood has a moisture content below 18%. Therefore it is acceptable to enclose this material. Construction Phase: Drywall Inspection: Insulation Inspection Building materials have signs of water damage and high moisture content. A moisture meter verifies that the moisture content of the framing is below the recommended 18%.
109
4.4-5 Interior walls not enclosed (e.g., with drywall) if either the framing members or insulation products have high moisture content 15 D Critical Point: Moisture Flow — No high moisture content insulations are enclosed in the wall system Picture Description: BAD- GOOD- Construction Phase: Drywall Inspection: Insulation Inspection BAD PIC OF WET BLOWN INSULATION PRODUCT GOOD PIC OF WET BLOWN INSULATION PRODUCT
110
EPA Disclaimer Any mention of trade names, commercial products and organizations in this document does not imply endorsement by the U.S. Environmental Protection Agency ("EPA") or the U.S. Government. The EPA and its collaborators make no warranties, whether expressed or implied, nor assume any legal liability or responsibility for the accuracy, completeness or usefulness of the contents of this publication, or any portion thereof, nor represent that its use would not infringe privately owned rights. Further, the EPA cannot be held liable for construction defects or deficiencies resulting from the proper or improper application of the content of this guidebook. Critical Point: To prevent water on the slab from draining toward the home and causing potential moisture issues. Summary:
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.