1 MSEDCL’S Performance Review
MAHADISCOM 15/11/2018 MSEDCL’S Performance Review

2 Issues inherited by MSEDCL
Demand Supply Gap of 3500 to 4000 MW High T&D Loss – 35.2% (04-05) Low Collection Efficiency – 88.34% Deteriorated T&D Infrastructure (Aged and overloaded transformer and S/S) Pending applications for connections Loss making Entity (Rs.804Cr.) Poor consumer response Unmotivated and directionless employees (42 Unions) 15 November 2018

3 “10 Point Action Plan” A: Improving quality of supply and reduction of interruptions Proactive distribution network planning with viable funding plan Consumer Grievances Redressal Systems Distribution system loss reduction Improvement in Collection efficiency Circles to act as profit centers Use of technological advance and computerization for improving the efficiency, accountability, information levels & consumer satisfaction etc. Improved services to Ag. Consumers Measures to improve working conditions of employees Demand Side Management and peak load management (Measures to reduce load shedding) B: KKPIs established for measurement of performance of the above action points C: Communication plan D: Organizational Changes 15 November 2018

4 Performance – MahaVitaran
* NYD: Not Yet Decided 15 November 2018

5 1. Ensuring Reliable and Quality Power Supply
Programs Preventive Maintenance: Identification of problems feeders in each sub-division Pre-monsoon Work (Tree cutting) Repair: loose / long span Arrange repairs and preventive maintenance during planned Load shedding DTC maintenance – Oil level checking Reduce loading on DTCs /Install new DTCs ( 100% Diversity) Action plan for prevention of DTC failure & quick replacement of DTCs,Monitoring through DSS control room Reduce length of LT line / HT:LT ratio Capacitor Maintenance Renovation & Modernisation Schemes for: Breakers, CTs, Capacitors,HT,LT lines ,indoor to Outdoor s/stn equipments 15 November 2018

6 Formats for SAIDI SAIFI and CAIDI have been finalized
KKPIs Formats for SAIDI SAIFI and CAIDI have been finalized Sub-Division wise data expected by 15 January * - Sample calculation for the sub-division Aurangabad in the month of Aug’ 05 15 November 2018

7 2. Proactive distribution network planning
Programs S/Dn. wise information about Load Profile & Demand growth for next five years S/Dn wise Infrastructure up gradation plan. Circlewise viable financing plan. Monitoring system for construction work plan & financial plan Detailed presentation being made separately 15 November 2018

8 3. Consumer Grievances Redressal System
Programs Complaint book at G.P./ S/Dn. / Section Office & J.M./ J.E. to visit these offices and redress complaints CFC at 50 S/Dns. to be expanded to 500 S/Dns. Consumers have Single Window Grievance Solving facility for For new connection /change of name in time Billing complaint/other complaints be resolved in specified time Call centers to be established in all major towns and municipal corporations KKPI FY 05-06 FY 06-07 Circle / Zone Wise Details Target Achieved (till Nov’05) Pending RCI Consumers NYD 275579 Progress of call centers 10 3 5 Progress OF CFC 50 1 500 Consumers grievance Redressal established in 11 zones and internal grievance Redressal units established in all O&M Circles 15 November 2018

9 4. Distribution Loss Reduction
Program Energy accounting of all levels DTC metering / 100 % consumer metering Theft cases including abetment HVDS Alternate meter reading by outsourced agency Mini franchisee scheme NSC information (in time) to IT Monitoring of temporary connection to builders / commercial establishments DRUM Project (10 Divisions ) 15 November 2018

10 KKPI for Distribution Loss Reduction T&D Losses
05-06 06-07 Particulars Target Achieved (Sept 05) EHV system/ Transmission Loss 6.00% 7.21% 5.80% Distribution Loss 28.00% 27.11% 25.00% T&D Loss 32.25% 32.36% 29.25% 15 November 2018

11 KKPI for Distribution Loss Reduction DTC Losses
Particulars Total No. of DTCs with losses > 50 % 25-50 % % 0-5% <0% Jul-05 No.of DTCs for which EA report has been genrated by IT atleast once 43291 9030 8491 14671 5565 5534 Proportion 21% 20% 34% 13% Oct-05 46642 9773 8978 15329 5953 7350 19% 33% 14% 15 November 2018

12 Theft Cases Detected In Rs lakhs (Jun – Nov 2005)
KKPI for Distribution Loss Reduction Theft Cases Detected (Jun – Nov 2005) In Rs lakhs 15 November 2018

13 5. Improvement in collection efficiency
Programs Elimination of average/abnormal bill Timely feeding of NSC report and first bill issue Monitoring of consumers to whom installments are granted Collection as per target 100% disconnection above Rs 5000/- arrears Reduction of live arrears / P.D. arrears Early disposal of B-80 Cases Spot billing Action on PD consumers declared live/verification & police cases ATM Cash Collection Centers (ATMs at 50 Locations in urban areas) e-payment / drop boxes KKPI 05-06 06-07 Zone/ Circle Wise Details Target Achieved (till Oct 05) Collection efficiency % 90.34% 93.80 % 89.67% a) % b) 92.34% Normal billing percentage 100% 78% Cases with arrears above Rs.5000 NYD 304847 a  without AG b  with AG 15 November 2018

14 Steps Taken to Improve Collection Efficiency
E-payment in Pune, Bhandup and Kalyan circles Spot Billing is introduced in Pune and Nagpur - To be introduced in 15 more locations by January 2006 15 November 2018

15 Repatriation (Rs. Crores)
Months  Increase April 981.83 984.82 0.30% May 953.63 11.56% June 976.81 6.00% July 983.53 4.62% August 912.32 34.91% September 948.25 17.50% October 967.51 1226 26.72% November 957.26 12.48% December January 1045.7 February March Total Total June to Nov Average June to Nov 957.61 16.82% 15 November 2018

16 Allocation of budget to circle
6. Profit Centre Programs Allocation of budget to circle Monitoring income and expense vis-a vis budget Analysing variation in income/expenditure Quarterly review of profit center Comparing distribution losses with respect to targets KKPI : Profit / Deficit 15 November 2018

17 7. Using technological advances for improving efficiency
Program Implementation of MIS,DA,AMR e-billing , online payment , SEVAK ATM, Bill junction /Bill desk e-tendering GIS network mapping KKPI 05-06 06-07 Details Target Achieved (till Oct 05) AMR progress 20000 To be completed by March ‘07 Not yet finalized SCADA progress 10 (by June 06) 10 No. of GIS maps ready NYD All urban electricity bills on internet 15 November 2018

18 8. Improved services to agricultural consumers
Programs Reduce pending Ag connections Krishi Vikas Applications (received: , released: 69737) DTC failure rate reduction Action plan Timely Ag NSC report to IT KKPI 05-06 06-07 Zone Wise Details Target Achieved (till Nov 05) Pending AG connections 1,00,000 42,361 15 November 2018

19 DTC FAILURE 2004-05 18.52% 2005-06 (Up to Nov 05) 11.34%
15 November 2018

20 9. Improvement in working conditions of employees
Programs Compulsory use of safety T&P (Earthing, Zoola, Hand gloves, Insulated pliers) Reduction in No. of accidents ( Fatal/Non-fatal) Timely payment of TA bill / Advances / CPF / Gratuity / Dues / Increments etc. Work culture / boosting employee moral by motivation Honesty/Integrity/Hardwork to be rewarded Special training programs to improve customer services & tech capabilities Mobile training program Regular communication with employees : Varta Uniform for all employees KKPI No of electrical accidents employees/outsiders Training of employees (No.s & mandays) Reduction in employees grievances 15 November 2018

21 10. DSM and Load management
Programs Single phasing scheme: 9800 Villages( Phase I) , 4515 (Phase II) Special feeders for Gaothans : 9846 Villages, 1650 feeders Akshay Prakash Yojna: 686 Villages Reactive Power Management through Capacitors: 3898 MVAR Energy Saving Scheme for R/C/I/Public Lighting (CFL) KKPI 05-06 06-07 Circle Wise Details Target Achieved (till Nov 05) No. of APY villages NYD 686 Special Gaothan feeder Schemes 9846 villages /1650 feeders 515 Crores 36 feeders 95 MW load relief Remaining feeders from 05-06 Single Phase Scheme 9800 (Nos) 235 Crores 7000 (Nos) 4515 (Nos) 170 Crores Capacitors( Substation / DTCs) WIP 20000 DTC 1,35000 AG Pumps LTLMS DSM/ Energy Conservation 10 lakh CFLs 1.25 Lakh 20 lakh 15 November 2018

22 Energy conservation measures
CFL Lamps Projected load saving of 9.75 MW during peak hours through installation of 3 lakhs CFL on pilot basis in Nasik & Thane Capacitor installation program Load saving of 500 MW through installation of LTLMS Capacitors in 20 Districts within 2 years 15 November 2018

23 Summary of New Initiatives taken
Collection increased by 16.82% From Rs Crs. in June – Nov’ 04 to Rs Crs in Apr – Nov’ 05 Distribution loss reduced by 2.14% From 29.25% in Apr – Sept’ 04 to 27.11% in Apr – Sept’ 05 Load profile and construction work plan for Rs. 11,424 crores finalized DTC failure Rate reduced by 7.18% From 18.52% in to 11.34% in Apr – Nov’ 05 Energy accounting of 51,000 DTCs in progress 15 November 2018

24 Summary of New Initiatives taken
Detection of 21,975 theft cases (from April to October ‘05) Consolidated distribution Automation plan – SCADA, AMR, e-billing etc. Formation of Quality control cell to ensure purchase of best quality material Four S.Es nominated as M.D’s representatives for monitoring various activities of the MSEDCL in the field DSM – Akshya Prakash Yojana, use of CFLs, capacitor installation on DTCs and at sub-stations 15 November 2018

25 Issues with MSEB Holding Company /Govt. of Maharashtra
Appointment of Director (Finance), Director (HRD), Director (Operations) Valuation/ New Balance Sheet/ New P&L Account Pending Govt. Guarantees & release of funds Funds for removal of backlog of Ag Pumps-Rs Cr Authorization of employees of MSEDCL for theft detection under the EA 2003 Establishing dedicated police stations and special courts- Appointments of SP’s on deputation 15 November 2018

26 Issues with MSEB Holding Company /Govt. of Maharashtra (Contd…)
M/s. Mula Pravara Electric Co-op Society – recovery of arrears and other pending issues – request for permission for disconnection of supply Amendment to EA 2003 to be applicable to state of Maharashtra-for removing the role of district consumer forums Arrears of payment of State Govt. Dept. Single point bill recovery from Police Dept. Regulatory Issues- Regulations to be framed under the EA 2003 15 November 2018

27 Thank You 15/11/2018 © 2004 PricewaterhouseCoopers. All rights reserved. PricewaterhouseCoopers refers to the network of member firms of PricewaterhouseCoopers International Limited, each of which is a separate and independent legal entity. *connectedthinking is a trademark of PricewaterhouseCoopers.