Download presentation
Presentation is loading. Please wait.
1
A Presentation on Grid Management
Presented By: Er.Suneel Grover Dated : 22nd February, Power Controller, HPSEB
2
Grid Management Definitions as per the Electricity Act-2003
(2)“Electricity System” means a system under the control of a generating company or licensee, as the case may be having one or more… generating stations; or transmission lines; or electric lines and sub stations and when used in the context of the State or Union, the entire electricity system within the territories thereof;
3
Grid Management Definitions as per the Electricity Act-2003
(50)“Power System” means all aspects of generation, transmission, distribution and supply of electricity & includes one or more of the following namely; generating stations; transmission or main transmission lines; sub-stations; tie-lines; load dispatch activities; mains or distribution mains; electric supply lines; overhead lines; service lines; works;
4
Grid Management Definitions as per the Electricity Act-2003
“Grid” means the high voltage backbone system of interconnected transmission lines, sub-station and generating plants. “Grid Code” means a Grid Code specified by the Central Commission, under clause (h) of sub-section 1 of Section 79 Sub-section 1 of Section 79 “Extracts” 1 (h) to specify Grid Code having regard to Grid standards. (i) to specify and enforce the standards with reference to quality, continuity & reliability of service by licensee.
5
Grid Management Definitions as per the Electricity Act-2003
“Grid Standards” means the Grid Standards specified under Clause (d) of Section 73 by the Authority; Section 73(d) (d) specify the Grid Standards for operation and maintenance of transmission line.
6
Grid Management Definitions as per the Electricity Act-2003
(65) “State Grid Code” means the State Grid Code specified under clause (h) of sub-section (1) of section86;
7
Grid Management Definitions as per the Electricity Act-2003
Clause 86 sub-section 1 (1)(h) specify State Grid Code consistent with Grid Code specified under clause (h) of sub-section 1 of section 79.
8
Grid Management Definitions as per the Electricity Act-2003
“sub-station” means a station for transforming or converting electricity for the transmission or distribution thereof and includes transformers, converters, switchgears, capacitors, synchronous condensers, structures, cable and other appurtenant equipment and any buildings used for that purpose and the site thereof;
9
Grid Management Definitions as per the Electricity Act-2003
“transmission lines” means all high pressure cables and overhead lines (not being an essential part of the distribution system of a licensee) transmitting electricity from a generating station to another generating station or a sub-station, together with any step-up and step-down transformers, switch-gear and other works necessary to and used for the control of such cables or overhead lines, and such buildings or part thereof as may be required to accommodate such transformers, switch-gear and other works.
10
Electricity - A scientific phenomenon
EMF travels at the speed of light Available ‘just-in-time’ Delivered to the customers fresh No one get placed on hold Impartial in its benevolence and wrath Good servant but a ruthless master Grid operation is a continuous interplay of technical phenomena and natural/ human intervention
11
Power flow characteristics
Is directional Does not recognize geographical boundaries, asset ownership Does not check the map to determine the shortest route Flows are dictated purely by Impedances of the transmission lines Point of injection by generators Point of consumption loads “Time & Location matter is fundamental to operation” -Shmuel Oren & Fernando Alvarado
12
Capability of a chain of parallel and series elements would depend on the weakest link in a series
Anchoring at intermediate points and their strength would affect the strength of the whole chain. Power system is also a chain of series and parallel elements with added complexity that strength of various links change dynamically and depend on each other also.
13
Reliability Is a general term encompassing all the measures of the ability of the system generally given as numerical indices to deliver electricity to all points of utilization within acceptable standards and in the amounts desired CIGRE Comprises of “Adequacy” and “Security”
14
Reliability Security Adequacy
Power system ability to withstand sudden disturbances. {system shall remain stable and integrated} Adequacy Capability of the power system to supply the load in all the steady states in which the power system exists considering standard conditions. Generation Transmission Source: CIGRE Reports on Power System Reliability Analysis (1987, 1992)
15
Security
16
Hierarchical Power System Security analysis
17
Stability Angle Stability
ability of interconnected synchronous machines of power system to remain in synchronism under normal operating conditions and after subjected to a disturbance Small signal, Transient, Mid term, long term Voltage Stability ability of a power system to maintain steady acceptable voltages at all buses in the system under normal operating conditions and after subjected to a disturbance
18
Which one is a stable system?
19
Power System in India Electricity is a concurrent subject
Both State and Central Govt. responsible for development & management of this sector State Electricity Boards (SEBs)/STU responsible for development of intra-state transmission system POWERGRID – the Central Transmission Utility for development of inter-state & inter-regional system Power distribution responsibility is with State Govt. and Private owned utilities 3 levels for Grid management system namely State, Regional & National
20
Hierarchy of Indian Power System
21
NATIONAL POWER SCENARIO Installed Capacity in 1947
NATIONAL POWER SCENARIO Installed Capacity in ,300 MW Installed Capacity as on ,35,000MW Demand Estimates (FY2012) 16th EPS* Energy Demand (Billion Units) 750 Peak Demand 155,000 Installed Capacity required to 195,000 meet peak demand (MW) Additional Capacity Required (MW) 71,000 Present Energy Shortage 8.2% Peak Demand Shortfall 13% * Energy Survey by GOI
22
Present Power Scenario
All figs. in GW Installed Capacity (IC)– 135 GW IC-36.6 PD- 32.3 IC-2.5 PD- 1.6 Peak Demand (PD)– 107 GW IC-40.5 PD-36.4 IC-17.6 PD- 11.1 Growth rate – 8-9% per annum IC-38.2 PD- 25.7
23
Transmission Network Synchronous Grid interconnecting four(4) regions of 90 GW capacity geographically spread over 2.6 million sq. kms. South(SR) is asynchronously connected Transmission Grid$ (as on 30th September 2007) 765 kV / 400 kV Lines ckt. km 220 kV Lines – ckt. km HVDC Bipole (3 nos.) ckt. Km, 5 GW HVDC back-to-back - 7 nos., 3 GW FSC – 18 nos.; TCSC – 6 nos. Inter-regional capacity – More than 16 GW $source: CEA, India
24
Development of Electric Grid
National Regional State Local 1950’s 1960’s 1970’s 1990’s
25
Energy Resources Geographically spread unevenly dispersed pocketed energy resources Hydro in NER & NR Coal in ER Integration of energy resources through high capacity National Grid with a motto - ONE NATION- ONE GRID
26
Installed Capacity & Inter Regional links
MW Capacity NER-ER 1,850 ER-NR 2,500 ER-SR 1,200 ER-WR 1,650 SR-WR WR-NR 900 Talcher Kolar HVDC Bipole 2,000
27
Synchronous Operation of ER & NER
28
Synchronous Operation of ER + NER & WR
29
Synchronous Operation of ER + NER + WR & NR
30
National Grid - Present
Inter-regional capacity : 16.2 GW National Grid - Present
31
Geographical Map Geographical Map
32
Zones and Flowgates in Northern Grid
34
HPSEB-Taking Power to people
Existing Power System Installed Capacity 460 MW Villages Electrified Nos Hamlets Electrified Consumer Connected Lacs Connected Load KW
35
HPSEB-Taking Power to people
Existing Power System EHV Station 35Nos. Distribution Sub Stns Nos. H.T.Lines Kms L.T.Lines Kms A State Load Dispatch Centre with Latest State of Art has been established to have online control and transaction of Electricity Minimum fatal/non-fatal accidents Minimum Transformer failure
45
Role of NRLDC/SLDC’s Established state of the art Northern Region Load Dispatch Centre and State Load Dispatch centers to effectively manage the Northern Grid. National Load Despatch Centre shall be commissioned shortly Implemented Open Access in non-discriminatory and transparent manner Maintaining system availability above 99%, that too with limited redundancy
46
Role of Himachal Pradesh State Load Dispatch Centre
Himachal Pradesh State Load Dispatch Center is ensuring integrated operation of the power system of the HP State with the Northern Region Load Dispatch Center of India. The main responsibilities of HPSLDC are: Management, Monitoring & Control of power system parameters and security etc. To ensure the integrated operation of the power system of HP State Grid with Northern/NEW Grid. System studies, planning and contingency analysis. Analysis of tripping/disturbances and facilitating immediate remedial measures. Issuance of Day Ahead Schedules/Dispatches w.r.t demand of loads, generations etc. and operational planning/control. Facilitating bilateral exchanges. Computation of energy dispatch and drawal values using SEMs. Augmentation of telemetry, computing and communication facilities.
47
Critical Grid Incident
– An Example 27th January, 2007
48
Critical Corridor In Northern Region Central UP to western part is a critical corridor having the following lines: HVDC Rihand-Dadri Pole-I HVDC Rihand-Dadri Pole-II 400 kV Kanpur-Agra 400 kV Kanpur-Ballabgarh 400 kV Kanpur-Auraiya D/C 400 kV Allahabad-Mainpuri-Ballabgarh-I 400 kV Allahabad-Mainpuri-Ballabgarh-II 400 kV Lucknow-Moradabad 400 kV Panki-Muradnagar 400 kV Unnao-Agra 400 kV Unnao-Bareilly-I 400 kV Unnao-Bareilly-II 220 kV Kanpur/Panki-Mainpuri D/C Probability of all lines available is only 72.3% going by the target availability as per CERC (95% for HVDC and 98% for AC lines)
49
Fog on 27th January 2007
50
Incident on 27th January 2007 Heavy Fog in North West India (rail, road, air traffic) Tripping/Auto Reclosure started from 0300 Hrs. Maximum impact in Delhi, Western UP and Haryana areas. Most critical period between 0745 Hrs to 1130 Hrs. Max 53 (400 & 220kV) lines were out at 0812 Hrs. Western UP/Uttaranchal (approx 1200 MW load) area was being fed through 400 kV Agra-Muradnagar and 400 kV Lucknow- Moradabad lines only for more than 2 hours.
51
The five hour ‘test of nerves’
Time of incident: 0600 hrs to 1100 hrs Information overload 3300 Alarms : 11/Minute 1200 Sequence of Events : 4/Minute Situational awareness challenge 17 number of corridors affected 32 no. of lines out of 81 lines in these corridors affected Total 82 no. of Auto-Reclosures on 17 lines 400 kV Bus-II lost at Dadri at 08:12:22 hrs 220 kV bus-II lost at Auraiya at 08:46:11 hrs 220 kV Bus fault at Panipat (BBMB) at 09:00:51 hrs 8 no. of 400 kV & 16 no. of 220 kV lines declared under breakdown Auraiya 2 GTs and 1 STs & Panipat(Th) # 1, 2, 3 & 4 tripped Backing down of generation at Singrauli, Rihand-1 & Rihand-2 Curtailment of Inter-Regional STOA transactions
52
Flow gates & Zones affected
17 of 37 axes were affected. System separation possible on any of the three axis. 2(2)/6 3(4)/7 1(1)/4 1(1)/9 2(4)/2 1(1)/2 1(5)/13 2(2)/2 1(1)/1 2(9)/5 4(17)/6 1(4)/5 2(21) /2 1(2)/1 2(4)/2 2(30) /2 4(6)/12
53
December-2007 FOG RELATED TRIPPINGS OCCURRED
ON 1st, 13th , 14th & 25th December2007 Humidity more than 85% On 1st /14th and 25th December 2007
54
January 2008 FOG RELATED TRIPPINGS OCCURRED ON 7th , 8th & 19th January 2008 Humidity more than 85% On 7th /8th and 19th January 2008 On 24th January FOG trippings occurred in Central & Eastern UP
55
Fog Related incident on 4th /5th Feb 2008 in Northern Region
56
Fog Related incident on 4th /5th Feb 2008 in Northern Region
First line tripped at 20:49 hrs/ 04 Feb- 2008 63x400 kV lines and 54x220 kV lines tripped 15x400 kV Substations and 9x220 kV Substations dead. NR System separated into two parts at 0437 hrs. Islanded system comprised of Punjab -Chandigarh -North Haryana -HP-Jammu & Kashmir –BBMB Island size about 5500 MW Rest of NR(Delhi/UP/Uttarakhand/Rajasthan) remained connected with “NEW” Grid.
57
Fog Related incident on 4th /5th Feb 2008 in Northern Region
At 07:45 hrs, 400 kV Dadri remained connected with rest of the grid only via 400 kV Dadri-Maharanibagh-Ballabhgarh line Tripping of 400 kV Dadri-Maharanibagh-Ballabhgarh would have led to islanded operation of Dadri (T) & Dadri (G) Islanded operation continued for 4 hour 19 minutes
58
Fog Related incident on 4th /5th Feb 2008 in Northern Region
Load shedding of around 5000 MW to avert cascade failure and survival of island Generation affected at Panipat (T )(unit 3 & 8) –110 MW x1+1x250MW=360 MW 2600 SOEs received from 00 hrs to 0900 hrs of 5th Feb 2008 121 number of switching instructions issued by NRLDC 83 instructions for closing of lines
60
Fog Related incident on 4th /5th Feb 2008 in Northern Region
5000 MW
61
ACTION TAKEN Total 1500 MW of Generation Backed down at
Singrauli,Rihand,Unchahar,Dadri(G),Auriya Additional support of MW taken from BBMB for more than 10 hours Inter-Regional STOA curtailed Power exported to Central grid to the tune of 700 MW against a normal import of 1270 MW( swing of 1970 MW)
62
Generation Backdown ISGS From To Generation Reduction Singrauli 1529
1270 259 Rihand 1753 1231 522 Unchahar-I 400 267 133 Unchahar-II 408 300 108 Dadri(G) 700 Anta(G) 485 344 141 Auraiya(G) 351 246 105 Total 5626 4058 1568
63
IMPORT/EXPORT IMPORT OF 2500 MW 1270 MW EXPORT OF 780 MW
64
BBMB GENERATION ACTUAL SCHEDULE
66
Fog Related incident on 4th /5th Feb 2008 in Northern Region
Island kept ready for synchronisation at two places viz. Bassi end on 400 kV Bassi-Hissar and Hissar end on 400 kV Hissar-Bawana but finally synchronised at hours at Hissar .
67
Highlights/Issues-Fog related Trippings
Behaviour of autoreclosure feature System separation alerts issued continuously since 02:30 hours and BBMB/Punjab/Haryana/J&K/HP SLDCs alerted on 5th Dec-08 morning Loss of 220 kV Panipat(BBMB) bus at 02:30 hours while carrying out switching operations to isolate the stuck breaker of 220 kV Panipat-Ch.Dadri line………..islanding of Panipat unit-3 & its tripping.
68
Highlights/Issues-Fog related Trippings
1x250 MVA, 400/220 kV ICT at Dehar providing the synchronous interconnection for nearly 40 minutes. Attempts to maintain connectivity on 220 kV Panipat-Narela D/C Survival of Island after separation possible only as it was surplus by 250 MW at the time of separation Absence of free governor operation in the Island
69
Highlights/Issues-Fog related Trippings
UFR operation in Island at 04:49 Hours Relative Humidity not dropping…..conscious decision to synchronize only afer hours Response from SLDCs/Substations during crisis Outage of 400 kV Muradnagar(UPPCL) for more than 4 hours No communication to substation either through SLDC or directly from NRLDC Overdrawal by Rajasthan Data related issues raised by DTL Loading of 400 kV Dadri-Malerkotla (PSEB STATE SHD ACT (OPN)
70
Highlights/Issues arising out of FOG related tripping 5th/6th Feb-08
Fault leading to isolation of 400 kV Bawana at 01:50 hours Load remaining connected at Bamnauli…..
71
The Road Ahead…
72
75
73
Future Demand-Capacity Projection
Source: Integrated Energy Policy, Govt. of India
74
Perspective National Grid
1200kV UHVAC / 800kV HVDC – Super Grid 765kV EHVAC and 500kV HVDC - Support Tr. Network 400kV AC System - Sub-transmission Network POWERGRID, INDIA 77 77
75
National Grid by 2012 Inter-regional capacity : 37.7 GW
POWERGRID, INDIA
76
Grid operation - A collective responsibility
Transmission is an indivisible shared facility (public service) “Failures in one location can propagate through the network”- Thomas Overbye “Power markets are the only markets that can suffer a catastrophic instability that develops in less than a second… The extent and speed of the required coordination are unparalleled”-Steven Stoft
77
Grid Management outlook
Need for infusion of Intelligence in the Grid for Growing demand for digital quality power Increasing number of interconnections Economic dispatch Features of Intelligent Grid Phasor measurements for Wide Area Monitoring Adaptive islanding Self-healing Establishment of Power Exchange
78
CONCLUSION Grid Management – The Need
We need a a smarter Electrical Grid , one that is prepared for real-time information, innumerable choices, quick decisions, and fast response. We’ve already seen the benefits of this in other industries. we file our taxes electronically, order books, clothes and even food online. We communicate around the world at nearly the speed of light via . But, we still generate and deliver electricity much the same way we have for over a century.
79
THANK YOU WELCOME TO HPSEB
Similar presentations
© 2025 SlidePlayer.com Inc.
All rights reserved.