1 Construction Report March 24, 2009

2

3 Projects KMS Phase I Completed KMS Phase II Close out
KMS Cafeteria Close out KMS Renovations & Additions Close out Royalwood Elementary Close out Monahan Elementary Close out KHS Cafeteria Close out KHS Annex Close out

4 Projects TAC Performance Contract Close Out
Diamond Sports Project Close Out Covered PE areas Completed Maintenance / Transportation Complex Design

5 Projects Sheldon ECA On schedule Carroll Elementary Close Out
M. R. Null Middle School On schedule

6 C. E. King Middle School

7 C. E. King Middle School

8 H. M. Carroll Elementary

9

10 Monahan Elementary School

11 Monahan Elementary School

12 Monahan Elementary Library

13 Utilities Project (TAC)
Savings Report Guaranteed Annual Savings $ ,097.00 Total Energy Cost Savings through December $ 2, Guaranteed Energy Cost Savings through Dec $ 877,605.00

14 Michael R. Null Middle School
Project Started January 2008 Estimated Completion August 2009

15

16 Michael R. Null Middle School

17 Michael R. Null Middle School

18

19

20

21

22

23 Royalwood Elementary School

24 C. E. King High School

25 C. E. King High School Annex

26 Sheldon Early Childhood Academy

27 Sheldon Early Childhood Academy

28

29

30

31 Maintenance Operations / Transportation Complex (MOT)
Property purchased Programming resumed/completed Surveys Design development Utility Service

32 District Projects Air Balance Sheldon Elementary ECA
Carroll Elementary KHS Annex KHS two story Monahan Elementary Royalwood Elementary C. E. King Middle School

33 Summer Projects Asbestos Track Carpet Paving / parking / drainage

34 District Projects Fence / gates Science Classrooms / lab
Auditorium lighting Sports Fields

35 Summer Projects Covered PE areas Walking tracks Water wells Technology
-Servers -LCDs -Computers -Audio Enhancement -Cameras -Virtualization