Download presentation
Presentation is loading. Please wait.
Published byPresley Lakey Modified over 10 years ago
1
Jon Chiglo, PE Project Director 2014 Construction Plans
2
Tentative 2014 Construction Timeline
3
Access to businesses and residences Local access will remain during business hours and at all times to residences. -Business signage -Detour signage -Temporary gravel roads
4
2014 Minn. Approach Work Contracted Maximum Impacts North Frontage Road50 calendar days Osgood Avenue40 calendar days Greeley Street40 calendar days Oakgreen Avenue25 calendar days South Frontage Road70 calendar days
5
Highway 36 Single-lane in each direction – Open AT ALL TIMES Work: Resurface road Westbound: Spring to mid-summer 2014(red) Eastbound: Mid-summer to fall 2014(green)
6
South Frontage Road – East of Osgood Closed to through traffic Local access to businesses and residences Work: Resurface road, replace public utilities Spring to mid-summer 2014 (red)
7
Hwy 95 / Lookout Trail / Sunnyside Hwy 95 Single-lane in each direction Work: Construct 4-lane road Spring to mid-summer 2014 (red) Lookout Trail Work: Reconstruct access to Hwy 95 to right in/out intersection Spring to mid-summer 2014 Sunnyside Marina Work: Reconstruct driveway Spring to mid-summer 2014
8
North Frontage Road North Frontage Road – Northwestern to Greeley Possible detours to access North Frontage Road. Work: Resurface road, add turn lane, add curb & gutter Spring to mid-summer 2014 (red)
9
North Frontage Road North Frontage Road – Greeley to Osgood Possible detours to access North Frontage Road, either from Greeley St. or Osgood Ave. Permanent closure of right in/out connection to Hwy 36 Work: Resurface road, add turn lane, add curb & gutter Spring to mid-summer 2014 (red)
10
Greeley St./Oakgreen Ave. Intersection North/south traffic closed for 2 periods of 6 calendar days each OakgreenClosed between S. Frontage Road and 58 th St./Oak Park Blvd. for 25 days. Local residential access only. (green) Work: Build new frontage road system further away from Hwy 36; shift intersection to the east; install three traffic signal systems; add double left turn lanes
11
Osgood Ave. Intersection North/south traffic closed for 2 periods of 6 calendar days each Work: Add double left turn lanes, resurface intersection Osgood intersection and Greeley-Oakgreen intersection WILL NOT close at the same time
12
Final Hwy 36 Intersections Looking East
13
S. Frontage Road – Oakgreen to Osgood Possible detours/temporary roads to access businesses/residences Work: Resurface road, add turn lane, add curb & gutter, replace public utilities Late summer to fall 2014 (blue)
14
Trail Construction Work: Construct pedestrian/bicycle trails Occurs as time allows, complete in fall 2014
15
Other area county/city projects
16
Wisconsin Approach Work Work occurs: March 2014-late summer 2016 Goal: Open WIS 64 at the same time as the new bridge
17
2014 Wisc. Approach Work Grade from the bluff to County Road E Build the WIS 35 overpass over the new WIS 64
18
2014-2017 Wisc. Approach Schedule
19
The New St. Croix Crossing
20
Bridge Superstructure Timeline: Dec. 2013 to late-summer/early fall 2016 Winter/Spring 2014 Impacts: Pile driving on the Minnesota shoreline and work on Pier 8 Through May 6 days per week -- 7 a.m.-7 p.m. Goal: As much work done as possible while windows are closed
21
Minnesota Land Piers Work Progress
22
2014 Bridge Construction Build all river piers and land piers vertically (Piers 1-13)
23
2014 Bridge Construction Begin casting segments – Approx. 1,000 656 extradosed segments 330 approach segments Two casting yard locations -- Gray Cloud Island and at the Hwy 36/95 interchange Place first segment in fall 2014
24
River Bridge Construction Staging
25
Segment Lifter Example
26
Construction Sequence
87
Contact Information Hotline 1-855-GO-CROIX ( 462-7649) Email stcroixcrossing.dot@state.mn.us Website/Regular project updates www.mndot.gov/stcroixcrossing Facebook www.facebook.com/saintcroixcrossingmndot Twitter @stcroixcrossing
88
Questions?
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.