PROPOSAL FOR NEW AIRSPACE DESIGN
OUTCOME OF PBN IMPLEMENTATION – STAKEHOLDERS CONSULTATION MEETING ULAANBAATAR 2015 PROPOSAL FOR NEW AIRSPACE DESIGN Gangerel.B PBN IMPLEMENTATION WORKING GROUP
2
Civil Aviation Authority of Mongolia
CONTENT NAV SPECIFICATION Assumptions Fleet capability Navigation specification ROUTE STRUCTURE Design Benefit SECTORISATION IMPLEMENTATION PLAN
3
NAV SPECIFICATION
4
Civil Aviation Authority of Mongolia
KEY ASSUMPTIONS VOR/DME coverage partial-RNAV5 DME/DME coverage partial-RNAV2, RNAV 5 7 MSSR operational (above 6150m /FL200) almost 100% without western area; 10 ADS-B(more) installed, not integrated, not mandated; 5more to be installed in ; 100% VHF coverage above 6150m/FL200 Entry/Exit points Current planning: Same existing Entry/Exit Future: Possible new Entry/Exit No special use airspace constraint
5
Civil Aviation Authority of Mongolia
FLIGHT STATISTICS Type of flights RNAV Ref: ATFM survey 2013
6
Civil Aviation Authority of Mongolia
AIRLINES Co-operated with:161 airliners of 45 countries. Ref: ATFM survey 2013
7
Civil Aviation Authority of Mongolia
TYPE OF AIRCRAFT Ref: ATFM survey 2013
8
Civil Aviation Authority of Mongolia
NAV SPECIFICATION International Routes (At or above RVSM LevelsFL ) RNAV 10 No RADAR Surveillance VHF DCPC 95km (50NM) Separation RNAV 5 RADAR Surveillance Surveillance Based Separation Domestic Routes (Below RVSM Levels) Conventional
9
ROUTE STRUCTURE
10
OVERFLIGHT TRAFFIC DISTRIBUTION ON EXISTING AIR ROUTES
Civil Aviation Authority of Mongolia OVERFLIGHT TRAFFIC DISTRIBUTION ON EXISTING AIR ROUTES MORIT GINOM DARNO BAMUK NIGOR LETBI AMUTA SERNA SULOK INTIK POLHO NIXAL NOPUS TEBUS 13.2% 22.1% 2.1% 5.4% 7.6% 1.2% 9.3% 0.3% 1.1% 28.3% 8.1%
11
Civil Aviation Authority of Mongolia
ROUTE STRUCTURE GINOM DARNO BAMUK NIGOR LETBI AMUTA SERNA SULOK INTIK POLHO NIXAL MORIT NOPUS TEBUS 13.2% 22.1% 5.4% 1.2% 9.3% 1.1% 28.3% 8.1% RNAV5 RNAV5- Crossing RNAV10 (95KM/VHF DCPC)
12
EXPECTED IMPROVEMENTS
Civil Aviation Authority of Mongolia EXPECTED IMPROVEMENTS № CURRENT ROUTES PERCENTAGE OF TRAFFIC BENEFIT 1 NIXAL DARNO 28.3 4KM 2 SERNA POLHO 22.1 1KM 3 GINOM NTIK 13.2 5KM 4 NIGOR MORIT 9.3 5 INTIK DARNO 7.6 7KM 6 INTIK AMUTA 8.1 26KM 7 SULOK POLHO 5.4 0KM 8 GINOM POLHO 2.1 -1KM 9 NIGOR NIXAL 1.2 28KM 10 POLHO DARNO 1.1
13
Civil Aviation Authority of Mongolia
FIRST PHASE GINOM DARNO BAMUK NIGOR LETBI AMUTA SERNA SULOK INTIK POLHO NIXAL MORIT NOPUS TEBUS 13.2% 22.1% 5.4% 1.2% 9.3% 1.1% 28.3% 8.1% RNAV5 RNAV5- Crossing RNAV10 (95KM/VHF DCPC)
14
SECTORISATION
15
SECTORISATION Due Facility Limitations, only 5 Sectors are possible
Current 5 Sectors will be maintained during Phase 1 5 sectors: Altai (Non-surveillance) Central Dornod Muren Gobi
16
Civil Aviation Authority of Mongolia
SECTORISATION GINOM DARNO BAMUK NIGOR LETBI AMUTA SERNA SULOK INTIK POLHO NIXAL MORIT NOPUS TEBUS 13.2% 22.1% 5.4% 1.2% 9.3% 1.1% 28.3% 8.1% RNAV5 RNAV5- Crossing RNAV10 (95KM/VHF DCPC)
17
IMPLEMENTATION PLAN
18
Civil Aviation Authority of Mongolia
DETAILED IMPLEMENTATION PLAN En-route PBN Implementation Working Group set up Developed with assistance of RSO Plan officially Approved by DG of CAAM First Phase: Planned Effective on AIRAC Sep 2015
19
Civil Aviation Authority of Mongolia
ACTION PLAN VALIDATE AIRSPACE CONCEPT CONTROLLER TRAINING OBTAIN MINISTRY APPROVAL FOR NEW ENROUTE STRUCTURE Important for planned effective date
20
Thank you for your attention Questions?