Presentation is loading. Please wait.

Presentation is loading. Please wait.

Moab UMTRA Uranium Mill Tailings Remedial Action

Similar presentations


Presentation on theme: "Moab UMTRA Uranium Mill Tailings Remedial Action"— Presentation transcript:

1 Moab UMTRA Uranium Mill Tailings Remedial Action
July, 2018 looking northeast, May, 2018 image courtesy of DOE Second Quarter Review for Steering Committee by Lee Shenton Grand County UMTRA Liaison

2 Highlights FY18 funding increased $2.9 mil to ~$38 mil
FY19 funding ~$42 mil by House, pending Senate passage 58% of tailings removed Defensive wells still protecting river 4 days x 34 railcars x 4 containers x 38 tons average as of Nov, 2012 Observations provided by Grand County UMTRA Liaison on behalf of the Moab Tailings Project Steering Committee, as established by Grand County Resolution 2970A.

3 Non-Defense Environmental Small Projects
Five other DOE Non-Defense Environmental Small Projects ARRA* ARRA* ARRA* * American Recovery and Reinvestment Act of 2009, aka “Stimulus” Tailings shipment and funding information provided by Moab UMTRA. Other observations provided by Grand County UMTRA Liaison on behalf of the Moab Tailings Project Steering Committee, as established by Grand County Resolution 2970A.

4 201,000 tons per month with ARRA
58% of Tailings Removed Assumed 40,000 tons for July, 2018 Shipments curtailed Dec 2012 – Feb 2013 due to funding cuts 39,400 tons per month since workforce reduced Shipments interrupted by rock slide 201,000 tons per month with ARRA Tailings shipments suspended due to lack of adequate funding. Tailings shipment and funding information provided by Moab UMTRA. Other observations provided by Grand County UMTRA Liaison on behalf of the Moab Tailings Project Steering Committee, as established by Grand County Resolution 2970A.

5 Main Project Goals Move tailings away from Colorado River
Protect river by intercepting ground water contaminants Remediate vicinity properties (VP) Reclaim project sites at Moab and Crescent Junction UNOFFICIAL PROJECTION by Liaison, actual end dates depend on future funding levels ACTIVE REMEDIATION 1 remaining of 15 Total project costs are estimated at about $1 billion At the current rate (rolling six month average) the last of the tailings will be shipped in late-2032. Grand County UMTRA Liaison 2018

6 Impacts Around Moab: 17Q2-18Q1
Per Cent of Allowable Impact Average for last 4 quarters 8 RADON 13 GAMMA PARTIC 40 30 48 17 23 1 Guideline 3.7 100% 5 61 Offsite radon not to exceed 3.0 pCi/L above background 22 2.5 61% 12 Radon level at northwest boundary Three exposure risks, OFFSITE stations, 24x7 monitoring, 0=bkgd, 100=NRC max for public exposure. 1 Background 0.7 0% Impacts Around Moab: 17Q2-18Q1 pCi/L = picoCuries per Liter, radiation from Radon gas in the air, L4Q average

7 Impacts Around CJ: 17Q2-18Q1 Per Cent of Allowable Impact
Average for last 4 quarters RADON 23 East Rail Bench GAMMA 17 5 PARTIC 67 Thompson Springs 16 mREM Guard Hut 192 100% Gamma Guideline Nearest Home 1% 1 93 0% 3Q Radon and gamma data installed Nov 27th, radioparticulate data installed Dec 12th, FLS Background 92 mREM in CJ area Guideline: Gamma not to exceed 100 mREM/yr above background. Gamma total for last 12 months at nearest home was 93 mREM, So 1% above CJ background of 92 mREM. Impacts Around CJ: 17Q2-18Q1 mREM = milli-Roentgen Equivalents in Man, biological dose equivalent, sum of L4Q

8 Moab Radon CJ Radon pCi/L for quarter pCi/L for quarter
South Boundary Moab Radon CJ Radon Guard Hut NW Boundary Total mREM for last four quarters Total mREM for last four quarters NW Boundary Moab: 129 orange, S bdry blue, MEI green, ANP dots CJ: Asay green, Guard Hut purple, rail bench orange, Thompson dots background Environmental monitoring data provided by Moab UMTRA. Other observations provided by Grand County UMTRA Liaison on behalf of the Moab Tailings Project Steering Committee, as established by Grand County Resolution 2970A.

9 Airborne Radioparticulates
Total DCG for 17Q2 – 18Q1 DCG = Derived Concentration Guideline, a calculated estimate of radiation levels from radioparticulates Particulates roughly track rate of tailings shipments during ARRA SHIPMENTS CURTAILED Dec’12-Feb’13 Background averages 1.5 mREM per year (DCG) based on average of last 9 quarters before excavations began. Environmental monitoring data provided by Moab UMTRA. Other observations provided by Grand County UMTRA Liaison on behalf of the Moab Tailings Project Steering Committee, as established by Grand County Resolution 2970A.

10 Ground Water Remediation
Extraction wells between pile and river intercept contaminated ground water Fresh water “curtain” injected when river is low Side channel habitat protected seasonally with added fresh water Injection wells between side channel and Riverside Trail 908,000 pounds ammonia 4,880 pounds uranium extracted through June, 2018 (kept out of river) Injecting during winter does not protect habitat any better, and tends to clog up wells. ACTIVE ground water remediation could continue 1-2 years after pile removed. Supplemental standards may be applied for PASSIVE remediation. Well field data provided by Moab UMTRA. Other observations provided by Grand County UMTRA Liaison on behalf of the Moab Tailings Project Steering Committee, as established by Grand County Resolution 2970A.


Download ppt "Moab UMTRA Uranium Mill Tailings Remedial Action"

Similar presentations


Ads by Google