1 Recent VT Results in the STF-2 cavities
Outline STF cavities VT results Summary STF Cavity Group: H. Hayano, E. Kako, S. Noguchi, M. Satoh, T. Shishido, Y. Yamamoto and K. Watanabe Kirk TTC Meeting

2 Outline Facility status at STF
MHI#12 and #13 achieved ILC specification Very recent results of MHI#14 and #15 Summary TTC Meeting

3 STF location South East West North ATF/ATF2 STF
SC cavity fabrication facility East West ATF/ATF2 STF North TTC Meeting

4 Outline of STF Cryogenic liquefier EP No.2 tunnel underground
TTC Meeting

5 Fabricated(ing) 9-cell cavities
MHI#1-#4 (STF Phase-1) MHI#5-#9 (S1-Global) MHI#8 was sent to J-Lab for S0 plan! MHI#10, #11 (S0) MHI#12, #13 (Quantum Beam Project) HIT#1 (New vendor) TOS#1 (New vendor) IHEP#1 (International Collaboration) MHI-A (for cost reduction study) MHI#14~#22 (STF Phase-2) TTC Meeting

6 Typical Process for Vertical Testing
as received from a vendor f0 & Field flatness measurement surface treatment (bulk EP∼100μm) Optical inspection annealing >96% surface treatment (light EP ∼20μm, degreasing, HPR) Optical inspection pre-tuning Two weeks per one cycle failure Cryomodule test V.T. success Cavity string TTC Meeting

7 Cavity diagnostic system at STF
396 carbon resistors 182 PIN photo diodes 8 second sound sensors Radiation monitor Electron probe TTC Meeting

8 MHI#12 and #13 achieved ILC spec.
MHI#12 1st VT MHI#12 2nd VT MHI#13 1st VT MHI#13 2nd VT TTC Meeting

9 Radiation level They are perfect cavities! Every data Only recent data
Radiation level for MHI#12 and #13 was very low! They did not have any defect and problematic EBW bead. They are perfect cavities! TTC Meeting

10 Case of MHI#14 1st V.T. 2nd V.T. 26.0MV/m  14.1MV/m 25.9MV/m  12.4MV/m 15.0MV/m Cell #8 heating 13.0MV/m Cell #8 heating We observed the same situation between 1st and 2nd V.T. Around 26MV/m in the first power rise, explosion occurred and radiation level became much higher. TTC Meeting

11 Case of MHI#14 Radiation monitor 1st power rise @π mode
After the explosive event, the radiation level was much higher. The signals from PIN diodes at top flange were also drastically changed. TTC Meeting

12 Case of MHI#14 1st V.T. Typical case of field emission 4π/9 @29MV/m
280° Iris between cell #8 and #9 Making replica After manual grind, it disappeared! TTC Meeting

13 Case of MHI#14 4π/9 2nd V.T. T-mapping X-ray-mapping 34MV/m
TTC Meeting

14 Case of MHI#14 6π/9 2nd V.T. T-mapping X-ray-mapping 30MV/m
TTC Meeting

15 Case of MHI#11 Explosion occurred! After the 3rd V.T.,
we observed the problematic EBW bead at the connection between the end cell and the beam pipe. TTC Meeting

16 Case of MHI#15 1st V.T. 2nd V.T. Will be tested on this Thursday
22.5MV/m Cell #2 heating We expected any defect is found around heating location at Cell #2, because of the low quench field.  That was true! TTC Meeting

17 Case of MHI#15 Local grind Nothing was found! Disappeared! 62°
π, Local grind 5π/9, Nothing was found! Disappeared! This cavity will be tested on this Thursday. TTC Meeting

18 Case of MHI#10 5~9π/9 @20~21MV/m 4π/9 @24MV/m 3π/9 @41MV/m
323°(300μmx15μm) 310°(250μmx15μm) TTC Meeting

19 Achieved Gradient at STF
TTC Meeting

20 Final Q0-Eacc curve at STF
TTC Meeting

21 Summary MHI#12 and #13; Perfect cavities
MHI#10 and #15; Defect “just” on EBW bead MHI#11 and #14; Explosive event occurred due to problematic EBW bead (probably) MHI#16 and #17; Will be tested before summer MHI#18-#22; Will be tested after summer We are still studying the performance of 9cell cavity for ILC. TTC Meeting

22 Thank you for your attention!