1 Information about the resort recreation area "Kenderli"

2 Geographical location of Kenderli
The resort area is located in the Kenderli area in the Kazakh Gulf, located 70 km south of the city of Zhanaozen and 2 km from the existing recreation center Kenderli. There are: 1) Kendery Holiday Village Occupies an area of 7.5 hectares, a one-time capacity people; 2) Children's health camp "Aөbөbek" - occupies the territory 9 hectares, one-time capacity people; 3) Medical Rehabilitation Center "Medicker".

3 Existing tourist infrastructure
The nearest airport to Kenderli is located in Aktau, at a distance of 210 km; Currently, there is an asphalt road between Aktau and Kenderli, which stretches for 60 km to the south towards Turkmenbashi (the border with Turkmenistan); Access to Kenderli by rail does not exist. The power supply is provided from the existing substation of 110/6 kV Substation "Fetisovo" (actual load 56A), which is powered from 110 kV L-Fetisovo-2 HV-line by AC-95 with a length of 1x64.5 km. The line was built in 1990 on reinforced concrete pillars of the type UB-110-1, with insulators of the brand PSG-70, the number of supports is 316 pcs. The permissible current load of AC-95 wire at 40 C ambient 300A. Gas supply - along the highway Aktau-Turkmenbashi is laid gas pipeline "Okarem-Beyneu." According to the UEHKH, the construction of the gas pipeline and automated gas distribution system from the Okarem-Beyneu gas pipeline is being completed as part of the construction of the external infrastructure of the resort recreation area Kenderli. Water supply and water disposal - in the recreation area Kenderli there are CBS capacity of 120 m3 / day. Also there are two potable water tanks with a volume of 1000 m3, water treatment filters - 2 pcs. with a capacity of 25 m3 / h.

4 2. Decision of the Karakiyan regional maslikhat
1. Resolution of the akimat of the region from № 28 "On approval of the master plan for the creation and development of the tourist cluster in the Mangistau region". 2. Decision of the Karakiyan regional maslikhat Of December 21, 2010 № 32/229 "On the General Plan of the International Recreation Area" Kenderli “ 3. According to the information provided by the Akimat of the Karakiyansky district, 1700 hectares are in state ownership. NORMATIVE AND LEGAL DOCUMENTS FOR THE DEVELOPMENT OF THE KENDERLI RECREATION AREA

5 According to the General Plan, the resort area of Kenderli is based on the following project:
The total area of the project is hectares; There are 23 hotels with a capacity of beds. 500 houses and luxury villas in private property; More than 500 hectares are allocated exclusively for green areas and parks; Institutions and enterprises for service of the recreation area;

6 Individual exclusive villas in Kenderli Bay;
The Kenderli project includes: Construction of a new resort recreation area in the northern part of Kenderli Bay; Construction of a desalination plant, a wastewater treatment plant and a greenhouse (not far from the resort) - The desalination plant will be located 4 km north of the Kenderli resort recreation area and should also serve the future "Kenderley town". The productivity is 40,000 m3 per day. Construction of a new international airport 20 km east of the new Kenderli resort - "Kenderli Resort International Airport". Capacity up to 1 million passengers per year; Construction of sewage treatment plant with a production capacity of about 26,000 m3 per day, an additional facility for processing waste is also proposed; Construction of a new city, mainly for workers of the future resort and their families - a new city "Kenderli"; Individual exclusive villas in Kenderli Bay; Laying a railway line along the route "Aktau - Kuryk - Kenderli“ for a tourist train with panoramic windows along the coast of the Caspian Sea.

7 9 feasibility studies for the construction of external engineering networks of the client Kenderli were developed: 1) The construction of a sewage treatment plant at 26,000 m3 per day In resort area Kenderli; 2) Construction of sewage treatment facilities for the international airport of Kenderli; 3) Construction of water supply at Kanderli International Airport; 4) Construction of a high-pressure gas pipeline from AGDS to Kanderli International Airport; 5) Construction of a gas pipeline and AGDS from the Okkarem-Beyneu gas main; 6) Construction of a new 110 / 10kV substation with two 40MVA power transformers, 110 kV outdoor switchgear according to 110-4N scheme, reconstruction of the existing 110 kV L-Fetisovo overhead line with complete replacement of wires with partial replacement of supports and construction of a second power transmission line with 110 kV voltage from Substation " Uzen-220 " 7) Construction of substation PS 110/10 for Kenderli airport; 8) Construction of a highway to the resort area of Kenderli; 9) Construction of a highway to the international airport of Kenderli.

8 Design and estimate documentation (DED) with a positive conclusion for 6 sites:
Construction of a new 110 / 10kV substation with two 40MVA power transformers, 110 kV outdoor switchgear according to 110-4N scheme, reconstruction of the existing 110 kV L-Fetisovo overhead line with complete replacement of wires with partial replacement of supports and construction of a second power transmission line with 110 kV voltage from Substation " Uzen-220 “; (Estimated cost - 2,361 million tenge. Conclusion of the GE No / 13 of ) 2. Construction of the highway of the resort recreation zone "Kenderli" with a length of km (Estimated cost million tenge. Conclusion of the GE No / 12 of ) 3. Construction of substation PS 110/10 for Kenderli airport . (Estimated cost million tenge Conclusion of the GE No / 12 of December 23, 2012) 4. Construction of a high-pressure gas pipeline from AGDS to Kanderli International Airport (The estimated cost is 289 million tenge Conclusion of the GE № / 12 of December 24, 2012) 5. Construction of a gas pipeline and AGDS from the Okkarem-Beyneu gas main (Estimated cost-1106 million tenge. Conclusion of the GE № / 12 of ). 6. Construction of sewage treatment facilities for the international airport of Kenderli (The estimated cost is 754 million tenge Conclusion of the GE No / 12 of December 24, 2012)

9 For the following 3 objects the situation is as follows:
1 According to construction of water supply at the international airport "Kenderli" - does not correspond to the estimated costs: under the DED million tenge, feasibility study million tenge. The adjustment of the feasibility study was completed and commissioned for state expertise. 2 The construction of a sewage treatment plant at 26,000 m3 of the international resort recreation area Kendirli - does not comply with the estimated costs: for DED-4,687 million tenge, feasibility study million. 3 The construction of the motorway at the international airport "Kenderli" with the length of does not correspond to the estimated costs: according to the DED million tenge, feasibility study million tenge.

10 Memorandum on the implementation of the System Plan for the development of the recreation area "Kenderli" Akimat of Mangistau region Provides development of design estimates for the construction of external engineering infrastructure of the Kenderli resort area; Conducts work on development of the engineering and transport infrastructure of the region; Takes measures to allocate land for the construction of the resort; Ministry of Investment and Development of the Republic of Kazakhstan Ensures the development and further implementation of the Systemic Development Plan for the Kenderli Resort Area; Conducts work on attracting potential investors for the implementation of the project.

11 Proposal for engineering infrastructure
1).Take appropriate measures to adjust the General Plan of the Kenderli resort area; 2) Under the project of the international airport "Kenderli", a feasibility study was developed and approved. There is no DED. The decision is to submit a budget request for the allocation of funds for the development of DEDof the international airport of Kenderli. 3). Submit a budget request for the allocation of funds for the construction of the following facilities having a positive state expertise with the beginning of construction in 2015: a) Construction of a new 110 / 10kV substation with two 40MVA power transformers, 110 kV outdoor switchgear according to 110-4N scheme, reconstruction of the existing 110 kV L-Fetisovo overhead line with complete replacement of wires with partial replacement of supports and construction of a second power transmission line with 110 kV voltage from Substation " Uzen-220 “ b) Construction of a highway to the resort area of Kenderli; c) Construction of substation PS 110/10 for Kenderli airport; d) Construction of sewage treatment facilities for the international airport of Kenderli; 4). Ensure that the feasibility study and DED of the sewage treatment plant is accelerated at 26,000 m3 of the Kenderli resort area.

12 Thank you for your attention!!!