Presentation is loading. Please wait.

Presentation is loading. Please wait.

SEC Distribution Field Force Overview

Similar presentations


Presentation on theme: "SEC Distribution Field Force Overview"— Presentation transcript:

1 SEC Distribution Field Force Overview
Distribution Contractors Day with Saudi Electricity Company October 28th, 2015

2 The contracting phase consists of two main elements: tendering process and contracting process
Prequalification Contracting Operation 1. Tendering 2. Contract 1 2 Key levers 1.1 Ceiling distribution & coverage assurance 2.1 General terms & conditions Key elements 1.2 Bidding mechanism 2.2 Performance management 1.3 Pricing mechanism 2.3 Others

3 A number of key recommendations are implemented in Phase 1
13_84 A number of key recommendations are implemented in Phase 1 Prequalification Tendering Contracting 1 2 3 Key Changes' Prequalification model: new prequalification process and criteria to assess contractors Coverage model: model will be used on office level to help match supply to demand in all offices across the Kingdom Tendering strategy: will include the number of required contractors in each electricity department and how their ceilings will be defined Pricing mechanism: reference prices along with an improved pricing mechanism are expected to yield more accurate prices Contract ceiling: contract ceiling is distributed based on contractors’ work capacities, prequalification scores and bids Awarding strategy: will determine who gets awarded a contract, and what their ceiling will be. If contractor refuses to sign, his ceiling is given to the next in line contractor (cascading) Guarantees: Bid bonds are required from contractors. These are refundable unless contractor confirms intent to sign contract. Bank guarantees are 5% of contract ceiling. Contract duration: new UR contract term is reduced to 2 years with 1 optional year Payment terms: 50% payment upon completion of work is incorporated to allow better liquidity KPIs: KPIs are integrated in the contract to objectively measure contractor's performance, and linked to SEC’s evaluation sheet Incentives & penalties system: the building blocks for a future incentive & penalty system are put in place

4 Prequalification Tools Contracting & tendering Tools
12+ operational tools are developed to facilitate the operationalization of the new process 19_84 Prequalification Tools Contracting & tendering Tools Contracting guide Updated contract clauses KPI evaluation Price uniformization Coverage analysis model Value allocation & commitment Instructions for Bidders Work order allocation tool

5 Initiation includes developing historic reference prices to gauge
contractor bids 11267_84 Tendering Prequal Contracting Bids from last tendering process are entered into model Model applies appropriate inflation factor New price uniformization methodology is applied to bids Final historic reference prices are generated Historic bids entered to be compared against new contract bids An inflation factor based on a detailed contractor cost model is applied to historical bids New contract bids are uniformized on a line item level using a standard deviation methodology Bids are compared to historic reference prices and final prices are calculated

6 Contractors’ bids and prequal scores will be used in determining the
contract ceilings 13324_84 20_84 Tendering Prequal Contracting SEC will determine total coverage required in every office …And distribute it accordingly to contractors Demand Supply x 150% ~ x 40% Note: This data pertains to the Madinah office only Source: SEC data Example of Madinah Office

7 5 star safety system is now a mandatory system that all contactors
must abide by 17414_84 2_85 Tendering Prequal Contracting contract Safety requirements are updated to integrate 5-star SYSTEM contract Safety requirements are updated to integrate 5-star SYSTEM Safety KPIs are incorporate in contractor performance measurement: Number of Type 1 (First Aid) Incidents per 1 M work Number of Type 2,3,4 (Injury, Handicap, Death) Incidents per 1 M work Percentage of times that work site complied with SEC safety standards 12% of the points in the prequalification scoring pertains to safety record & HSE systems Safety performance averaged over the last three months will be reflected in work allocation through KPIs Contract addendum enforces the 5-star safety system in performance Safety systems will be checked in post-signing stage. Contract is subject to termination if standards are not met Non-compliance on safety requirements for trenches subject contractors to a penalty of 200 SAR

8 ~10 KPIs were developed based on current situation & best practices
3_ _84 Tendering Prequal Contracting Category KPI Description Timely Work Performance 1. Percentage of WOs completed within time (count) Total work orders completed on time compared to total number of WOs completed 2. Percentage of WOs completed within time (value) Value of all work orders completed on time compared to all work value performed under URC 5. Average delay on delayed WOs (count) The average number of delayed days for all work orders that have delays 7. Density of contractor work Average work value for a given contractor's work orders Safety Performance 9. Number of Type 1 (First Aid) Incidents per 1M SAR work Number of type 1 incidents that happen with a given contractor compared to his value of work 10. Number of Type 2,3,4 (Injury, Handicap, Death) Incidents per 1M SAR work Number of type 2, 3, 4 incidents that happen with a given contractor compared to his value of work 12. Percentage of times that work site complied with SEC safety standards Number of contractor site visits that complied with SEC safety standards compared to total number of site visits Collaboration & Responsiveness 18. Average number of days to accept work order Response time of contractor when a work order is issued 20. Number of emergency and maintenance rejected WOs* Number of emergency and maintenance rejected work orders in a given month 21. Number of construction rejected WOs Number of construction rejected work orders in a given month

9 dashboard for KPIs linked to the standard evaluation form
We have developed a new dashboard for KPIs linked to the standard evaluation form 20494_ _84 Tendering Prequal Contracting KPI dashboard to be generated monthly… … and automatically linked to evaluation using weights New evaluation system will the building block for a future incentive & penalty scheme


Download ppt "SEC Distribution Field Force Overview"

Similar presentations


Ads by Google