Presentation is loading. Please wait.

Presentation is loading. Please wait.

Jon Chiglo, PE Project Director 2014 Construction Plans.

Similar presentations


Presentation on theme: "Jon Chiglo, PE Project Director 2014 Construction Plans."— Presentation transcript:

1 Jon Chiglo, PE Project Director 2014 Construction Plans

2 Tentative 2014 Construction Timeline

3 Access to businesses and residences Local access will remain during business hours and at all times to residences. -Business signage -Detour signage -Temporary gravel roads

4 2014 Minn. Approach Work Contracted Maximum Impacts North Frontage Road50 calendar days Osgood Avenue40 calendar days Greeley Street40 calendar days Oakgreen Avenue25 calendar days South Frontage Road70 calendar days

5 Highway 36 Single-lane in each direction – Open AT ALL TIMES Work: Resurface road Westbound: Spring to mid-summer 2014(red) Eastbound: Mid-summer to fall 2014(green)

6 South Frontage Road – East of Osgood Closed to through traffic Local access to businesses and residences Work: Resurface road, replace public utilities Spring to mid-summer 2014 (red)

7 Hwy 95 / Lookout Trail / Sunnyside Hwy 95 Single-lane in each direction Work: Construct 4-lane road Spring to mid-summer 2014 (red) Lookout Trail Work: Reconstruct access to Hwy 95 to right in/out intersection Spring to mid-summer 2014 Sunnyside Marina Work: Reconstruct driveway Spring to mid-summer 2014

8 North Frontage Road North Frontage Road – Northwestern to Greeley Possible detours to access North Frontage Road. Work: Resurface road, add turn lane, add curb & gutter Spring to mid-summer 2014 (red)

9 North Frontage Road North Frontage Road – Greeley to Osgood Possible detours to access North Frontage Road, either from Greeley St. or Osgood Ave. Permanent closure of right in/out connection to Hwy 36 Work: Resurface road, add turn lane, add curb & gutter Spring to mid-summer 2014 (red)

10 Greeley St./Oakgreen Ave. Intersection North/south traffic closed for 2 periods of 6 calendar days each OakgreenClosed between S. Frontage Road and 58 th St./Oak Park Blvd. for 25 days. Local residential access only. (green) Work: Build new frontage road system further away from Hwy 36; shift intersection to the east; install three traffic signal systems; add double left turn lanes

11 Osgood Ave. Intersection North/south traffic closed for 2 periods of 6 calendar days each Work: Add double left turn lanes, resurface intersection Osgood intersection and Greeley-Oakgreen intersection WILL NOT close at the same time

12 Final Hwy 36 Intersections Looking East

13 S. Frontage Road – Oakgreen to Osgood Possible detours/temporary roads to access businesses/residences Work: Resurface road, add turn lane, add curb & gutter, replace public utilities Late summer to fall 2014 (blue)

14 Trail Construction Work: Construct pedestrian/bicycle trails Occurs as time allows, complete in fall 2014

15 Other area county/city projects

16 Wisconsin Approach Work Work occurs: March 2014-late summer 2016 Goal: Open WIS 64 at the same time as the new bridge

17 2014 Wisc. Approach Work Grade from the bluff to County Road E Build the WIS 35 overpass over the new WIS 64

18 2014-2017 Wisc. Approach Schedule

19 The New St. Croix Crossing

20 Bridge Superstructure Timeline: Dec. 2013 to late-summer/early fall 2016 Winter/Spring 2014 Impacts: Pile driving on the Minnesota shoreline and work on Pier 8 Through May 6 days per week -- 7 a.m.-7 p.m. Goal: As much work done as possible while windows are closed

21 Minnesota Land Piers Work Progress

22 2014 Bridge Construction Build all river piers and land piers vertically (Piers 1-13)

23 2014 Bridge Construction Begin casting segments – Approx. 1,000 656 extradosed segments 330 approach segments Two casting yard locations -- Gray Cloud Island and at the Hwy 36/95 interchange Place first segment in fall 2014

24 River Bridge Construction Staging

25 Segment Lifter Example

26 Construction Sequence

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47

48

49

50

51

52

53

54

55

56

57

58

59

60

61

62

63

64

65

66

67

68

69

70

71

72

73

74

75

76

77

78

79

80

81

82

83

84

85

86

87 Contact Information Hotline 1-855-GO-CROIX ( 462-7649) Email stcroixcrossing.dot@state.mn.us Website/Regular project updates www.mndot.gov/stcroixcrossing Facebook www.facebook.com/saintcroixcrossingmndot Twitter @stcroixcrossing

88 Questions?


Download ppt "Jon Chiglo, PE Project Director 2014 Construction Plans."

Similar presentations


Ads by Google