AARNA Progress Report-January 2017

Similar presentations


Presentation on theme: "AARNA Progress Report-January 2017"— Presentation transcript:

1 AARNA Progress Report-January 2017
MAHENDRA HOMES PVT LTD. AARNA Progress Report-January 2017

2 T1-T2 Block-B up to Terrace
Tower-1,2 Block-B T1-T2 Block-B up to Terrace

3 T1-Block-B above Terrace-LMR,OHT work in progress
Tower-1 Block-B T1-Block-B above Terrace-LMR,OHT work in progress

4 Club house ground floor pour-1 slab reinforcement work in progress
Tower-1,2 Block-A ,Block B Club house ground floor pour-1 slab reinforcement work in progress

5 Block Work in B1, Up to 7th floor
Tower-1 Block-B Block Work in B1, Up to 7th floor

6 Block Work in B2, Up to 8th floor
Tower-2 Block-B Block Work in B2, Up to 8th floor

7 Tower-1 Block A up to Sixth floor

8 Tower-2 Block A Footing work , back filling work in progress

9 TOWER -1&2 BLOCK- B OVER VIEW

10 TOWER -1&2 BLOCK- A ,BLOCK -B OVER VIEW

11 THANKING YOU