Presentation is loading. Please wait.

Presentation is loading. Please wait.

DOTmLPF-P Change Recommendations

Similar presentations


Presentation on theme: "DOTmLPF-P Change Recommendations"— Presentation transcript:

1 DOTmLPF-P Change Recommendations
CDR Rob “Rooster” Loughran 23 Jul 2014 1

2 Objectives Define Joint DCRs and their uses
Describe the Joint DCR generation and staffing process Review Joint DCR content and format requirements Describe the Joint DCR implementation process Provide best practices and common pitfalls for DCR drafting, staffing and implementation

3 DOTmLPF-P Change Recommendations
Joint DCRs document and validate non-materiel solutions as an alternative to, or complement of, materiel solutions (JCIDS Manual, 19Jan12) Required when: A non-materiel solution addresses a capability gap A materiel solution requires changes that impact DOTmLPF-P areas outside of the materiel program A material solution exists in the joint force, but must be organic to the sponsor (i.e. cannot be satisfied by an RFF or RFC) ICD DCR CBA, Studies, Lessons Learned, JROC, JIEDDO, etc… DCR

4 Staffing a DCR Gatekeeper will identify the appropriate FCB (and supporting FCB if necessary) (JCIDS Manual, 19Jan12) One of 4 JSDs will be assigned (change pending in JCIDS manual rewrite) JROC Interest JCB Interest Joint Integration Joint Information

5 Basic Parameters and Format
Maximum Length: 30 Pages, including Appendix A (NR-KPP) Structure Executive Summary: 1 Page (1) Purpose (2) Background (3) Description (4) Analysis Process (5) Joint DCR Findings and Proposed Implementation Plan Recommendation OPR Implementation Timeframe ROM Cost (6) Constraints (7) Policy (8) Issues (9) Recommendation Summary Appendices

6 Basic Parameters and Format
Maximum Length: 30 Pages, including Appendix A (NR-KPP) Structure Executive Summary: 1 Page (1) Purpose (2) Background (3) Description (4) Analysis Process (5) Joint DCR Findings and Proposed Implementation Plan Recommendation OPR Implementation Timeframe ROM Cost (6) Constraints (7) Policy (8) Issues (9) Recommendation Summary Appendices The critical section of a DCR

7 Approved Alternate DCR Format
Provides more logical flow with reduced redundancies Operational Context. Includes former Purpose, Background, part of Description, and part of Appendix A (Architecture Data) Threat Summary. Includes part of Description for the threat environment information and some clarifying verbiage from CJCSI (Intel Certification) Capability Discussion. Includes part of Description and all of Analysis Process Change Recommendations and Implementation Plans. Includes Joint DCR Findings and Proposed Implementation Plans, Constraints, Policy, Issues, part of Recommendations Summary related to recommendations and implementation, and part of Appendix A (Architecture Data) Alternatives. Includes part of Recommendations Summary related to alternative approaches and options More information available at:

8 Approved Alternate DCR Format
Provides more logical flow with reduced redundancies Operational Context. Includes former Purpose, Background, part of Description, and part of Appendix A (Architecture Data) Threat Summary. Includes part of Description for the threat environment information and some clarifying verbiage from CJCSI (Intel Certification) Capability Discussion. Includes part of Description and all of Analysis Process Change Recommendations and Implementation Plans. Includes Joint DCR Findings and Proposed Implementation Plans, Constraints, Policy, Issues, part of Recommendations Summary related to recommendations and implementation, and part of Appendix A (Architecture Data) Alternatives. Includes part of Recommendations Summary related to alternative approaches and options More information available at: The critical section of a DCR

9 Section 5, Joint DCR Findings and Proposed Implementation Plan
What makes a good DCR? Format and length conforms to JCIDS manual Recommendations: Discrete, actionable tasks Examples Stronger: “Update Joint Pub 3-03 to reflect…” Weaker: “Update joint doctrine to reflect…” OPR Specific organization with oversight or authority over assigned task Stronger: “STRATCOM J7” Weaker: “Combatant Commands” Implementation Timeframe Specific, realistic yet minimized to maintain momentum Stronger: “30 September 2013” Weaker: “FY2013 plus 60 months” ROM Cost Realistic, conservative Myth: DCRs don’t have a cost Section 5, Joint DCR Findings and Proposed Implementation Plan

10 Implementation of Validated DCRs
Approved recommendations from DCR Section 5 become JROC Memo (JROCM) actions Overall lead designated in JROCM; responsible for leading completion of actions with OPRs Functional Capabilities Boards (FCBs) provide oversight of execution Extensions for action deadlines approved by Joint Staff J8 Deputy Director for Requirements via JROCM

11 Why DCRs Fail in Implementation
Common Implementation Failures: OPRs fail to meet suspense dates Actions reported complete, yet intent is not met Causes: Failure to properly review draft DCRs Arbitrary or unrealistic action suspense dates “Lead Organization” fails to lead Recommendations: Sponsor is the Lead Organization POCs for OPRs identified prior to validation and engaged in drafting process Determine suspense dates by developing a POAM for each action Lead Organization forms an implementation working group upon validation Leverage all available resources to complete actions within suspense dates

12 DCR Help Joint Staff J8 Joint Capabilities Division: JCIDS Process Owners JCIDS Gatekeeper: CDR J.R. Hill, , DCR Lead: CDR Rob “Rooster Loughran, , Functional Process Owners (FPOs): Provide advice to sponsors during staffing of DCRs; oversee implementation of recommended changes DOTmLPF-P Area Functional Process Owner POC Joint Doctrine Joint Staff/J-7 CDR Todd Glasser, , Joint Organizations Joint Staff/J-8 TBD Joint Training Mr. Mitchell Johnson, , Joint Materiel Mr. Fred Gregory, , Joint Leadership and Education Mr. Jack Roesner, , Joint Personnel Joint Staff/J-1 Joint Facilities Joint Staff/J-4 CDR Brett Blanton, , Joint Policy Joint Staff/J-5 Mr. Jim Raycraft, , Functional Capabilities Boards FCB POC Battlespace Awareness Mr. Chris Hall, , C4/Cyber Ms. Becky Gentry, , Force Application Mr. Ben Vaught, , Force Support Mr. Joe Coleman, , Logistics Mr. Rick Gallagher, , Protection Mr. Mike Shalak, , KM/DS Help Desk: Mr. Mike Farmer, ,

13 Summary Joint DCRs document and validate non-materiel solutions as an alternative to, or complement of, materiel solutions Joint DCRs follow the standard JCIDS process for staffing (~83 days) 9 Sections (5 Sections for Alternate Format) Maximum 30 pages plus 1 page Executive Summary Critical Section: “Joint DCR Findings and Proposed Implementation Plan” Lead Organization coordinates implementation of validated Joint DCRs with FCB oversight Successful implementation is dependent on comprehensive staffing and a pro-active Lead Organization


Download ppt "DOTmLPF-P Change Recommendations"

Similar presentations


Ads by Google