Cryogenic Plant Electrical and Controls
Chris Scanlon LCLS-II Cryoplant General Contractor Installation Package Review June 1, 2017
2
Outline System Overview Deliverables Current Status Remaining Work
Completion Plan Available Resources Summary LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
3
System Overview Plant Purpose
Provide 2K liquid Helium to the linac while protecting personnel and equipment Cryoplant Controls Purpose Provide and install instrumentation and controls electronics in cryoplant Provide reliable plant automation, interlocks and alarms Provide local and remote monitoring and control At the heart of this control system are 19 Allen-Bradley ControlLogix 1756-L71 and L81 PLCs. LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
4
System Overview PLC Systems: Utility Gas Mgmt 4K CB 2K CB Warm Comps
LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
5
System Documentation Overview
Cryoplant Control System P&ID Covered Warm Helium Compressor LP Utility Warm Helium Compressor MP Warm Helium Compressor HP Gas Management 4K Cold Box 2K Cold Box LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
6
Deliverables Controls Electrical
6 total drawings submitted by JLab for the installation package Drawing objectives Defines power panel and field equipment locations Define testing requirements One line power wiring diagrams define cable types and quantity to submit to SG Defines JLab and GC supplied equipment Controls 68 total drawings submitted by JLab for the installation package Define enclosure and field equipment locations Define terminal to terminal wiring Interconnection diagrams defines cable types and quantity to submit to SG Define JLab and GC supplied equipment Review Reviews SG documentation developed into single GC installation package in CSI construction format coupled to an electrical subsection for final review LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
7
Electrical Deliverables
Electrical Single Line Diagrams Used by SG to build cable list Used by GC to generally understand AC connections between equipment Cable designator Wire gauge Voltage Current Conduit type LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
8
Controls Deliverables
Controls Assembly Drawings Used by SG to determine termination elevation and cable length Used by GC to determine location of cable terminations LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
9
Controls Deliverables
Controls Wiring Drawings Used by SG to build cable lists Used by SG to identify channels and instrument types Used by GC to identify per conductor wiring of cables LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
10
Electrical and Controls Deliverables
Electrical Interconnect Diagrams Used by SG to build controls cable list Used by GC to understand AC connections between control equipment Cable designator Wire gauge Cable type LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
11
Total Number of Drawings for Completion 100% Complete 99% Complete
Current Status Total Number of Drawings for Completion 74 Drawings 100% Complete 4 Drawings 99% Complete 66 Drawings 95% Complete 1 Drawings <95% Complete 3 Drawings LCLS-II Cryo Controls Integration Workshop, February 1, 2017
12
Drawing completion progresses in parallel
Remaining Work Drawing completion progresses in parallel Specific tasks to be completed are Add installation scope labels to controls enclosure and wiring drawings Add CAPTAR labels (cable numbers) to controls interconnect drawings Complete electrical interconnect diagrams LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
13
Available staff to complete the work
Completion Plan Available staff to complete the work EE – 4.25 FTEs ED – 1 FTE Remaining work is well defined Add installation scope labels to controls enclosure and wiring drawings Add CAPTAR labels (cable numbers) to controls interconnect drawings Complete electrical interconnect diagrams LCLS-II Cryo Controls Integration Workshop, February 1, 2017
14
Completion Plan Over the last week the work has advanced 45% of the remaining effort LCLS-II Cryo Controls Integration Workshop, February 1, 2017
15
JLab’s Electrical and Controls scope is well understood
Summary JLab’s Electrical and Controls scope is well understood The documentation is being prepared in sufficient detail for incorporation into an installation package Sufficient staff is on hand to complete the work Over the last week the work as advanced 40% of the remaining effort Expect the remaining 60% to be completed by June 15th LCLS-II Cryo Controls Integration Workshop, February 1, 2017
16
Backup LCLS-II Cryo Controls Integration Workshop, February 8, 2017
17
Ritendra Bhattacharya, Process Engineer, JLab 90%
Available Resources Ritendra Bhattacharya, Process Engineer, JLab 90% Antonio de Lira, Electrical Engineer, SLAC, 100% Boris Ilinets, Electrical Engineer, SLAC, 50% Tim McCool, Electrical Designer, JLab, 100% Robert Norton, Electrical Engineer, JLab, 10% Chris Scanlon, Electrical Engineer, JLab, 100% Swapnil Shrishrimal, Electrical Engineer, JLab, 75% LCLS-II Cryo Controls Integration Workshop, February 1, 2017
18
Deliverables LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
19
Deliverables LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
20
Deliverables LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
21
Add CAPTAR labels (cable numbers) to controls interconnect drawings
Remaining Work Add installation scope labels to controls enclosure and wiring drawings Add CAPTAR labels (cable numbers) to controls interconnect drawings Complete electrical interconnect diagrams LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
22
Deliverables JLab and SLAC give specification input to SG
Termination type Test criteria Pull test Continuity check High potential test JLab and SLAC review SG produced drawings and specifications during development and provide feedback LCLS-II Cryoplant General Contractor Installation Package Review, June 1, 2017
23
Release drawings – upon completion (de Lira, McCool, Norton, Scanlon)
Completion Plan Add installation scope to controls enclosure and wiring drawings - June 1 (McCool) Fill in CAPTAR labels (cable numbers) on electrical interconnect drawings - June 2-7 (Bhattacharya, de Lira, McCool, Scanlon, Shrishrimal) Release drawings – upon completion (de Lira, McCool, Norton, Scanlon) LCLS-II Cryo Controls Integration Workshop, February 1, 2017