Options to address fish barriers

Similar presentations


Presentation on theme: "Options to address fish barriers"— Presentation transcript:

1 Options to address fish barriers
Anthony Watkins & Jenny Davies June 2017

2 Asset barriers These structures are part of a key piece of infrastructure such as; Culverts Bridge Aprons/ pre weirs They serve a purpose and so cannot be removed, but they can usually be adapted.

3 Options to adapt structures
Baffles Pre weirs Rock ramps Technical fish pass By-pass channels

4 Baffles

5 Baffles

6 Pre weirs

7 Pre weirs

8 Pre weirs – rock

9 Rock ramp

10 Technical fish pass

11 By-pass channel

12 £££ Finances £££ There is no additional funding for asset barriers but SEPA staff will provide technical support. Disproportionate cost and technical feasibility will be considered. Historic barriers that are owned by a responsible authority are eligible for 75% funding from Scottish Government and will be supported by SEPA staff. Objectives are phased, 2021 and 2027, to help schedule resources.

13 Asset management plans
10 year plan with each local authority to deliver the RBMP objectives Developed in partnership Will take in to account the existing local authority management plans The plans will be supported by a statutory notice – a remedial notice.

14 Remedial notices New legislation - The Water Environment (Remedial Measures) (Scotland) Regulations 2016 Give SEPA the power to serve, vary or revoke a remedial measures notice on a responsible authority These notices require improvement work to be carried out to meet an RBMP objective. Will be drafted with partner organisations to set agreed timescales. Potentially could be used as an enforcement tool in exceptional circumstances.

15 Licensing requirements
The Water Environment (Controlled Activities) (Scotland) Regulations 2015 These regulations cover all work in the water environment. Upgrading structures to allow fish passage is seen as environmental improvement so these licenses are free. Responsible Person should be the persons doing the work.

16 Partnership approach We appreciate that public sector has huge resource pressures. We will help by providing technical support throughout the process We will help to find low cost, simple solutions where possible.

17 Summary We want to work with you to find the most straight forward solution. Although we cannot fund improvements we will provide technical support. Remedial notice will formalise agreement to deliver works and help secure funding.