Presentation is loading. Please wait.

Presentation is loading. Please wait.

The need for the scheme: congestion

Similar presentations


Presentation on theme: "The need for the scheme: congestion"— Presentation transcript:

1 A14 Integrated Delivery Benefits and Improvement Team Sally Coultas-Paul, Balfour Beatty

2 The need for the scheme: congestion
Unreliable journey times Economic cost of delays 85,000 vehicles per day 26% HGVs Route at 95% capacity 13,000 vehicles in peak am/pm

3 The need for the scheme: safety
Driver stress Incidents every other day Sub-standard road design Mix of local and strategic traffic Non-motorised road users

4 Safe & Serviceable Network
Scheme objectives Economic Growth Safe & Serviceable Network Free Flowing Network Improved Environment Accessible Network Unlocking growth Connecting people Building a legacy Improving safety Combatting congestion

5 Delivering the A14: sections

6 Delivering the A14: collaborative structure
Highways England Package Contract 1: Costain / Skanska Package Contract 2: Costain / Skanska Package Contract 3: Balfour Beatty / Carillion Designer Atkins / ch2m JV Integrated Delivery Team

7 Delivering the A14 Earthworks (off-line) Landmark structures (on-line)
3.4 million m3 of topsoil/subsoil to strip and replace 1.9 million m3 cut to fill plus 4.7million m3 of fill from borrow pits Landmark structures (on-line) Steel construction 80m high piers 180m clear span

8 Delivering the A14: legacy
Minimum targets: Employment and skills 3% apprentices 10% jobs created 7% NVQ starts 1% graduates employed SMEs 25% of spend tier 2 and below

9 A14 Benefits and Improvement team

10 Introduction To The Benefits Department
Benefits and Improvements Team - Sub-Departments: Benefits Improvements Lean Collaborative Performance Framework (CPF)

11 The Benefits Department’s Ultimate Aim
Measure and monitor progress across the project and where necessary – Implement action plans to improve a process Remove blockers Drive continuous improvement

12 The Team

13 Tools – Culture – Change

14 What is Lean to the A14? Lean is an approach
Lean is a way of thinking (Philosophy) Lean is a way of doing more with less Lean aims to come closer and closer to providing customer requirements At the heart of Lean is a flexible, motivated team members continuously solving problems

15 A14 Approach to Lean Lean - will form the basis of all improvement activities Learning by doing Analyse & Evaluate Challenge everything, no assumptions

16 A14 Lean Objectives Deploy Lean Construction to the highest standard
Deliver process improvements Embed Lean thinking throughout the team Support the collaborative team in achieving their aim Create Sustainable improvements Deliver significant quantifiable Benefits

17

18 A14 Current Lean Projects(Phase 2 – 1st Sept)

19 Collaborative Planning (The Last Planner System)

20 Collaborative Planning
Collaborative Planning (CP) brings together all our business work flows CP allows knowledge and experience to benefit the whole team

21 What does it look like?

22 Milestone Plan

23 Benefits of using the Last Planner System
Safer working Environment Reliability of Weekly Work Plans improve Productivity Plans Improve Encourages integration Critical issues are addressed

24 Lean Visual Management
VM creates a pro-active work environment VM applies to all levels in the business VM aligns the management routines for effective communication

25 Daily Implementation Meet once a day, around a visual board to understand progress in accordance to the plan

26 Weekly Work Plan & PPC

27 Planned Percentage Complete (PPC)
Using PPC ensures effective planning Aims to complete all the works planned A score of above 70% PPC is generally accepted as the break even point for meeting budgets

28 Efficiency Process on the A14
Paper copy Survey Monkey QR Code Benefits Register tracker Online Benefits Register Knowledge Share Lessons Learnt Weekly/Monthly Reports

29 A14 Efficiency Register Efficiency Targets
Year 1(April 2015-April 2016): £1,000,000 (Completed) Year 2(April 2016-April 2017): £16,000,000 Year 3(April 2017-April 2018): £32,000,000 Year 4(April 2018-April 2019): £74,000,000 Year 5(April 2019-April 2020): £109,000,000 Efficiency Register is updated on a monthly basis, checked by quality assurance and sent to HE

30 Questions Sally Coultas-Paul, Balfour Beatty


Download ppt "The need for the scheme: congestion"

Similar presentations


Ads by Google