1 GAUSS Work plan Software Week 6 March 2002 F.Ranjard / CERN

2 Contents Work plan set in October 2001 Gauss today Planning
5 December 2018 GAUSS Work plan

3 Work plan as set in October 2001
GAUSS should be able to read HepMC files is done A task for GAUDI GAUSS should be able to write an output at various levels of the processing and to restart the processing from where it was stopped is done A task for GAUDI (writing) and GAUSS (reprocessing) GAUSS should be able to simulate various setups selected with job options. A task for GAUDI (condition data base) and GAUSS not yet done (see Sebastien’s talk on Friday) These tasks do not need all detectors in , they could be achieved by June Will be achieved before June 2002 5 December 2018 GAUSS Work plan

4 Gauss today The following packages have been installed yesterday on Lxplus. Gen/GeneratorModules/v1r0 ATLAS origin Gen/GeneratorObjects/v1r0 Gen/GeneratorUtils/v1r0 Gen/Pythia_i/v1r0 Gen/PYTIA/v61r52 interface package Sim/HepMC/v1r2 ATLAS package Sim/GiGaCnv/v4r0 Sim/Gauss/v1r0 application package 5 December 2018 GAUSS Work plan

5 Update of the work plan 5 December 2018 GAUSS Work plan

6 Planning We still expect to have a framework with full functionality by June 2002. That would allow to add detectors when they are ready to come in. 5 December 2018 GAUSS Work plan