Chair : Hon’ble Secretary Secretary / Chief Executive Officer (CEO)
Annual Action Plan :: IWMP IMPLEMENTATION March 20, 2014 Chair : Hon’ble Secretary Department of Land Resources Government of India :: PRESENTED BY :: Secretary / Chief Executive Officer (CEO) Department of Land Development & Water Resources Government of Uttar Pradesh
2
Funds Received[Central+State] Projects closed / cancellation
Summary of IWMP Particulars Year of Appraisal Total Batch – I Batch – II Batch – III Batch – IV Batch – V [Rs. in cr.] No. of projects 66 183 158 64 67 538 Project Area 349982 890682 763594 318018 328086 Project Cost 419.97 916.31 381.62 399.68 Funds Received[Central+State] 227.85 283.29 61.96 24.55 -- 597.65 Total Expenditure 181.71 221.72 43.77 10.33 457.53 DPRs sanctioned 37 286 Projects closed / cancellation 16 Timeline for DPRs N/A Aug' 14 Dec' 14 Fund not released
3
IWMP – Abstract of Fund Requirement by SLNA during 2014-15
[Rs. in cr.] Sl. No. Item I st Quarter II nd Quarter III rd Quarter IV th Quarter Total Unspent Balance as on Actual requirement (7-8) 1 2 3 4 5 6 7 8 9 Batch-I 36.09 27.19 25.10 23.90 112.28 46.14 66.14 (Sanctioned in ) Batch-II 119.35 83.93 141.00 140.34 484.62 61.57 423.05 (Sanctioned in ) Batch-III 33.10 27.53 40.61 38.24 139.48 18.19 121.29 (Sanctioned in ) Batch-IV 22.28 13.96 14.86 14.90 65.99 14.23 51.76 (Sanctioned in ) Batch-V 20.40 18.25 19.90 20.20 78.75 0.00 (Sanctioned in ) Batch-VI 6.00 5.04 23.04 (To be Sanctioned in ) 237.22 175.90 247.46 243.58 904.16 140.13 764.03
4
IWMP - Monthly proposed expenditure during 2014-15
S.No. Month Proposed Expenditure (Rs. In Cr.) 1 April 79.07 2 May 3 June 4 July 58.63 5 August 6 September 7 October 82.49 8 November 9 December 10 January 81.19 11 February 12 March Total 904.16
5
IWMP-Fund Requirement for year 2014-15
Batch-I (Project Sanctioned in ) [Rs. in cr.] Sr.No. Budget Component Total fund received Total expenditure % Expenditure Fund Required for year Remarks (Timelines etc.) ( ) 1 DPR 4.20 3.72 89% 0.00 2 EPA 16.80 100% 3 I & CB 15.70 10.98 70% 3.20 4 Administrative cost 22.34 15.90 71% 8.74 5 Watershed Works 136.58 117.87 86% 30.78 6 Livelihood activities 14.67 7.37 50% 10.53 7 PS & ME 7.82 53% 8 Monitoring 1.51 0.85 56% 1.01 9 Evaluation 1.38 0.40 29% 1.35 10 Consolidation Phase 0% Total 227.85 181.71 80% 66.14
6
IWMP-Fund Requirement for year 2014-15
Batch-II (Project Sanctioned in ) [Rs. in cr.] Sr.No. Budget Component Total fund received Total expenditure % Expenditure Fund Required for year Remarks (Timelines etc.) ( ) 1 DPR 10.69 9.30 87% 0.00 2 EPA 42.75 41.90 98% 3 I & CB 34.06 18.13 53% 11.14 4 Administrative cost 28.89 21.21 73% 45.44 5 Watershed Works 125.21 108.76 275.06 6 Livelihood activities 17.65 9.69 55% 42.62 7 PS & ME 9.85 56% 8 Monitoring 2.70 1.12 41% 3.33 9 Evaluation 3.69 1.76 48% 2.84 10 Consolidation Phase 0% Total 283.29 221.72 78% 423.05
7
IWMP-Fund Requirement for year 2014-15
Batch-III (Project Sanctioned in ) [Rs. in cr.] Sr.No. Budget Component Total fund received Total expenditure % Expenditure Fund Required for year Remarks (Timelines etc.) ( ) 1 DPR 10.32 6.46 63% 0.00 2 EPA 41.31 31.35 76% 3 I & CB 5.16 2.60 50% 22.33 4 Administrative cost 5.17 3.36 65% 13.16 5 Watershed Works 0% 74.54 6 Livelihood activities 9.16 7 PS & ME 8 Monitoring 1.83 9 Evaluation 2.75 10 Consolidation Phase Total 61.96 43.77 71% 121.29
8
IWMP-Fund Requirement for year 2014-15
Batch-IV (Project Sanctioned in ) [Rs. in cr.] Sr.No. Budget Component Total fund received Total expenditure % Expenditure Fund Required for year Remarks (Timelines etc.) ( ) 1 DPR 3.81 1.98 52% 0.00 2 EPA 15.26 6.55 43% 3 I & CB 2.20 0.70 32% 9.25 4 Administrative cost 2.08 1.10 53% 5.55 5 Watershed Works 0.90 0% 27.72 6 Livelihood activities 0.12 3.70 7 PS & ME 8 Monitoring 0.02 0.74 9 Evaluation 0.04 10 Consolidation Phase Total 24.55 10.33 42% 51.76
9
IWMP-Fund Requirement for year 2014-15
Batch-V (Project Sanctioned in ) [Rs. in cr.] Sr.No. Budget Component Fund Required for year Remarks (Timelines etc.) 1 DPR 3.94 March 2 EPA 15.75 3 I & CB 11.81 4 Administrative cost 7.87 5 Watershed Works 29.53 6 Livelihood activities 7 PS & ME 8 Monitoring 0.79 June 9 Evaluation 1.18 10 Consolidation Phase 0.00 Total 78.75
10
IWMP-Fund Requirement for year 2014-15
Batch-VI (Project to be Sanctioned in ) [Rs. in cr.] Sr.No. Budget Component Fund Required for year Remarks (Timelines etc.) 1 DPR 3.84 March 2 EPA 15.36 3 I & CB 1.92 4 Administrative cost 5 Watershed Works 0.00 6 Livelihood activities 7 PS & ME 8 Monitoring 9 Evaluation 10 Consolidation Phase Total 23.04
11
CB Plan to be submitted for approval in coming SLNA meeting.
Capacity Building Capacity Building Plan for all levels of stakeholders have been prepared . CB Plan to be submitted for approval in coming SLNA meeting. CB Plan will be uploaded after approval of SLNA . Training modules for all levels of stakeholders have been prepared .
12
Capacity Building Training Modules have been Prepared in local language-Hindi and to be put-up for approval in Coming SLNA Meeting . Training module will be uploaded after approval of SLNA. Preparation of training calendar for is under process. The total budget required for Capacity Building during is Rs Cr.
13
Proposed Capacity Building Plan for 2014-15
No. of persons proposed to be trained during Rs. in cr. Level of stakeholder No. of Training No. of Beneficiaries trained Subject of Training program Name of Training Institute Proposed Expenditure SLNA level 12 30 Planning of water shed Project, Project appraisal skill , GIS based web Monitoring & Evaluation, Livelihood and PSME Planning, and monitoring . MANAGE,CAZARI,NIRD,IIRS, NRAC, ICRISET, NABARD 0.20 District level 280 1700 Refresher on paradigm of IWMP, Awareness generation technique, Basic principle of DPR Preparation, NRM, convergence with diff. deptt. Programme, Participatory planning process tools and its applications, SHG-federation formation and Bank linkages. NIRD, MANAGE, ICRISET, IIRS, IGFRI, SIRD, RIRD, State Agriculture universities , NRCAF, BHU, IVRI, NABARD 14.00 WDT level 375 1500 Participatory planning process tools and its applications, NRM, Community mobilization technique, LA, PS & ME, Benefit sharing, Gender equity issue , WC,UG/SHG- federation formation, etc. WALMI, DIRD, RIRD, NABARD, NIRD, IVRI, SIMA, BHU, etc. 11.25 WC level (Village) 11000 780000 NRM, Community motivation and mobilization, Livelihood , PS & ME, Basics of records and financial mgt, Benefit sharing, , Revolving fund utilization ,WDF mgt. Gender equity issue , WC,UG/SHG- federation formation, Trade wise skill based training- Food processing etc. Polytechnic, ITI, U.P.L.D.W.R.- Belikala, WALMI, DIRD, Horticulture, Animal Husbandry, Food processing, deptt. RIRD, NABARD, Khadi Gramodyog , Udyamita vikash Sansthan etc. 46.80 Exposer Visit [ All Level ] / IEC Material / seminar / Workshop 9.75 Total 11667 783230 82.00
14
IMPLEMENTATION STRATEGY FOR PROJECTS PROPOSED FOR 2014-15
Area allocated for (lakh ha.) 320000 2 No. of Projects 64 3 No. of Districts 45 4 Timeline for completing the initial capacity building March 5 Timeline for completion of DPRs 6 Completion of EPW 7 Completion of WCs Aug 8 Training of WCs March
15
IWMP-Financial Targets for 2014-15
Name of the State:- UTTAR PRADESH [Rs. in cr.] Sr.No. Components Fund Released up to previous year ( ) Expenditure up to previous year ( ) Unspent Balance as on ( ) Annual Target for Total ( ) Actual Requirement of grant Ist Quarter IInd Quarter IIIrd Quarter IVth Quarter 1 2 3 4 5 7 8 9 10 11 12 Administrative Cost 58.48 41.57 16.91 14.36 19.34 32.95 32.94 99.59 82.68 Monitoring 4.23 1.97 2.26 2.66 2.40 2.45 9.96 7.70 Evaluation 5.11 2.16 2.95 2.00 2.60 4.62 12.17 9.22 Entry Point Activity (EPA) 116.12 96.60 19.52 18.70 9.07 9.10 45.97 26.45 Institution & Capacity Building 57.12 32.41 24.71 20.00 14.13 27.66 22.57 84.36 59.65 6 Detailed Project Report (DPR) 29.02 21.46 7.56 7.57 2.12 2.25 14.19 6.63 NRM Work (Total) 262.69 226.63 36.06 154.00 91.77 100.95 121.15 467.87 431.81 Livelihood for the asset-less persons 32.44 17.06 15.38 9.19 30.14 27.30 85.33 69.95 Production System &Micro-enterprises 17.67 14.77 8.74 15.78 39.01 21.20 84.72 Consolidation Phase 0.00 Total:- 597.65 457.53 140.12 237.22 175.90 247.46 243.58 904.16 764.04
16
Status of Evaluation of Preparatory Phase of IWMP
Sl.No. Items For Projects sanctioned in For Projects sanctioned in 1 Status of empanelment of Evaluating Agencies Evaluating Agencies are empanelled Only 6% fund released sofar. Evaluation begins after receiving 20% funds and its 60% utilization. 2 Status of Evaluation of Preparatory Phase (completed/ on-going/ not done) completed -- 3 If evaluation not done then timeline for completion. -- 4 If completed then status of submission of Evaluation Report along with ATR to DoLR. (Submitted/ not Submitted) Submitted out of 183 Projects evaluation report , executive summary along with ATR of 170 Projects were submitted. Rest 13 Projects evaluation reports are received in SLNA. 5 If not submitted, then time line for submission of evaluation report along with ATR -- Remaining 13 Projects executive summery along with ATR will be submitted before March
17
Status of Evaluation of Works Phase of IWMP
S. No. Items For Projects Sanctioned in For Projects Sanctioned in 1 Status of empanelment of Evaluating Agencies Evaluating Agencies are not empanelled 2 Status of Evaluation of work Phase ( completed/on-going/not done) Not done 3 If Evaluation not done then timeline for completion. March, 2015 June, 2015 4 If completed then status of submission of Evaluation report along with ATR to DoLR (Submitted/not submitted) N/A N/A 5 If not Submitted, then time line for report submission along with ATR September, 2015
18
Status of engagement of Agencies for Concurrent Monitoring and Evaluation of IWMP
S. No. Items Remarks 1 Date of Advertisement Under Process 2 Status of selection of Agencies 3 If not done then timeline for completion. June -2014 4 If completed then status of submission of Report along with ATR to DoLR. ( Submitted/not submitted) -- 5 If not Submitted, then time line report submission along with ATR