29th July, 2017 Dealing with Construction Permits
Municipal Corporations of Delhi 29th July, 2017
2
Parameter wise Reforms
Procedures Reduced: From 29 to 8 Time Total time of all approvals during construction cycle reduced from 213 days to less than 60 days. Quality of Regulation enhanced: - Latent defect liability and decennial defect liability insurance included. - Professionals qualifications defined . - Risk based classification of all buildings enabling fast pacing in plinth level inspection and OCC incorporated. Cost Cost associated with Construction Permit reduced from 13.6 lacs to INR 1.91 lacs 2
3
Online - Common Application Form
Online Common Application Form (CAF) for Building permit, includes the information required by external NOC agencies Online checklist available in the Public Domain for user to validate on requirement of applicable NOCs through GSDL superimposed CCZM Single Interface for Applicants for Construction Permit under SWCS Online registration of Architects/ Structural Engineers No physical Interface of the applicant with external NOC agencies Online provision to track Application Status. Online Issuance of digitally signed sanction letter and approved plan / Plinth Level Certificate / Occupancy –cum- Completion certificate SMS/ mail to the applicant / architect at all stages of application
4
Integration of Departments
Departments integrated Last Year Departments integrated This Year Departments NOC Dispensed with Forest DFS DISCOMS(3) DUAC DPCC DJB** DMRC DJB* AAI HCC NMA * Integrated for OCC ** NOC dispensed with from sanction plan CIF
5
Process Simplification
The Digital Signatures have been incorporated so there is no interaction between the applicant and the department All the requisite information regarding Building Bye-Laws, Master Plan of Delhi, Office Orders, Circulars, List of Building Plans, DMC Act etc. are available on the MCD website Check List : The ‘Check List’ and FAQ are available in public domain The affidavits (16 Nos) have been converted into e-undertaking from architect and an undertaking from applicant Online Single payment option is available through Net banking / RTGS / NEFT/ Debit-Credit Card. Online Calculator to determine the Building Plan fee is available on the website. For awareness of General Public, Facebook page (MCD Ease of Doing Business) has been launched on which all circulars / office order / information are shared regularly. For day to day grievances / technical issues WhatsApp group is functional on which the replies are given on daily basis.
6
HCC NMA CIF AAI DMRC Forest DUAC DFS DPCC
Saturday, November 17, 2018 HCC NMA CIF AAI DMRC Forest DUAC DFS DPCC Case scrutinized by the AE(B)and processed Single Window System After receiving the requisite NOCs (Deemed NOC on 16th Day), cases are Processed for approval After approval of EE(B) / SE(B) and payment of requisite fee , construction permits released online Corporation Office In case of no response from Deptt., Deemed sanction on 31st Day
7
Process Flow for Issue of Construction Permit
Saturday, November 17, 2018 Process Flow for Issue of Construction Permit Check Guidelines for NOC Requirement Fill Common Application Form Upload the Drawing Filling of NOC forms Submit the Request Pay Processing Fee AE to Validate the Request NOC request is automatically Forward to respective external Agencies External Agencies to Approve/Reject Return Status to MCD Plan Sanction / Rejected by MCD Pay Sanction Charges & External Agencies Charges (Single fee) Plan Released with Digitally signed sanction letter In case of no response Deemed Sanction on 31st Day 0.5 Day 28 Days 0.5 day
8
Process Flow for Plinth Inspection Certificate
Saturday, November 17, 2018 Process Flow for Plinth Inspection Certificate 7 Days Fill Requisite details in CAF (Plinth Inspection) Upload the Drawing and Documents along with online fee of INR 500/- In case of Low and very low risk, C-2 is issued by Architect / Engineer In case of Moderate & High Risk, C-2 application reaches to Department Inspection by Department within 7 days Issue C-2 Certificate within 7 days or deemed issued by system
9
Process Flow for Completion Certificate
Fill Requisite details in Common Completion Request Form Upload the Drawing and Documents along with online fee Forward to applicable NOC Department automatically (to be returned within 15 days else deemed) In case of Low and very low risk, Inspection by Architect / Engineer In case of Moderate & High Inspection by Department within 7 days Intimate the charges to the applicant Release digitally signed Completion-cum-Occupancy Certificate Issue Completion-cum- Occupancy Certificate on 23rd days or deemed issued by system 7 Days 15 Day 0.5 Day
10
Procedures, Time and Cost comparison between DBR- 2017 and Current scenario (1/5)
S. No Process, Time & Cost As Per DBR- 2017 Process, Time, Cost & Legal Basis After Reform Implementation 1 Obtain a certified copy of the property record 17 days INR 2,000 Procedures Eliminated (Time : 0, Cost : 0) Not required now goo.gl/z6lQ5e 2 Request and obtain consent to establish from Delhi Pollution Control Committee 30 days INR 1,000 goo.gl/YX0Wen 3 Obtain no objection certificate regarding land use per the zoning plan INR 25,000 4 Request and obtain approval of the water and sewer connection plans 7 days - goo.gl/2fPkhU 5 Obtain certificate of no tax due 2 days 6 Notarize the affidavit/undertaking 1 day INR 100 Replaced by e-undertakings and no requirement of attestation goo.gl/Y7Ar16 7 Request building permit 60 days INR 64,151 Procedure 1: Submit online CAF along with requisite building permit fees, drawings and documents (Time: 0.5 days, Cost: 13006/- INR) goo.gl/P6NpfY
11
Procedures, Time and Cost comparison between DBR- 2017 and Current scenario (2/6)
S. No Process, Time & Cost As Per DBR- 2017 Process, Time, Cost & Legal Basis After Reform Implementation 8 Request no objection certificate from Electricity Department 1 day - Procedures Eliminated (Time : 0, Cost : 0) Not required now goo.gl/2fPkhU 9 Obtain no objection certificate from Planning Department within the MCD 14 days goo.gl/z6lQ5e 10 Receive inspection from the Electricity Department Not applicable since Procedure 8 is eliminated 11 Request and obtain building plans approval from the Director of Factories of Labor Department Integrated with CAF, completely online goo.gl/FxL8Ka 12 Obtain no objection certificate from Electricity Department 7 days 13 Request and obtain no objection certificate from Fire Department 14 Receive inspection by building section Procedure 2: Grant of online sanction within stipulated period (Time: 28 days, Cost: 0) goo.gl/P6NpfY
12
Process, Time & Cost As Per DBR- 2017
Procedures, Time and Cost comparison between DBR and Current scenario (3/6) S. No Process, Time & Cost As Per DBR- 2017 Process, Time, Cost & Legal Basis After Reform Implementation 15 Obtain sanctioned plans 1 day - Procedure 3: Payment of requisite fees and charges, as applicable, and release of sanctioned building plans (Time:1 day, to be considered as 0.5 days as per WB methodology Cost: INR 65,000/-) System is completely online goo.gl/P6NpfY On payment of requisite fee, building plan is released through digitally signed sanction letter which is available for download having integration with SMS & 16 Submit commencement notice to the MCD Procedures Eliminated (Time : 0, Cost : 0) The requirement was present in Building Bye Laws 1983 but same was removed in UBBL 2016 goo.gl/oZOttn 17 Submit Notice of commencement and completion to Labour Inspector 18 Submit notice of completion up to the plinth level Procedure 4: Intimation of completion of work up to plinth level (Time: 0.5 day, Cost : INR 500/-) Through online system at goo.gl/ONmhq7 19 Request and receive inspection at the plinth level INR 15 Procedure 5: Plinth level inspection followed by issue of plinth level inspection certificate (Time: 7 days, to be considered as 0 days as per case study, Cost: 0) Plinth level inspection is not carried out by agency as per UBBL 2016, inspection report is submitted by architect online
13
Process, Time & Cost As Per DBR- 2017
Procedures, Time and Cost comparison between DBR and Current scenario (4/6) S. No Process, Time & Cost As Per DBR- 2017 Process, Time, Cost & Legal Basis After Reform Implementation 20 Obtain C-form approval of the plinth completion 22 days - (Time : 0, Cost : 0) Subsumed in Procedure 19 (New procedure 5) 21 Request water and sewer connection approval 1 day INR 12,20,680 Integrated with CAF at Procedure 27 which is now Procedure 6 Cost reduced from 12.2 lacs to 1 lac 22 Receive on-site inspection for water and sewer connection and receive approval 34 days Integrated with CAF at Procedure 28 which is now Procedure 7 23 Request final no objection certificate from the Fire Department 24 Receive site inspection from the Fire Department 25 Receive final no objection certificate from the Fire Department 10 days Integrated with CAF at Procedure 29 which is now Procedure 8
14
Procedures, Time and Cost comparison between DBR- 2017 and Current scenario (5/6)
S. No Process, Time & Cost As Per DBR- 2017 Process, Time, Cost & Legal Basis After Reform Implementation 26 Notarize the affidavit/undertaking to request the occupancy permit 1 day INR 100/- Procedures Eliminated (Time : 0, Cost : 0) Replaced by e-undertakings and no requirement of attestation goo.gl/Y7Ar16 27 Submit notice of completion INR 1,301/- Procedure 6: Submission of application for issue of Occupancy-cum-Completion Certificate (OCC) in Common Occupancy-cum-Completion Certificate Request Form (COCCRF) along with requisite fees, drawings and documents (Time: 15 days, Cost: 13,006/- INR) goo.gl/P6NpfY 28 Receive final inspection of the construction - Procedure 7: Inspection by Municipal Corporation of Delhi (Time: 7 days, Cost : 0) 14
15
Procedures, Time and Cost comparison between DBR- 2017 and Current scenario (5/6)
S. No Process, Time & Cost As Per DBR- 2017 Process, Time, Cost & Legal Basis After Reform Implementation 29 Obtain completion/occupancy permit 30 days INR 51,145 Procedure 8: Intimation of compounding fee and charges, if applicable, and release of OCC and completion plan (Time: 0.5 days, Cost:1,00,000/- INR) goo.gl/P6NpfY TOTAL 29 Procedures 213 days INR 13,65,492 8 Procedures 60 days INR 1,91,512 % of Warehouse value (INR 5,114,479) 26.7% 3.74% 15
16
Reforms undertaken to improve building quality control index
S. No Reform Impact Legal Basis 1 Now UBBL-2016 mandates Risk based inspections are carried out during construction based on the risk category of the building A score of 2 should be assigned for “What types of inspections (if any) are required by law to be carried out during construction? ” Clause 2.5 2 Now UBBL-2016 provides professional indemnity insurance to cover latent defect liability for structural defects for 10 years Liability for structural flaws after the building is put to use lies with professionals such as architects, structural engineers, site engineers and construction company A score of 1 should be assigned for “Which parties (if any) are held liable by law for structural flaws or problems in the building once it is in use (Latent Defect Liability or Decennial Liability)?” Clause 2.10 3 Now UBBL-2016 provides that Professional are required to obtain decennial professional liability insurance to cover liabilities arising out of structural defects for 10 years A score of 1 should be assigned for “Which parties (if any) are required by law to obtain an insurance policy to cover possible structural flaws or problems in the building once it is in use (Latent Defect Liability Insurance or Decennial Insurance)?” 4 Now UBBL-2016 provides that Professionals with defined number of years of experience, university degree and being a registered architect or engineer can supervise the construction on ground A score of 1 should be assigned for “What are the qualification requirements for the professional who supervises the construction on the ground?” Annexure 1
17
Plans under process - 143 Nos. Plans rejected - 425 Nos.
Statistics of Building Plans Sanctioned by the Corporations (From 08/04/2016 to 25/07/2017) S. No. REFORMS 1 Plans received Nos. Plans Sanctioned Nos. Plans under process Nos. Plans rejected Nos. 2 Average time of sanction is approx days 3 730 building plans sanctioned within 1 day of submission 4 2086 Nos. (65%) building plans were approved within 7 days 5 Deemed construction permits were granted in 74 cases 6 Now real-time Statistics on approved and rejected cases is available on department’s website at goo.gl/6WHLr8 17
18
Quarter wise average time of grant of Construction Permits
18
19
Cases of fastest building plan approvals granted
S. No. Plan ID Applicants Name Architects Name Corporation Time Taken 1 Smt. Vibha Jain Sh. Sridhar K EDMC 09 Min. 56 sec. 2 Smt. Veena Anand Sh. Om Parkash NDMC ½ Hr. 5 min. 3 Smt. Kanta Aggarwal Ms. Shweta Agarwal ¼ Hr 3 min. 4 Sh. Gopal Krishan Khera Sh. MD Budhiraja SDMC ¾ Hr. 3 min. 5 Smt. Bhagwati Devi Aggarwal Sh. Pradeep Sharma ¾ Hr. 5 Min. 19
20
Comparison with leading economies Dealing with Construction Permits
Indicator New Zealand (CP Rank:1) Australia (CP Rank:2) Taiwan, China (CP Rank:3) India* Procedures (number) 10 8 Time (days) 93 112 60 Cost (% of warehouse value) 2.2 0.5 0.4 3.74 Building quality control index (0-15) 15 14 13 * Claim for DBR 2018 20
21
Good practices adopted in India
Single window clearance system has been implemented covering entire construction life cycle from building plan approval till issuance of occupancy certificate All internal and external agencies are integrated into the single window with no interaction required with separate agencies, however in New Zealand applicant needs to interact with multiple departments 21
22
Facebook Page to provide information pertaining to various Initiatives
22
23
Handling Day to Day Issues/communication through WhatsApp Group
23
24
Handling Day to Day Issues/communication through WhatsApp Group
24
25
Advertisement in Times of India on 06th March, 2017
25
26
Advertisement in Times of India on 11th March, 2017
26
27
Walkthrough on Building Plan approval till issuance of Occupancy cum Completion Certificate
27
28
Twitter Poll Feedback 28
29
Twitter Poll Feedback 29
30
Twitter Poll Feedback 30
31
Risk based inspections
31
32
Latent Defect Liability
32
33
Qualification requirements for professionals
33
34