Problem 4.3 (a) The network of the Deluxe model

Similar presentations


Presentation on theme: "Problem 4.3 (a) The network of the Deluxe model"— Presentation transcript:

1

2 Problem 4.3 (a) The network of the Deluxe model
45 6 18 Punch (base) Form (base) S_assemble (base) 10 12 36 Start Separate Assemble Inspect 30 12 Punch (roof) Form (roof) TFT_Deluxe_Path1 = = 127

3 Problem 4.3(b) TFT for 25% Deluxe and 75% standard 33.75 6 14.25 Punch (base) Form (base) S_assemble (base) 10 10.5 36 Start Separate Assemble Inspect 24 12 Punch (roof) Form (roof) TFT_Deluxe_Path1 = = 110.5 The flow time efficiency is 110.5/4800 = 2.3%

4 Problem 4.3 (alternative way for part b using the network of the Standard model)
The network of the Standard model is as follows 30 6 13 Punch (base) Form (base) S_assemble (base) 10 10 36 Start Separate Assemble Inspect 22 12 Punch (roof) Form (roof) TFT_Standard_path1 = = 105 TFT_Deluxe = 127 0.75× ×127 = 110.5


Download ppt "Problem 4.3 (a) The network of the Deluxe model"