PRESENTATION TO PUBLIC HEARING ON CONDITIONAL GRANTS 22 MAY 2007

Similar presentations


Presentation on theme: "PRESENTATION TO PUBLIC HEARING ON CONDITIONAL GRANTS 22 MAY 2007"— Presentation transcript:

1 PRESENTATION TO PUBLIC HEARING ON CONDITIONAL GRANTS 22 MAY 2007
VOTE 9 DEPARTMENT OF HOUSING AND LOCAL GOVERNMENT NORTHERN CAPE PRESENTATION TO PUBLIC HEARING ON CONDITIONAL GRANTS 22 MAY 2007

2

3 ALLOCATION VS EXPENDITURE 2006/07
The Northern Cape was allocated a budget of R104, 774m for the 2006/07 in respect of the Integrated Housing and Human Settlement Development grant. The expenditure for 2006/07 was R104,713 A rollover request of R60,000 was submitted to treasury

4

5 DRAW DOWNS VS. ACTUAL EXPENDITURE 2006/2007

6

7 REASONS FOR SLOW SPENDING
The first two quarters expenditure trends was low due to non-performing contractors on a number of projects Capacity constraints within the department

8 HOUSING ACHIEVEMENTS DURING 2006/07
Houses Services District Running Blocked Frances Baard 701 247 528 Kgalagadi 277 180 Siyanda 278 153 311 Namakwa 21 76 10 181 Pixley ka Seme 327 215 319 56 Total houses and services 1604 691 1348 237 Grand total 2295 1585

9 PROGRESS ON BLOCKED PROJECTS
The department had 52 blocked projects 25 of these projects have been completed 24 are currently under construction for completion by March 2008 3 blocked projects under construction will only be completed by March 2009

10

11

12 SUMMARY OF PLANNED HOUSES PER DISTRICT 2007-08
Top structures Service Sites Allocation R’000 Frances Baard 507 522 37,899 Kgalagadi 180 100 6,717 Siyanda 455 922 25,560 Namakwa 290 12,203 Pixley Ka Seme 1 234 1241 42,798 TOTAL 2 666 2785 125,177

13 CROSS BOUNDARY HOUSING PROJECTS TO BE COMPLETED BY NORTH WEST
Project name Project manager/ Developer Current status Completion date Ba- Ga Motlhware 500 Subs Metro Projects 334 Complete May 2007 Mothibistad 1000 Subs Tshireletso Developers 950 Complete June 2007 Seoding 750 M3D 400 Complete 250 Foundations September 2007 Pampierstad Ext 2 250 Subs Rectification of houses March 2008 Pampierstad Ext 4 900 Subs 628 Completed

14

15 THANK YOU