TUSD Facilities Update November 8, 2010. Deferred Maintenance.

Similar presentations


Presentation on theme: "TUSD Facilities Update November 8, 2010. Deferred Maintenance."— Presentation transcript:

1 TUSD Facilities Update November 8, 2010

2 Deferred Maintenance

3 What is Deferred Maintenance? TUSD – Planned Maintenance Major repair or replacement of existing school building components so that the educational process may safely continue.

4 Deferred Maintenance Eligible Repairs Floor Covering Painting Electrical Classroom Lighting Roofing Plumbing HVAC Wall Systems Paving Underground Toxic Tank Asbestos Lead

5 Typical Facilities Component Life Spans ComponentTimeframeRepair/Replacement Carpet15 YearsRotation Interior Paint10 Years* As Needed Exterior Paint15 Years* As Needed HVAC15 Years* As Needed Roofing20 Years* As Needed * Function and condition assessed annually

6 09/10 Deferred Maintenance Projects: ProjectSchoolExpenditure Carpet ReplacementUtt MS$135,825 Walkway Roof Replacement Beswick ES$114,640 Exterior Painting Heideman ES Tustin HS $39,407 Slurry/StripingVarious Sites (12)$119,459 $409,331

7 Proposed 10/11 Deferred Maintenance Repairs: ProjectSchoolPreliminary Budget Carpet ReplacementTustin Ranch ES$250,000 Exterior Painting(2) Sites – TBD$300,000 Roof Replacement(2) Sites – TBD$200,000 Slurry/StripingVarious Sites – TBD$100,000 HVAC ControlsVarious Sites – TBD$100,000 Replace HVAC UnitsVarious Sites – TBD$250,000 $1,200,000

8 Building Program * This presentation includes construction projects that are funded from a number of sources including: CFDs, General Obligation Bonds (Measure G & L), and Statewide school construction bonds.

9 Completed Projects 2010: ProjectBudgetStatus Orchard Hills K-8$56,000,000Complete FHS Pool Replacement$ 3,900,000Complete BHS Field Replacement$ 200,000Complete * THS Summer Modernization$ 5,600,00098% Complete * Math/Special Education Remodel and Building 230 HVAC $65,700,000

10 Orchard Hills K-8 - Adminstration

11 Orchard Hills K-8 - Library

12 Orchard Hills K-8 - Gymnasium

13 FHS Pool Replacement

14

15 BHS Field Replacement – Progress Photo

16 BHS Field Replacement - Completion

17

18 THS Summer Modernization - Courtyard

19 THS Summer Modernization - Exterior

20 THS Summer Modernization – Special Ed.

21 THS Summer Modernization – Math

22 Projects in Construction ProjectBudgetStatus Heritage School$12,000,00070% Complete THS Science Center$ 11,800,00060% Complete FHS Locker Room Remodel$ 4,500,00095% Complete $28,300,000

23 Heritage School - Administration

24 Heritage School - Multipurpose

25 Heritage School – Storm Drain Filtration

26 Heritage School – Classroom Building C

27 THS Science Center - Exterior

28

29 THS Science Center – Interior Stairs

30 THS Science Center - Classroom

31 FHS Locker Room Remodel - Exterior

32 FHS Locker Room Remodel - Restrooms

33 FHS Locker Room Remodel - Showers

34 FHS Locker Room Remodel – Lockers

35 Proposed Future Projects 2010/11 ProjectCost EstimateStatus BHS Snack Bar/Restrooms$600,000DSA Review THS Gymnasium$ 9,000,000DSA Approved FHS Events Center$10,500,000DSA Approved MS Multipurpose Facilities$20,000,000DSA Review * Currie Modernization$ 4,100,000In Design * Building 400, 500 & 600 $44,200,000

36 Building Program Summary CategoryBudget Completed Projects 2010$65,700,000 Projects in Construction$28,300,000 Proposed Future Projects 2010/11$44,200,000 $138,200,000 * The referenced construction projects are funded from a number of sources including: CFDs, General Obligation Bonds (Measure G & L), and Statewide school construction bonds.


Download ppt "TUSD Facilities Update November 8, 2010. Deferred Maintenance."