Presentation is loading. Please wait.

Presentation is loading. Please wait.

Facility Logistics Simulation at a Large Retailer

Similar presentations


Presentation on theme: "Facility Logistics Simulation at a Large Retailer"— Presentation transcript:

1 Facility Logistics Simulation at a Large Retailer
Scott J. Mason, Ph.D. Fluor Endowed Chair in Supply Chain Optimization and Logistics Professor of Industrial Engineering

2 k distribution centers
The Logistics Network Mode: LTL Modes: LTL or TL Modes: Intermodal and TL i suppliers j facilities k distribution centers Suppliers Consolidation Points Distribution Centers Simulating a single CP Scott J. Mason,

3 What is being modeled? A generic CP that includes the following aspects: Inbound (IB) less-than-truckload (LTL) arrival process Flexible assignment and dispatching of LTL shipments to dock doors Processing at the purchase order (PO) level Outbound (OB) truckload (TL) departure process Flexible assignment of outbound trucks to dock doors Flexible dispatching of cross-docked purchase orders to outbound trucks Resource Requirements Contention for dock doors, associates for loading/unloading, material handling equipment Purchase Order (PO) Modeling Origin and destination for each PO Weight and cube Scott J. Mason,

4 How can the simulation be used?
Tactical Analysis based on optimization To evaluate the effect of the new supplier/CP/DC product flow decisions on CP performance Can the CP handle the projected demand over the planning horizon? What should the size of the CP actually be? # dock doors, # associates, material handling equipment Operational Analysis The simulation can be used to evaluate operational changes within a CP New PO dispatching rules Inbound trailer door assignments Outbound trailer door assignments Scott J. Mason,

5 Unloading/loading efficiency
What is being measured? Utilization Resource utilization (doors, associates, material handling equipment) Space utilization (% of floor space utilized) PO processing # POs processed per week PO cycle time (time to be processed through CP) % of POs exceeding 48 cycle time threshold Unloading/loading efficiency Queuing times for POs Queuing times for inbound trucks % of outbound trucks leaving LTL Scott J. Mason,

6 Overview of Model Process
LTL trailers arrive and wait for a free dock door Dispatcher assigns LTL trailer to IB door Each shipment has a number of POs Each PO may be unloaded by either clamps, forklifts, slips, or carts Each PO has an origin, destination, weight, and cube Each PO is unloaded Either sent directly to OB trailer designated for destination for loading, or Waits within the CP’s bay until OB trailer is available for loading OB trailers wait until they meet their weight requirement or until 48 hour threshold is passed Scott J. Mason,

7 Demand: LTL Shipment Arrival Process
Assume 5 day operation (M-F) LTL shipments that arrive during the weekend are processed on Monday Weekend demand is added to Monday’s demand LTL truck arrival data was collected and retailer personnel gave input Number of trucks that arrive during each hour of the day is random and varies with the time of day Mean arrival rate as function of time Scott J. Mason,

8 CP 6901 LTL Arrival Model Daily LTL arrival pattern varies with the time of day. Weekend Model - summed 20 week aggregated weekend demand and divided by 20 to get 21.5 LTL arrivals per weekend, modeled with Poisson distribution Scott J. Mason,

9 LTL Shipment Origin Modeling
Randomly determine the supplier zip that sent the shipment according to a discrete probability distribution Where is the probability that the LTL came from origin zip and is the number of POs from origin zip processed through the CP Scott J. Mason,

10 CP 6901 Shipment Origin Model
Let be the number of POs from origin zip i processed through CP The probability that the LTL came from origin zip i is: Scott J. Mason,

11 LTL Shipment Purchase Order Model
Each LTL shipment contains a random number of POs to be processed. We assume that the number of POs on a shipment does not depend on the shipment origin or destination. We assume that the number of POs on a shipment is normally distributed with a mean and standard deviation and that there must be at least 1 PO per shipment. CP 6901 Mean = 8.4 Standard deviation = 5.1 Scott J. Mason,

12 Purchase Order Weight and Cube Model
Each PO has its own weight and cube May depend on supplier and destination (i.e., certain suppliers have heavier weights or larger cube products and certain destinations may tend to get heavier or larger products from certain suppliers) Results in highly significant data requirements and statistical analysis Simplifying Assumptions We assume that weight and cube depends only upon supplier We assume that the distribution of weight and cube is well modeled by a triangular distribution We assume that the Pareto Principle applies 20% of suppliers account for 80% of POs passing through the CP, resulting in the need for only distributions for 20% of the suppliers Combine other 80% of suppliers into group and use one distribution for the group Scott J. Mason,

13 CP 6901 PO Weight/Cube Models
Scott J. Mason,

14 CP 6901 PO Weight/Cube Models
Scott J. Mason,

15 CP Resource and Process Modeling
Model the processing within the CP at the PO level When a LTL shipment arrives the number of POs on the shipment is generated. Each PO is given a weight, cube, destination DC, and load type. After the LTL is assigned an unloading dock, the POs are unloaded when resources are available. Each PO is unloaded (individually) using an associate and the material handling equipment for its type of load (pallet, slip, or floor). Material handling equipment (forklifts, clamps, carts, and slips) are modeled as transporters that can move at a given velocity over a given distance. Scott J. Mason,

16 Resource and Process Modeling Data Requirements
Quantity Number Dock Doors 20 Number of Associates 6 Number of Fork Lifts 4 Number of Clamps Number of Carts 10 Length of CP (ft) 400 Width of CP (ft) 200 Load Type Discrete Distribution Pallet 0.4 Slip Floor 0.2 Transporter Type Cube (ft3) Lbs Forklift 70 3,000 Clamp Cart 192 500 Slip Transporter Minimum Mode Maximum Clamp 5 7 9 Cart 1 3 Fork Lift Scott J. Mason,

17 Unloading/Loading Process
The unloading and loading Process times were obtained through onsite time studies 10 observations per load and unload process per transporter type were averaged Type Minimum Mode Maximum Floor 52 208 375 Pallet 6 11 15 Slip 7 20 36 Type Minimum Mode Maximum Floor 40 192 310 Pallet 5 9 13 Slip 6 16 32 Scott J. Mason,

18 CP Physical Modeling Distances were calculated using rectilinear calculations from dock to dock door and the dock door to bay Scott J. Mason,

19 Example Distance Matrix
Scott J. Mason,

20 IB and OB Shipment Dispatching
Whenever a dock door is freed, we randomly determine whether it should be designated for IB or OB according to the distribution, 25% OB, 75% IB We know that the CP consolidation ratio is roughly 3:1 (3 LTLs for 1 TL); therefore, dock door usage is 25% for loading OB, 75% for unloading IB. IB shipments are assigned to a door based on a first come first served basis. OB trailers are assigned to a door based on discrete distribution PMF from destination distribution such that an assignment will be made to a door if one is not already been assigned IB/OB trailer to dock assignment This is an area of active research. Many companies are beginning to use optimal assignment strategies to improve cross-docking efficiency. Develop heuristic assignment rules based on optimization and expert dispatchers. Scott J. Mason,

21 PO Dispatching and Load Building
Logic used for load Building If IB arrives with OB destination truck ready, then IB will be unloaded and loaded onto OB truck If POs on Bay have an OB destination truck ready, then POs will be loaded onto OB truck If OB truck exceeds 48 hour threshold, then check POs in Bay, if none then immediately ship OB truck to destination else load then ship If OB truck is at capacity (cube/pound) then dispatch OB truck to destination Scott J. Mason,

22 Verification and Validation
Collected data from real system and compared real system to simulation output Optimization model showed an 84.03% CP dock door utilization Simulation showed an 82.90% dock door utilization! Retailer Actual Simulation Output Expected Number of POs 2057 2029 CP Consolidation Ratio (LTL to TL) 3 to 1 2.75 to 1 Maximum Time PO Spends at CP 48 + grace* 51.7 % of Late POs 5% 5.20% * grace time to load remaining POs in Bay Scott J. Mason,

23 Validation Example for a Single CP
Increased demand by 10% – 12% over ten years Door and Bay utilization increases as demand increases Scott J. Mason,

24 Validation Example for a Single CP (2)
As demand increases, PO time in Bay increases As demand increases, average OB trailer waiting time decreases Scott J. Mason,

25 Your Takeaway? The iterative use of optimization and simulation in practice can provide powerful insights into smarter, more effective decision making. However, there is a non-trivial amount of time and resources required to pull this off! This project was funded by the retailer over a 12 month period for $75,000 through the CELDi research center As a consultant myself, I can honestly say that no consultant could have done this any cheaper! Scott J. Mason,


Download ppt "Facility Logistics Simulation at a Large Retailer"

Similar presentations


Ads by Google