Stage 2 Light Rail Transit Program “In the ground ready”

Similar presentations


Presentation on theme: "Stage 2 Light Rail Transit Program “In the ground ready”"— Presentation transcript:

1 Stage 2 Light Rail Transit Program “In the ground ready”
National Capital Heavy Construction Association January 12, 2017 John Manconi General Manager City of Ottawa Transportation Services Department

2 Agenda Background Project overview Bundled Projects Funding Status
Procurement overview Next Steps Questions

3 2013 Transportation Master Plan
The Vision City of Ottawa 2013 Transportation Master Plan 2031 Affordable Network Existing/Committed Rail Future Rail

4 24,000 person-years of employment
Benefits $10.8B less in commuting costs 14,000 less vehicles $3.8B Economic Impact 24,000 person-years of employment GHG Reductions: 155,000 tonnes 70% of City’s population within 5 km of rail

5 Background December 2012 – Confederation Line Contract Awarded
November 2013 – Transportation Master Plan February 2014 – Statements of work for Stage 2 Environmental Assessment studies July 2015 – Stage 2 Light Rail Transit (LRT) Environmental Assessment and Functional Design

6 The Confederation Line

7 Stage 2 LRT Project

8 Project Scope Budget: $3 billion Schedule: Scope:
Construction begins in 2018 Service operation begins in 2023 Scope: 36 kms of new track and 22 new stations, including: Trim Extension ($165M) Airport Rail Link ($155M) Maintenance and Storage Facilities Vehicles

9 Confederation Line West

10 Confederation Line West Dominion Station

11 Confederation Line West New Orchard Station

12 Confederation Line West Queensview Station

13 Confederation Line East

14 Confederation Line East Place D’Orléans Station

15 Trillium Line South

16 Bundled Projects City infrastructure projects
Road, sewer, structure (bridges, culverts) works Province’s Hwy 417 Expansion project Benefits: Capitalizes on economies of scale Eliminates risks Lessons learned from Confederation Line Bundle during procurement period

17 Funding Status 1/3 funding – City/Province/Feds
June 2016 – Ontario Government announced 1/3 funding, plus 50% funding for Trim and Airport Federal Government supported Stage 2 in 2016 Budget $45 million from Public Transit Infrastructure Fund for Stage 2 preliminary engineering activities

18 Procurement Overview Seeking Public Private Partnership (P3) model used for Confederation Line Market survey and analysis on procurement options Procurement model to City Council early 2018

19 Next Steps Q1 2017 – Stage 2 LRT Implementation Report to Council
Q – Release Request for Qualification (RFQ) Q – Release Request for Proposal (RFP) Q – Stage 2 LRT Contract Approval by Council Q – Construction Q – Revenue Service

20 Questions? www.stage2lrt.ca