Presentation is loading. Please wait.

Presentation is loading. Please wait.

Braidwood Prototype Test

Similar presentations


Presentation on theme: "Braidwood Prototype Test"— Presentation transcript:

1 Braidwood Prototype Test
June, 2004 Braidwood Collaboration meeting, May 13, 2005. Surface Facility Rerquirements Definition of Scope; Discovery Definition of Methods Deliverables Project Definition Plan Establish Requirements Rough Cost & Schedule Value Engineering Phase Critical Review of CDR Expert Consultation Belding Walbridge Hilton Conceptual Design Report Reasonable Cost & Schedule Ray Stefanski Fermilab Braidwood Collaboration Meeting May 13, 2005

2 Braidwood Collaboration Meeting
Why Ray is Anal Compulsive?? What does it cost to build a magnetic horn? Ans: $~500K Larry might answer. This might show up in a proposal cost estimate. Better: Cost to install a horn into a beam is about $5 M. Contingency can’t cover this. Braidwood Collaboration Meeting May 13, 2005

3 “Baseline” Cost and Schedule Estimates
“Baseline” Cost Estimate: Civil Costs: (From Hilton and Assoc. consulting firm) Const.+EDIA $34M Contingency $8.5M Detector and Veto System (From Bartoszek Eng. and Argonne) Four Detectors $17M with Veto systems Contingency $5M Other with cont. $1M Schedule: 2004: R&D proposal submission. 2005: Full proposal submission 2007: Project approval; start const. 2009: Start data collection Please, these are not baseline numbers. Can we say that the costs are based on our current best working mode? A baseline is not required until we apply For CD1. We haven’t yet received CD0. There has been little value engineering applied to these cost estimates Likely cost savings in developing an integrated plan for shafts, detectors,and access. Results of bore holes and geology studies reduces the needed contingency Project also lends itself to operational phasing with near and far shafts and multiple detectors

4 Baseline, as a term used in Project management:
A baseline is an approved configuration item, e.g. a project plan that has been signed off for execution. Definition of the term baseline in DOE 4133. c. Baseline and Change Control Levels. The project baseline consists of cost, schedule, and scope as stated on the Project Data Sheet (PDS), the project baseline summary, or similar documents. A baseline range is established at CD-1, Approve Preliminary Baseline Range, for tracking purposes. A performance baseline, against which project performance will be measured, is established at CD-2, Approve Performance Baseline. (See Chapters 1 and 2 for more information on CDs.) Baseball: Changing the baseline Changes the game!

5 Joel Butler’s P5 Presentation
$60 M in labor!!

6 Dear Ray et al., After the discussion about moving costs versus building costs at the end of the phone conference last week, I checked with Vic about the context of the conclusion in the June detector design document.  Ray correctly pointed out that it says "...size limits transportation so that a majority of the construction have to occur on site which will require fixturing and added cost."  Vic tells me that this conclusion was based on transportation costs that were estimated from very rough estimates.  But these included both surface options and helicopter options.  These costs were considered large compared to the quotes for near and far detector buildings of $300K each.  They would not necessarily be large compared to $15M.  This issue is obviously separate from the issue of a crane, which was estimated at $1.4M in the June document and is presumably included in the $15M. Ray, if I remember correctly, you mentioned the minutes of some meeting where the $15M estimate was discussed.  Is that correct? Thanks Maury

7 Braidwood “Baseline” Current Working Model
Design Goals: Flexibility, Redundancy, and Cross Checks Four identical 65 ton detectors Outside Radius = 3.5 m Fid. Radius = 2.6 m Two zones (Inner: Gd Scint, Outer: Pure oil) Good access for calibrations Increased fiducial mass Redundant detectors at each site Cross checks and flexibility Moveable detectors Allows direct cross calibration at near site Flat overburden at 450 mwe depth Equivalent to 580 mwe mountain 5 Hz muon rate in 6.5 m radius Deep near detector allows access to unique additional physics (Janet’s talk) Optimized to use both rate and shape analysis Mitigate Correlated Background with extensive, active veto system Fast neutrons from muons 9Li and 8He produced from muon Braidwood Strategy: Identify and veto the few shower producing muons which produce the neutrons and spallation products Veto Detectors p n m 6 meters Shielding

8 Braidwood Reactor Experiment

9 Staging & Assembly Area
Braidwood Reactors Connecting rail Far Site Near Site

10 Detector Assembly Schedule
The bits & pieces: Oil, Gd, scintillator, storage & mixing tanks acrylic sphere, glue, curing methods steel tank (stainless?) detector base with Thompson bearings. PMTs, mounting fixtures, power supplies, readout cables DAQ Computing Facilities Assembly Sequence In parallel as much as possible. 1. Build lower portion of tank 2. Install PMTs in lower tank 3. Build upper section of tank 4. Build acrylic sphere 5. Place acrylic sphere into lower tank 6. Install PMTs in upper tank 7. Stick the upper tank onto the 8. In situ PMT tests 9. Fill detector with oil, etc. 10. Test PMTs again 11. Send detector to hole. Veto Counters ?? Unknown!!

11 Rough Sketch of Staging and Assembly Area
If we give up the ability to build detectors in parallel, we can reduce the size of the assembly building. PMT staging & test Acrylic Tank Assembly Outer Shell Assembly Area PMT Installation  Off to shaft Final Assembly Area Oil StorageArea Welding the tank together can be done outdoors on a hardstand.

12 Near Shaft Head House (area 1664 sf) $425/sf 708,838 Building Shell
The building shell cost is similar comparing Maury and FESS. FESS also assumes An emergency generator Humidity Control for the Cavern. (based on Numi/Minos experience.) Fire detection and Protection Near Shaft Head House (area 1664 sf) $425/sf 708,838 Building Shell 355,712 Mechanical 137,174 Fire Protection 36,648 Electrical 127,656 Fire Detection 51,648

13 We may need decommissioning costs in FESS estimates.
Surface costs may be duplicated in the FESS and Hilton estimates We may need decommissioning costs in FESS estimates. Site Preparation includes $1,400,000 in road upgrade that probably isn’t needed.

14 We’re entering a value engineering phase. We’ll eliminate the things
that are now obvious we don’t need. We’ll add in the stuff we have not yet considered. Belding Walbridge should clear up questions of conveyance. airlifts over-road transport from nearby facility onsite conveyance on a flatbed bad roads may need minimal upgrade to handle 150 T loads. 2. Eliminate double counting and disagreement between Hilton and FESS we need dimensions used by Hilton. elevator cabins may be too small. reconcile occupancy requirements 3. Add methodology for fabrication, assembly, and installation of veto counters. what will they look like.

15 RFP in draft form prepared for Belding Walbridge.
. There will be four detectors in total. Each detector: 1. will assembled at the surface, 2. must be movable, 3. will be calibrated at the near shaft location before deployment to the far shaft location, and 4. will be filled just once and always move fully filled with oil. The scope of work shall include the following: Brainstorming of initial schemes for the movement of the detectors in three distinct translations; horizontal movement along the surface from fabrication building to shafts (approx. 1,000 feet) and between each shaft (approx. 4,800 feet). b. Vertical movement of the detectors up and down the shaft (approx. 600 feet), c. Horizontal movement below grade (from 75 feet to 220 feet) at 90 degree angles. b. Feasibility analysis of the movement of a completed detector from ANL or FNAL to the Braidwood site. The analysis should consider possible means of moving including truck, barge or airlift. c. Analysis of expected g-loading during the moving process.

16 Engineering/R&D Proposal (Submitted to NSF and DOE)
What we may have left out: Tank vibration studies. Put a liquid filled tank on a truck and monitor signal output. Build a small proto-detector and test reconstruction algorithms. Requests funding to complete the design and engineering of the baseline project. Civil engineering design leading to RFP for a “Design and Build” Detector engineering leading to full “Design Report” Final development of stable Gd loaded scintillator Amount requested Civil Engineering $525k Detector Engineering $408k Liquid Scint. $28k Edu. and Outreach $78k Another way of looking at the costs: Project Management $257 K 2004 R&D Proposal $782 K EDIA, OH&P, Contingency $1,564K

17 Things to consider: Accelerator based experiments are very expensive. >$100M/yr Reactor experiments get the beam at no cost. Braidwood is a US program that will be the best experiment of its kind in the world. Summary: The detector design will not be complete until we have resolved the methods for their construction and installation. We need to model the entire sequence of events for building the detectors - from procurement to commissioning, in order to comfortably predict budget and schedule requirements. The veto counters are a concern, because they represent an unkown – they could have an unpredictable impact on our ability to build Braidwood.


Download ppt "Braidwood Prototype Test"

Similar presentations


Ads by Google