LIU – SPS Low level RF Updates and schedule G. Hagmann,

Similar presentations


Presentation on theme: "LIU – SPS Low level RF Updates and schedule G. Hagmann,"— Presentation transcript:

1

2 LIU – SPS Low level RF Updates and schedule G. Hagmann,

3 Overview SPS LLRF upgrade
uTCA VME/uTCA uTCA?

4 Cavity Controller – RF test stand
TWC 200MHz 3 section BAF3 uTCA platform

5 Cavity Controller – RF test stand
uTCA (Direct-sampling) Custom design (BE-CO, BE-RF) DS8VM1 (Desy/Struck) SIS8300-KU (Desy/Struck) 125MHz/250MHz

6 Cavity Controller(s) - uTCA
Item Qty Remarks Status uTCA.4.1 crate 4 (2 for RF) NAT NATIVE_R9 9U, 12 slots AMC Received Power module 6 (2 for RF) NAT-PM-AC600D 600W, 12V MCH 4 NAT-MCH-PHYS CPU NAT-MCH-RTM & CPU module Timing module carrier 4 1 NAMC-PMC NAMC-PMC-T261 (double width) AMC extender 2 NAMC-EXT-RTM-F-PS (uTCA.4) RTM extender NAMC-EXT-RTM-R (uTCA.4) AMC – SIS8300-KU 8AC, 2DC DAC & Interlock to zone3 White-rabbit option DRTM – DWC8VM1 ? RTM with down-converter, Vector modulator Under eval DRTM – DS8VM1 3 (R12) 1 (R11) RTM for direct-sampling, Vector modulator 1x (R11) Received 2 repaired! R12 Expected to be delivered week 38

7 Cavity Controller - RF test stand
Cavity combiner Prototype V1 under test (1x) Cables received for 1 cavity (time of flight compensation) 1 combiner per section => 3 needed for test stand V2 series (4x) will be launched by end of Sept. Will be ready for installation (1 cavity) by December 2017 Mechanical support to be designed (BE-RF-PM ?)

8 Cavity Controller - RF test stand
Cavity controller (uTCA) Hardware ready (uTCA: CPU, MCH, RTM (DS8VM1), AMC (SIS8300)) Europa crate Predriver: production launched RF calibration (filtering, attenuation, …): to be developed Firmware BE-CO will provide the infrastructure by end Sept (PCIe bridge, White-rabbit core, interfaces (SPI,…), DDR interface) BE-RF is developing the RF feedback (1-turn feedback, polar loop, demodulator, modulator, …) Software Driver: Encore for PCIe/PCI under dev. By BE-CO (by end 2017) FESA class (wait for Encore or use BE-CO internal library -UAL)

9 Original 2017 schedule for uTCA RF Test stand
uTCA crate received SIS8300 (AMC) received DS8VM1 (RTM) uTCA received BE-CO firmware (AMC) ready RF test stand Postponed to beginning 2018 Encore for PCIe/PCI (BE-CO) Dec 2017: uTCA platform go/no-go uTCA RF feedback in lab

10 SPS-LIU RF power (LS2) SPS-LIU Master plan
We are here Beam for physics Long Shutdown Commissioning Operation Technical Stop RF power upgrade (courtesy E. Montesinos) LLRF hardware commissioning Bit too short!