Presentation is loading. Please wait.

Presentation is loading. Please wait.

TE-MSC activities in SPS during YETS

Similar presentations


Presentation on theme: "TE-MSC activities in SPS during YETS"— Presentation transcript:

1

2 TE-MSC activities in SPS during YETS 2017-2018
J. Bauche, on behalf of the TE-MSC team 8th November 2017

3 Outline Magnet test campaign at the start of YETS
Magnet patrol HV test of main magnets Planning of test period – week 50/2017 Magnet maintenance activities Magnet exchanges Standard maintenance LIU activities aC coating Other (co-)activities J. Bauche, TE-MSC, 08/11/2017

4 Inspection “Magnet Patrol” (IMPACT 102490)
Magnet test campaign Inspection “Magnet Patrol” (IMPACT ) To detect coil movements in main magnets and transfer line quadrupoles Removal of the magnet covers Audio-visual inspection in pulsed mode Machine conditions Machine closed to non-MNC personnel during tests (coord. with Carb Cavity) All technical services shall stay available and operational (Electrical network, main magnet converters, cooling, interlocks, access) Access system in «Magnet Patrol» mode Support from other groups BE/OP to power the magnets and lock the accesses All other teams ready to intervene in case of system/service failure (EPC, EL, MPE, ICS, CV, etc…) J. Bauche, TE-MSC, 08/11/2017

5 High voltage tests (+ delta I) (IMPACT 102490)
Magnet test campaign High voltage tests (+ delta I) (IMPACT ) To detect weaknesses in main magnet circuits insulation Main dipoles and quadrupoles (962 units) Busbars and water cooled cables are tested together with the magnets! Machine conditions Machine closed, in dedicated configuration (CIS system of EPC) Cooling circuits running Separation of power converters from load Test +/- 6kV on dipole and +/- 4 kV on quadrupole circuits, from BA3 In case of failure, localization in the machine, repair, and re-test Support from other groups TE/EPC for CIS configuration + HV test bench BE/OP for access control J. Bauche, TE-MSC, 08/11/2017

6 Magnet tests - week 50/2017 Planning
Monday 18/12: opening of all main magnet covers Consignation main magnet circuits at 07:45 Covers opening all day Tuesday 19/12: MAGNET PATROL Deconsignation main magnet circuits between 06:30 and 07:00 (according to Carb cavity works) Preparation of machine by BE/OP  07:00 to 08:30 Magnet patrol between 8:30 and 17:00 (hopefully…) Consignation main magnet circuits at the end of the patrol Wednesday 20/12: HV test + delta I test + TT quadrupole patrol Preparation of machine by BE/OP and TE/EPC (CIS configuration) HV test + delta I test  morning TT20 – TT40 – TT60 quadrupole patrol  afternoon Thursday 21/12: start of general access Earthing main magnet circuit at 07:45 Closing of magnet covers all day J. Bauche, TE-MSC, 08/11/2017

7 Preventive / corrective exchange of main magnets
Magnet system maintenance Preventive / corrective exchange of main magnets (IMPACT ) Expected around 10 main magnets to be replaced Based on inspection campaign results Aperture restrictions to be considered Machine conditions Free access to material lift and passage for transport equipment Support from other groups EN/HE, TE/VSC, EN/ACE/SU Inputs from BE/OP for aperture restrictions Planning to be discussed with coordination (BA3 lift revamping…) Main magnet replacement J. Bauche, TE-MSC, 08/11/2017

8 Magnet system maintenance
Magnet general maintenance (IMPACT )  Corrective/preventive maintenance Repair of magnets non-conformities in-situ Busbar system inspection Machine conditions Activities transparent for other teams Support from other groups None Activity distributed over the whole YETS, ending with the most radioactive zones Broken pole shim Water leak J. Bauche, TE-MSC, 08/11/2017

9 aC coating and Impedance Reduction (IMPACT to be issued by VSC)
LIU activities aC coating and Impedance Reduction (IMPACT to be issued by VSC) Magnets removal / reinstallation followed by MSC Details in TE-VSC presentation ( MBB 51470, and aC treated in-situ QF SSS 512 and 514, and QD SSS 515 will be dismantled and aC treated ex-situ QD will be aC treated ex-situ or replaced by pre-coated spare All removed magnets will be disconnected on 21/12/2017 Machine conditions Free access to material lift and passage for transport equipment Support from other groups EN/HE, TE/VSC, EN/ACE/SU Planning following VSC request and SPS coordination J. Bauche, TE-MSC, 08/11/2017

10 Other activities Prototype fire door installation around MBA.41570
MSC support will be provided if needed Installation of TPSWA (ZS diffuser) MSC support for SSS girder modification and MDVA.21604 Lift maintenance BA1and BA2 on 20th December Date foreseen not compatible with HV test (CIS configuration)  to be modified BA3 goods lift revamping from 16th January Impacts on possibility to transport magnets via BA3 for magnet replacement campaign  complete campaign in 6 days or transport via BA6 J. Bauche, TE-MSC, 08/11/2017

11 Many thanks in advance for your support to the TE-MSC activities!


Download ppt "TE-MSC activities in SPS during YETS"

Similar presentations


Ads by Google