Presentation is loading. Please wait.

Presentation is loading. Please wait.

“Other” Cost Estimates

Similar presentations


Presentation on theme: "“Other” Cost Estimates"— Presentation transcript:

1 “Other” Cost Estimates
Stan Hadley SSC Meeting December 3, 2012

2 Other Cost Categories Costs not reported in MAPS
Annual costs, values are for 2030 only Energy Efficiency Demand Response Variable Resource Integration Thermal Contingency Factors Fixed O&M Capital Costs, Overnight costs through 2030 All costs in 2010 $

3 Phase 2 Part 5 Final Draft Page 41

4 Energy Efficiency Supply curves based on McKinsey and Ga Tech studies
Scenario 3 (Future 1 or BAU in Phase 1) includes existing EE policies 2030 cost $0.8 to $2.1 billion Future 2 in Phase 1 includes BAU EE plus CO2 cost Assume demand reduction from demand substitution by using EE 2030 cost $5.7 to $17.2 billion CO2-alone cost = $4.9 to $15.1 billion Scenario 1 (Future 8) has incremental EE policies Reduce demand growth rate by an additional 1%/year 2030 cost $11.3 to $26.6 billion, includes CO2 Scenario 1 non-CO2 EE cost = $6.4 to $11.5 billion

5 Energy Efficiency Supply Curves

6 Demand Response: Cost versus Price
Phase 1:FERC-developed National Assessment of Demand Response (NADR) model for total Price in model used $750/MWh Cost using early estimate of equipment Phase 2: Updated assumptions Create tiered price curve for models Expand and update equipment costs

7 Demand Response Price Curve
6-Block Supply Curve and Model Curve with Allocated Non-Pricing DR in 2030

8 Communications Network Deployment Management
DR Cost Estimates Estimated Cost-per-Meter of Various AMI System Component ($) Scenario Meters IT Systems Communications Network Deployment Management Annualized AMI O&M High 243 65 66 81 23 Medium 190 27 43 63 7 Low 129 11 28 4 2030 Costs include ongoing O&M S1 = $604 million S2, S3 = $323 million 2030 AMI capital equipment cost S1 = $148 million S2, S3 = $87 million

9 Variable Energy Resource Integration Estimated Cost for 2030
Estimated Wind Integration Costs (2010$) Low Range (-50%) Medium High Range (+75%) $1.95/MWh $3.91/MWh $6.83/MWh Assumptions EWITS Scenario 4 served as starting point - $5.13/MWh (2009$) Gas price adjustment to capture the difference of EWITS and EIPC natural gas forecasts Scenario TWh Low Medium High S1 733 $1.4 B $2.9 B $5.0 B S2 568 $1.3 B $2.5 B $4.4 B S3 223 $0.5 B $1.0 B $1.8 B

10 Thermal Contingency Reserves
$2/MWh * (Coal + Nuclear + Combined Cycle) Estimated Contingency Cost in 2030 (Billions 2010$) S1 S2 S3 1,881 TWh 2,494 TWh 3,107 TWh $3.8 $5.0 $6.2 Assumptions A 2003 study, Allocating Costs of Ancillary Services: Contingency Reserves and Regulation, suggests that costs of contingency reserves to accommodate the loss of the largest unit increases the operating costs and recommends a method that allocates based on its size and forced outages to incentivize generators to maintain their units.

11 Fixed O&M Costs Not calculated in GE MAPS Take from relevant NEEM case
Value is for the EI in 2030 Scenario NEEM Case O&M in 2030 S1 F8S7 $34.7 Billion S2 F6S10 $52.1 Billion S3 F1S17 $48.1 Billion

12 Estimated Nuclear Uprate Costs
Future Uprated Capacity Costs (Billions 2010$) All three Scenarios 1,538 MW $4.9 Assumptions $2,600/kW Costs occur before 2030

13 Estimated Distributed Generation Costs
2x Distributed Generation in BAU Assumed all behind-the-meter PV Assumed weighted average of the 2-5 kW and 5-10 kW, $8,045/kW (2010$) The estimated capital cost of the renewable distributed generation added during is $83.4B.


Download ppt "“Other” Cost Estimates"

Similar presentations


Ads by Google