UPGRADE MOORING FACILITIES JETTY NUSTAR TERMINAL GRAYS (LONDON) DESIGN, TENDER AND RISK MEETING DD 25 JANUARY 2017
2
aGENDA Actual design and scope
Presentation Works Methods and equipment Schedule RISKS (and Opportunities) Offer date: mid February Contract format (technical, legal, financial conditions) Local and Nustar regulations (safety)
3
SCOPE Dredging appr. 6000 m3 including land disposal (DEC)
8 pc. Breasting Dolphins with fender panels 8 pc. Mooring Dolphins 12 pc. Quick Release Hooks 2 pc Landing Stages for ship gangways Removal of old fender structures Interconnecting bridges to breasting dolphins New pipe bridges/walkway from shore to jetty 1 (partly) Lifting activities for Marine Loading Arms (MLA’s) New foundation on jetty platform for MLA’s Installation task lights and navigational lighting
4
Actual design
5
Actual design
6
Actual design
7
Actual design (jetty 1)
8
Dredging area
9
Dredging area (extended – Client’s/plA’s decision)
10
MIDDLE MOORING DOLPHIN CONFIGURATION (PLA’s wishes)
11
MIDDLE MOORING DOLPHIN CONFIGURATION
12
breasting dolphins
13
Mooring dolphins
14
Marine loading arms
15
Walk way / pipe bridge
16
Methods / equipment
17
Methods / equipment
18
Methods / equipment
19
Methods / equipment
20
Methods / equipment
21
Methods / equipment
22
Methods / equipment
23
Methods / equipment
24
Risks
25
Contract format and conditions
FIDIC yellow with conditions Client’s responsibilities: Permits and licenses and applications Functional requirements (BOD) UXO’s/ obstacles in underground (ship wrecks, unknown construction) Jetty’s free in time and undisturbed execution not stopped or hindered by Nustar activities Correctness of documents made available by client Correctness of soil data made available by client (not the interpretation) Piping and E & I works Delivery of MLA’s Safety coordination on site Basic survey of existing construction
26
Contract format and conditions
FIDIC yellow with conditions Contractors responsibilities: Technical requirements (BOD) General and detail design Execution within schedule (excl. influence of extreme weather) Quality control according to Eurocode RC2/CC2 Steelworks performed according tot NEN 1090 (CC2) Safety management of works within DEME scope according to Nustar regulations Execution according to (known) requirements coming from Port (PLA) and permit requirements (noise measurement, slow start, starting time for piling)