Presentation is loading. Please wait.

Presentation is loading. Please wait.

by Awad S. Hanna, Ph. D., P. E. The University of Wisconsin, Madison

Similar presentations


Presentation on theme: "by Awad S. Hanna, Ph. D., P. E. The University of Wisconsin, Madison"— Presentation transcript:

1 Single Source PROJECT DELIVERY SYSTEMS: Engineer/Procure/Construct and Design-Build
by Awad S. Hanna, Ph. D., P. E. The University of Wisconsin, Madison Department of Civil and Environmental Engineering Construction Engineering and Management Program Prof Awad S. Hanna Prof Awad Hanna

2 Single Source Project Delivery System
Outlines: Introduction and definition of terms Advantages and disadvantages to owners and contractors Importance of involving major specialty contractors and vendor up front in the project development Required conceptual designs and assemblies cost data Value engineering studies Prequlaification, proposal evaluation, and insurance and bonding Prof Awad S. Hanna

3 Traditional Method (Design_then _Build)
Also known as design_bid_build or hard money or competitive bid contract. Has three sequential phase design - bid - construction. Architect-Engineer hired Architect- Engineer hired Bid/Award Design Phase Construction Phase Single Construction Contract Prof Awad S. Hanna Prof Awad Hanna

4 Traditional Organization
Owner A/E General Contractor Sub Contractor Sub Contractor Sub Contractor Sub Contractor Sub Contractor The owner contracts separately with designer and a contractor Prof Awad S. Hanna Prof Awad Hanna

5 Estimating Needs for Design-Bid-Build
Complete set of drawings Specification Other contract documents General conditions Special conditions Addenda Others (soil report) Prof Awad S. Hanna Prof Awad Hanna

6 Single Source Delivery
1. Design Build 2.Engineer/Procure/Construct (EPC) EPC model#1 ( CM agency “pure” ) EPC model#2 ( CM at Risk ) Other Multiple prime contractors Owner design construct Integrated teams or strategic alliance Design-Build-Finance and Design-Build-Develop Prof Awad S. Hanna Prof Awad Hanna

7 Fast Track or Phased Construction Method
CM and A/E or DB hired Concepts Working Drawing Design Phase Construction Phase Variable separate construction contracts Prof Awad S. Hanna Prof Awad Hanna

8 Level of Influence Time Project Cost Influence Ability to Influence
Prof Awad S. Hanna Prof Awad Hanna

9 1. Design Build Owner Design-build entity Own force Subcontractors
work Single firm performs both design and construction under single design-build contract. Prof Awad S. Hanna Prof Awad Hanna

10 Advantages of Design & Build for Owners
Owner only has to communicate with one entity for the entire project Total project duration can be reduced because phased construction is easier to implement,(Fast tracking) Integration of construction planning and design phases Claims reduction (reduction of adversary relationships) Innovation in design and construction can be encouraged Risk assigned to party best able to manage that risk Prof Awad S. Hanna Prof Awad Hanna

11 Disadvantages of DB for Owners
Fewer checks and balances, owner must rely on integrity of the design-build firm All your eggs in one basket Prof Awad S. Hanna Prof Awad Hanna

12 Advantages to a design-build organization
Improved constructibility through design/construction integration A specialized organization can be developed that has a specific expertise which will be attractive to specific market areas Reduction of negligence claims between the Architect/Engineer and the construction contractor since they are under one umbrella firm Ability to react rapidly to change in scope Prof Awad S. Hanna Prof Awad Hanna

13 Disadvantages for the design-build firm
Acceptance of additional project risk Scope of work changes can be difficult to identify under DB/ fast track construction Prof Awad S. Hanna Prof Awad Hanna

14 Summary of average differences between project delivery systems (CII-133)
Prof Awad S. Hanna

15 Importance of Involving Specialty Contractors up front in the Project Development
Specialty works represent 60% to 70% of the project cost Specialty works control the pace of construction Integration of electrical and mechanical systems early in the design stage Specialty works are labor intensive (high risk for cost overrun) Prof Awad S. Hanna

16 2. Engineer/Procure/Construct Model#1 (EPC)
Pure CM (CM agency) Owner In-House Design or Engr. Firm CM Specialty Contractors and Vendor Specialty Contractors and Vendor Specialty Contractors and Vendor Specialty Contractors and Vendor EPC Model #1 Prof Awad S. Hanna Prof Awad Hanna

17 2. Engineer/Procure/Construct Model#2 (CM at Risk)
General Contractor acting as CM Owner Engineering/Procure Construct Specialty Contractors and Vendor Specialty Contractors and Vendor Specialty Contractors and Vendor Specialty Contractors and Vendor EPC Model #2 Prof Awad S. Hanna Prof Awad Hanna

18 Estimating Needs for Single Source Delivery
Conceptual Design General idea about the proposed quality Assemblies cost data Update your estimate as the design develops Value engineering studies Prof Awad S. Hanna Prof Awad Hanna

19 Value-Engineering Study
Prof Awad S. Hanna

20 Required Conceptual Design and Assembly Cost Data
Example of assembly cost data Prof Awad S. Hanna

21 Design-Build Issues 1. Prequalification
The reduction of the number of possible bidders to a small group of serious, qualified bidders improves the effectiveness of the selection process. Prof Awad S. Hanna Prof Awad Hanna

22 Design-Build Issues (cont.)
2. Proposal Evaluation Cost only Cost and time Multiparameter (quality, safety…etc.) Prof Awad S. Hanna Prof Awad Hanna

23 Design-Build Issues (cont.)
3. Legal a. Insurance and bonding The contractor should have the proper insurance to cover design deficiencies or cover construction errors. b. Conflict of interest Design-build eliminates the checks and balance of the traditional methods. Prof Awad S. Hanna Prof Awad Hanna

24 Critical Success Factors for Design-Build
Project team selection; Pre-qualification of contractors; Level of design complete prior to engaging construction team; Individual experience of team members with similar facility type; Individual experience of team members with the project delivery systems; Team’s prior experience as a unit; Project team communication; Owner type (public or private); Owner/project team relationship (first time, partnering or repeat); Owner’s ability to define the project scope; Project complexity; Prof Awad S. Hanna


Download ppt "by Awad S. Hanna, Ph. D., P. E. The University of Wisconsin, Madison"

Similar presentations


Ads by Google