Capital Improvement Program Annual Report – 2016/17

Similar presentations


Presentation on theme: "Capital Improvement Program Annual Report – 2016/17"— Presentation transcript:

1 Capital Improvement Program Annual Report – 2016/17
Joe Mouawad, P.E. October 5, 2017

2 2016-2021 Capital Improvement Program
Total budget of $461M with estimated external funding of $63M Water system investments average $49M/year over the five-year period TVRWRF Expansion at $99.2 M accounts for largest single project expenditure

3 2016-17 Capital Improvement Program Breakdown
1% 7% 65% 57%  PROJECT TYPE COUNT 2016 – 17 ($ Million) WATER 56 $49 M SEWER 22 $41 M RECYCLED 17 $17.5 M GENERAL 5 $1.5 M TOTAL 100 $109 M

4 2016-17 Capital Improvement Program Performance

5 2016-17 CIP Expenditures Top 5 Project Expenditures:
TVRWRF 23 MGD $29.9 Mil North Trumble Pond $ Mil Paradise Meadows Tank $3.4 Mil Sun City Lift Station $ Mil Redlands & Hemlock BS $2.6 Mil Total $43.2 Mil

6 FY 2016-17 Construction Projects Completed
Completion Date Contract Amount 1 AC/OMC Public Access Areas Renovation Jul-16 $1.9 M 2 Well 93 Equipping Aug-16 $1.9 M 3 TVRWRF Effluent P.S. Heat Exchanger Rep. Sep-16 $0.2 M 4 Palm Avenue Pipeline Replacement Oct-16 $0.8 M 5 MV/PV/SJV/SC RWRF's Solar Phase 2A Oct-16 $11.9 M 6 TVRWRF Solar Phase 2B Oct-16 $2.6 M 7 Wine Country PH I - Loma Ventoso Lift Station Nov-16 $2.4 M 8 7th Street Road Repair Jan-17 $0.5 M 9 AC/OMC Energy Mgmt System Replacement Feb-17 $0.4 M 10 Menifee/Perris I Desalter Noise Abatement Mar-17 $0.6 M 11 Perris II Desalter Transmission Pipelines Ph II May-17 $0.2 M 12 Nuevo Tank Structural Rehab May-17 $0.3 M 13 County Water Company Consolidation May-17 $1.6 M 14 Oliver Tank Interior Recoating Jun-17 $0.9 M 15 Redlands & Oleander Pipeline Replacement Jun-17 $1.9 M Total = $28.1 M

7 Impacts to CIP Expenditures
Funding Delays Alessandro Pond Optimization Cottonwood Recycled Water Pipeline La Piedra Recycled Water Pipeline Bid Protests Paradise Meadows Tank Construction Delays North Trumble Pond Redlands & Hemlock Booster Project Deferments Goetz Rd Tank Diaz Lift Station Favorable Bids

8 Recent Construction Bid Results
Project Bid Date Low Bid Engineers Difference Amount Estimate Audie Murphy Road Sewage LS Sept-16 $2,496,140 $2,800, % Winchester Pond Site Rec Well Ph1 Oct-16 $1,198,357 $785, % SJVRWRF Erosion Mitigation Oct-16 $763,000 $600, % "A" Street 24-Inch Water Pipeline Rel Nov-16 $373,333 $477, % Nuevo Tank Structural Rehab Nov-16 $296,100 $625, % Well 37 Drilling & Testing Nov-16 $1,145,659 $1,475, % La Piedra RWP and Freeway Crossing Nov-16 $1,540,885 $1,800, % Perris II Desalter Trans Pipelines Ph. 2B Dec-16 $252,217 $321, % Oliver Tank Interior Recoating Dec-16 $974,500 $1,155, % Morton Road LS Pump Replacement Jan-17 $371,410 $458, % Moreno Valley Sewer Improvement Jan-17 $1,833,900 $2,261, % Perris and Elder Booster Station Feb-17 $5,533,121 $5,628, % Quail Valley Subarea 9, Phase 1 Sewer Feb-17 $7,308,134 $6,414, % Daily Road Drainage and Hydro BS Feb-17 $721,500 $1,137, % Fleet Serv In-Ground Vehicle Lift Repl March-17 $184,300 $120, % Sanderson LS Pump Electrification Pro April-17 $437,600 $385, % Lakeview Effluent PL Cathodic Pro Rehab June-17 $69,977 $128, % Total = $25,500,133 $26,572, %

9 Water Supply Diversity and Reliability
Project Budget Status Cactus II Feeder $48 M Design Project Budget Status PWFP Membrane Replacement $8 M Construction Project Budget Status SJV Recharge & Recovery $22.9 M Design

10 Water Recycling Project Budget Status Purified Water Replenishment
Prelim Design Project Budget Status French Valley RW Pipeline $1.2 M Bid Project Budget Status Temecula Recycled Water Pipeline $15 M Design Project Budget Status TVRWRF 23 MGD Expansion $99.2 M Construction

11 Salinity Management Project Budget Status Brackish Well 94 $1.3 M
Construction Project Budget Status Perris II Desalter $31 M Design Project Budget Status Brackish Wells 95 & 96 $2.6 M Construction

12 Protection of Public and Environmental Health
Project Budget Status Quail Valley Sewer -Phase 1 $14.4 M Construction Project Budget Status OMC Laboratory Mods $3.4 M Design

13 Sound Planning and Appropriate Investment
Project Budget Status MARB Groundwater Recovery $55 M Planning Project Budget Status Solar Phase III $0.2 M Prelim Project Budget Status EM-11 Pipeline TBD Planning

14 Accomplishments Perris II Desalter Grant Funding and Local Resources Program Agreement MARB Groundwater Recovery Program Feasibility Study USACE Well 94 Grant Funding Well 59 U.S. Air Force Funding Agreement RWRF’s Disinfection System Conversion Design Recycled Water Accelerated Retrofit Program Audie Murphy Ranch Water And Sewer Facilities

15 Looking Forward: 2017/18 CIP PROJECT TYPE COUNT 2017-18 ($ Million)
WATER 51 $41.4 Mil SEWER 34 $57.9 Mil RECYCLED 15 $11.3 Mil GENERAL 3 $0.9 Mil TOTAL 103 $ Mil

16 Looking Forward: 2017/18 CIP Pursue Funding in Support of MARB Groundwater Recovery Program Coordination with MWD to Advance EM-25 Raw Water Pipeline and EM-11 Transmission Pipeline Planning Advance Construction of Quail Valley Subarea 9 Phase I Sewer Complete Perris II Desalter Design Complete Wells 95/96 Construction Initiate Reach 4 Recycled Water Booster Construction Advance Solar Phase III Recommendations Advance PWR Phase I Preliminary Design & Public Outreach Implement RWRF’s Disinfection System Conversion

17 Contact Information Joe Mouawad, P.E. Assistant General Manager Planning, Engineering, and Construction (951) Ext. 4463