Transmission and Distribution Loss Study

Similar presentations


Presentation on theme: "Transmission and Distribution Loss Study"— Presentation transcript:

1 Transmission and Distribution Loss Study
Virgin Islands Water and Power Authority June 2008

2 Purpose Quantify T&D facility losses using available tools
Provide a basis for recommendations to reduce T&D system losses Prioritize recommendations based on impact to T&D losses

3 Results of Loss Study - St. Thomas FY 2007

4 Results of Loss Study – St. Croix FY 2007

5 Results of Loss Study FY 2007 System Statistics Type STT STX
Cost of Power (1) ($/kWh) $0.164 $0.195 Annual Cost of Losses (2) ($/peak kW) $817.51 $1,032.71 Transmission (mi) 30 N/A Distribution (mi) 339 479 Number of Customers 32,369 25,839 System Peak (MW) 88.1 54.1 Notes: (1) Based on fuel costs for FY 2007, only (2) Calculated costs of losses based on cost of power for FY 2007.

6 Basis of Analysis & Assumptions
Engineering models of T&D system loads at FY 2007 peak FY 2007 system energy & peak demand, and financial statistics VIWAPA and industry standards Cost of losses based on FY 2007 fuel cost only Customer load based on transformer size Secondary lengths and types based on averages Load factors per customer class based on 2007 system load factor

7 Strategies to Reduce T&D Losses
Support, maintain, and upgrade engineering models Standardize distribution transformer sizing for more efficient use of capacity Increase maintenance practices Use economic analysis to select conductors for construction, upgrades, and conductor replacement program

8 Strategies to Reduce T&D Losses
Implement new DOE Transformer Efficiency Standards GPS inventory of system facilities Improve voltage regulation on T&D systems Add proposed substation for St. Croix Add line regulation as interim solution for proposed substation Accelerate tree trimming program Increase infrared camera inspections

9 Strategies to Reduce Other System Losses
Improve QA/QC of collected metering data Ensure billing processes are timely and accurate Implement Automated Meter Reading (AMR) system-wide Without AMR: Accelerate meter calibration program Continue focus on meter resealing and meter lock ring programs Reconcile unmetered lighting accounts Field verification of light operation


Download ppt "Transmission and Distribution Loss Study"