1 Recognising and managing the key challenges in water service delivery
Analysis of a sample of WSAs Kevin Jacoby 14 June 2013

2 Overview of presentation
The sample! Standard of water service provision Financial cost estimation Potential consequence of sub-standard water service delivery Conclusions

3 Sampled municipalities
No. Name of Municipality Category Province 1 Nelson Mandela Bay Metropolitan Municipality (NMBM) A Eastern Cape 2 Ekurhuleni Metropolitan Municipality Gauteng 3 eThekwini Metropolitan Municipality Kwa-Zulu Natal 4 Cape Town Metropolitan Municipality Western Cape 5 Buffalo City Metropolitan Municipality 6 George Municipality B 7 uMhlathuze (Richards Bay) Municipality 8 Steve Tshwete (Middleburg) Municipality Mpumalanga 9 Kouga Municipality 10 Sol Plaatjie (Kimberley) Municipality Northern Cape 11 Polokwane Municipality 12 Stellenbosch Municipality 13 Overstrand Municipality 14 Midvaal Municipality 15 Amathole District Municipality C

4 Standard of water service provision
Backlog of water service infrastructure maint. and rehab. For 10 sample municipalities: Water = R million (decrease from previous year) R 91k/capita Sanitation = R million (increase from previous year) R 400k/capita Ekurhuleni sanitation requires a R 1 545k/capita investment Capital cost of addressing the service coverage backlog Water = R million (same as previous year) R 503k/capita Sanitation = R million (increase from previous year) R 607k/capita Polokwane water requires a R 3 042k/capita investment and sanitation a R 1 306k/capita investment.

5 Standard of water service provision (cont.)
Potable water service interruptions in 2009/10 – recorded in Cape Town Days failed sanitation services 24 days in 2009/10 – 15 of these in Ekurhuleni DWA blue drop quality 9 out of 15 DWA green drop quality 5 out of 15 Prioritisation of water services by municipalities 10/13 incl. water service operational readiness as a risk 3/10 classify this as a high risk

6 Standard of water service provision (cont.)
Monitoring effort by municipalities Average years since last meter audit for 13/15 is 4 years Polokwane last meter audit 15yrs prior Metros average years for meter audits is 2 years Skills adequacy 31% of water service posts are vacant Skilled staff service members of the population Engineers service members of the population Technologists service members of the population Technicians service members of the population

7 Standard of water service provision (cont.)
Planning effort 14/15 had water service development plans 12/15 had water service master plans Management of capex Sources of funding Internal sources 17% Grants 45% Developers contributions 1% External loans 34% Other 4% Note – most external loan funding used by metros Overall capex budget allocated to water services =15%

8 Standard of water service provision (cont.)
Per capita investment in water services R220 Allocation of water service capex budget Rehabilitation of water service infrastructure 32.27% New infrastructure assets - networks 26.21% New capital - sanitation facilities 15.04% New capital - bulk water and sanitation/sewage 25.95% Capital budget spent = 84%

9 Standard of water service provision (cont.)
Management of opex Budgeted result R 786million Actual result R 267 million ? : Variable costs and costs of transfer exceeded the budget External support options Water service consultants (project design) – 14/14 PPPs /14 Water Boards /14 District Municipalities /14

10 Financial cost estimation
Ring-fencing 2/15 provide for ring-fenced water service (Metros) 11/15 find the cost estimation of the water service easy Internal costing methodology Percentage of total cost of support services – 6/11 ABC costing /11 Mixture of the above /11 Source and pricing of bulk water provision 49% of water self supplied (R0,0385 to R3,02/kl) 23% of water from DWA (R0,4301 to R1,892/kl) 29% of water from water boards (R3,25 to R4,64/kl)

11 Financial cost estimation
Fixed and variable cost analysis 51% fixed costs 49% variable costs Varies significantly from authority to authority NMBM 30% fixed Ekurhuleni 90% fixed Asset valuation methods and asset registers 10/15 – Replacement value 8/15 - Historical value 3/15 – Use both methods Most asset registers are detailed and include extent, age, value and state (condition) of an asset

12 Financial cost estimation
Adequacy of depreciation A variance of R90m between estimated and actual depreciation for potable water service in 2009/10 DRC R8,204 billion CRC R9,015 billion DRC/CRC is 75% : is this cash backed? Impact on accumulated surplus/deficit? Scarcity cost consciousness Few!– strategies vary from demand management to additional supply Environmental cost of waste water management not considered

13 Potential consequences
The municipal capital budget in 2006 equalled 75% of the value of buildings completed This percentage was 49% in 2009/10

14 Conclusions Per capita cost to address sanitation backlog infrastructure maintenance and rehab. was increasing Metros focused more on reducing water coverage backlog rather than the sanitation coverage backlog Potable water service interruptions must be recorded Days of failed sanitation are not being recorded, an indicator of munic. not monitoring sanitation services No negative correlation between quality certificates and backlogs in maintenance and rehabilitation A correlation rather exists with skills and quality of service

15 Conclusions Operational readiness of the water service a risk but not the highest risk for municipalities Long period between the audit of water meters Municipalities are involved in water service planning. Are these plans being implemented? Various funding sources are available for capital programmes-high levels of external borrowing 15% of total capital budget to water services Municipalities (small) spending more capital on new infrastructures as opposed to maintenance and rehabilitation

16 Conclusions Municipalities underspend on capital budgets (conditional grants risk?) Budget comparisons reveal the cost of service is recovered by tariffs. Material variations exist if compared with the actual result. Impact on tariff calculations is significant Municipalities make limited use of external support The principle of ring-fencing is not implemented by most Municipalities know little about consumption trends and the nature of demand by users

17 Conclusions Municipalities use various costing methodologies
The bulk water supply varies Inconsistent approach applied to the categorisation of costs between fixed and variable Asset registers complete Depreciation not being recovered by tariffs and not being used to manage the replacement of assets Next water supply is material and not provided for Exogenous environmental costs not considered Capital expenditure/value of building plans decreased

18 The End Thank you Comments/questions?